Cover matl. aggr. no. 78, VDOT 312SD20-0005

Low bidders on VDOT contracts carried a median of $150.00 per TON for this item, over the 24 months to 28 OCT 2026, across 3 low bids. Half of all 7 bids fell between $98.15 and $142.50.

Owner
Virginia DOT
Item
312SD20-0005
Unit
TON
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 10478 on lettings from 26 MAR 2002 to 18 DEC 2019 (389 bids); 312SD20-0005 on lettings from 22 OCT 2025 to 17 DEC 2025 (8 bids). They are combined here into one trend.

$150.00Low bidder's median, per TON
$109.18Median of all bids, per TON
3Contracts in the window

By year of letting

Cover matl. aggr. no. 78, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20021818$28.8051$26.40
20032424$26.0066$25.35
20042626$31.2965$32.49
20051717$32.0037$32.75
20061818$36.0046$36.75
200788$33.7520$33.69
200899$33.2525$36.10
200955$29.0015$42.00
201077$31.0020$32.00
201122$38.106$37.50
201233$44.659$44.65
201344$32.9512$35.32
201411$44.103$42.00
201522$148.406$79.28
201611$70.003$60.00
201922$78.795$67.43
202533$150.007$109.18

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Lynchburg55$28.00154$29.66
Staunton45$33.50117$34.00
Salem37$43.1996$40.95
Culpeper6$22.8215$23.65
Hampton Roads3$150.006$120.91
Cover matl. aggr. no. 78, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (TON)Low bidsLow-bid median
5 to 10637$65.00
106.31 to 19438$28.84
195 to 37637$27.30
376 to 2,64938$34.45
Cover matl. aggr. no. 78, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Pearson Construction, Inc.3020 (67%)
F. Clayton Plecker & Sons, Inc.257 (28%)
D. S. Nash Construction Co.166 (38%)
A. R. Coffey and Sons, Inc.146 (43%)
General Excavation, Inc.155 (33%)
Plecker Construction Company135 (38%)
Cover matl. aggr. no. 78, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
17 DEC 2025C0000126197N01Lynchburg863$90.00$103.503Superior Paving CorporationVDOT
17 DEC 2025C0000107430C01Hampton Roads1,110$195.00$135.003Kokosing Construction Company, Inc.VDOT
22 OCT 2025C000117033M01DHampton Roads2,649$150.00$150.001Joseph B. Fay Co.VDOT
18 DEC 2019C0000090173B26Staunton106.31$62.58$62.583Kanawha Stone Company, Inc.VDOT
20 MAR 2019C0000111711C01Hampton Roads40$95.00$100.912Allan Myers Va, Inc.VDOT
27 JUL 2016C000108204N01Lynchburg10$70.00$60.003Burleigh Construction Co., Inc.VDOT
28 OCT 2015C0000106805N01Lynchburg10$200.00$200.003Burleigh Construction Co., Inc.VDOT
28 JAN 2015C00064422C01Salem122$96.80$60.003Boring Contractors, Inc.VDOT
23 JUL 2014C000102733C01Staunton116$44.10$42.003General Excavation, Inc.VDOT
22 MAY 2013C00019092N01Salem210$58.00$56.003Sowers Construction Co., Inc.VDOT
22 MAY 2013C00101217N01Staunton189$32.00$32.003Commonwealth Excavating, Inc.VDOT
27 FEB 2013C00087917N01Lynchburg267$26.85$28.763Pearson Construction, Inc.VDOT
27 FEB 2013C00097552C01Fredericksburg891$33.90$33.903Sargent CorporationVDOT
21 NOV 2012C00103612N01Lynchburg10$200.00$200.003Burleigh Construction Co., Inc.VDOT
28 MAR 2012C00094911N01Staunton378$38.60$37.753Plecker Construction CompanyVDOT
Latest VDOT contracts carrying Cover matl. aggr. no. 78

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy