Warning light TY. B, VDOT 512SD20-0029
Low bidders on VDOT contracts carried a median of $2.58 per DAY for this item, over the 24 months to 28 OCT 2026, across 32 low bids. Half of all 119 bids fell between $1.32 and $5.00.
- Owner
- Virginia DOT
- Item
- 512SD20-0029
- Unit
- DAY
- Data through
- 28 OCT 2026
VDOT prints this item as “WARNING LIGHT TY. B”.
VDOT has bid this work under more than one code: 24288 on lettings from 29 JAN 2002 to 15 DEC 2021 (869 bids); 512SD20-0029 on lettings from 19 NOV 2025 to 28 OCT 2026 (122 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 7 | 7 | $1.50 | 20 | $2.00 |
| 2003 | 9 | 6 | $2.00 | 19 | $2.35 |
| 2004 | 11 | 9 | $2.10 | 26 | $2.00 |
| 2005 | 9 | 8 | $2.50 | 19 | $2.50 |
| 2006 | 6 | 6 | $1.25 | 14 | $2.35 |
| 2007 | 13 | 13 | $1.75 | 31 | $1.50 |
| 2008 | 15 | 15 | $2.50 | 42 | $2.12 |
| 2009 | 15 | 14 | $1.52 | 41 | $2.00 |
| 2010 | 10 | 9 | $2.10 | 27 | $2.25 |
| 2011 | 9 | 9 | $2.00 | 26 | $2.16 |
| 2012 | 11 | 11 | $2.25 | 29 | $2.50 |
| 2013 | 15 | 15 | $1.60 | 41 | $2.54 |
| 2014 | 18 | 18 | $2.30 | 50 | $2.50 |
| 2015 | 21 | 21 | $2.29 | 59 | $2.41 |
| 2016 | 35 | 35 | $2.00 | 100 | $2.00 |
| 2017 | 21 | 21 | $2.00 | 56 | $1.95 |
| 2018 | 18 | 16 | $2.45 | 45 | $2.40 |
| 2019 | 19 | 19 | $2.50 | 52 | $2.00 |
| 2020 | 27 | 27 | $2.00 | 70 | $2.00 |
| 2021 | 28 | 27 | $2.50 | 74 | $2.28 |
| 2025 | 5 | 5 | $2.67 | 14 | $4.50 |
| 2026 | 27 | 27 | $2.50 | 105 | $2.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Salem | 7 | $4.00 | 24 | $4.00 |
| Culpeper | 4 | $1.90 | 19 | $3.15 |
| Bristol | 4 | $2.50 | 17 | $1.85 |
| Lynchburg | 4 | $4.00 | 12 | $2.20 |
| Richmond | 4 | $7.50 | 12 | $10.25 |
| Fredericksburg | 3 | $2.00 | 12 | $3.12 |
| Staunton | 3 | $2.46 | 9 | $2.46 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (DAY) | Low bids | Low-bid median |
|---|---|---|
| 5 to 108 | 8 | $5.50 |
| 200 to 896 | 8 | $2.00 |
| 953 to 1,630 | 8 | $2.90 |
| 1,800 to 5,660 | 8 | $2.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Lanford Brothers Company, Incorporated | 45 | 21 (47%) |
| Jones Road & Bridge, Inc. | 18 | 16 (89%) |
| Burleigh Construction Co., Inc. | 39 | 14 (36%) |
| Patrick Construction, Inc. | 21 | 13 (62%) |
| Branch Highways, Inc. | 15 | 11 (73%) |
| Elk Knob, Inc. | 35 | 10 (29%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | C0000128799N01B | Fredericksburg | 20 | $2.00 | $2.62 | 4 | Seminole Equipment, Inc. | VDOT |
| 28 OCT 2026 | C0000128800N01B | Fredericksburg | 20 | $10.00 | $6.62 | 6 | Seminole Equipment, Inc. | VDOT |
| 26 AUG 2026 | C0000124095M01 | Salem | 702 | $4.00 | $3.50 | 4 | Allegheny Construction Company, Inc. | VDOT |
| 22 JUL 2026 | C0000118431B20 | Culpeper | 480 | $1.50 | $5.00 | 6 | Freyssinet, Inc. | VDOT |
| 22 JUL 2026 | C0000121138B52 | Bristol | 2,160 | $4.00 | $4.00 | 5 | Elk Knob, Inc. | VDOT |
| 22 JUL 2026 | C0000115116C01 | Fredericksburg | 1,280 | $1.00 | $2.00 | 2 | J. L. Kent & Sons, Inc. | VDOT |
| 22 JUL 2026 | C0000120611C01 | Salem | 953 | $6.95 | $6.95 | 1 | Branch Civil, Inc. | VDOT |
| 22 JUL 2026 | C0000122147C01C | Richmond | 200 | $1.05 | $4.78 | 4 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 24 JUN 2026 | C0000108810C01 | Staunton | 959 | $1.25 | $55.00 | 2 | A & J Development and Excavation, Inc. | VDOT |
| 24 JUN 2026 | C0000123944C01 | Lynchburg | 60 | $6.00 | $4.20 | 2 | F & B Contractors, LTD. | VDOT |
| 27 MAY 2026 | C0000119206C01 | Culpeper | 1,630 | $2.30 | $2.15 | 6 | J. L. Kent & Sons, Inc. | VDOT |
| 27 MAY 2026 | C0000119458C01 | Salem | 2,220 | $8.05 | $2.00 | 6 | Branch Civil, Inc. | VDOT |
| 22 APR 2026 | C0000118863C01 | Culpeper | 5,660 | $1.50 | $1.50 | 1 | Caton Construction Group, Inc. | VDOT |
| 22 APR 2026 | C0000124564B64 | Culpeper | 3,200 | $4.25 | $2.63 | 6 | WG Construction Co., Inc. | VDOT |
| 22 APR 2026 | C0000119165C01 | Lynchburg | 1,800 | $2.00 | $3.50 | 2 | Haymes Brothers, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.