VDOT contract C0000123944C01 bid tabulation
Smart scale - roadway improvements. Let by Virginia DOT on June 24, 2026, Amherst, Lynchburg. 2 bids received; low bid $2,863,260 by F & B Contractors, LTD..
- Owner
- Virginia DOT
- Letting
- 24 JUN 2026
- Pay items
- 143
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | F & B Contractors, LTD. | $2,863,260 | Low |
| 2 | W. C. English, Incorporated | $3,813,066 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. F & B Contractors, LTD. | 2. W. C. English, Incorporated |
|---|---|---|---|---|---|
| 0001-0010 | Clearing and grubbing (301SD20-0002) | ACRE | 0.22 | $396,027 | $204,510 |
| 0001-0020 | 15" conc. pipe (302SD20-0025) | LF | 327 | $152.80 | $263.00 |
| 0001-0030 | 18" conc. pipe (302SD20-0030) | LF | 50 | $215.20 | $275.00 |
| 0001-0040 | 18" end section ES-1 or 2 (302SD20-0200) | EACH | 2 | $1,779.00 | $1,925.00 |
| 0001-0050 | Drop inlet DI-1 (302SD20-0237) | EACH | 1 | $8,905.50 | $8,635.00 |
| 0001-0060 | Drop inlet DI-3A (302SD20-0309) | EACH | 1 | $11,808 | $8,573.00 |
| 0001-0070 | Drop inlet DI-3B,L=4' (302SD20-0311) | EACH | 2 | $10,954 | $11,732 |
| 0001-0080 | Drop inlet DI-3B,L=6' (302SD20-0312) | EACH | 2 | $11,503 | $10,469 |
| 0001-0090 | Drop inlet DI-3C,L=6' (302SD20-0329) | EACH | 1 | $12,071 | $10,469 |
| 0001-0100 | Manhole MH-1 or 2 (302SD20-0662) | LF | 3.90 | $2,053.00 | $2,127.00 |
| 0001-0110 | Frame & cover MH-1 (302SD20-0663) | EACH | 4 | $879.70 | $1,052.85 |
| 0001-0120 | Regular excavation (303SD20-0001) | CY | 1,155 | $143.90 | $107.90 |
| 0001-0130 | Check dam rock TY. II (303SD20-0023) | EACH | 2 | $741.30 | $1,328.80 |
| 0001-0140 | Siltation control excavation (303SD20-0029) | CY | 187 | $0.10 | $0.01 |
| 0001-0150 | Inlet protection type A (303SD20-0030) | EACH | 2 | $391.00 | $414.50 |
| 0001-0160 | Inlet protection type B (303SD20-0031) | EACH | 9 | $565.60 | $414.50 |
| 0001-0170 | Temp. silt fence type A (303SD20-0034) | LF | 651 | $6.80 | $7.25 |
| 0001-0180 | Utility test pit unpaved (303SX20-0012) | EACH | 9 | $851.50 | $484.55 |
| 0001-0190 | Utility test pit asphalt concrete (303SX20-0013) | EACH | 2 | $2,282.70 | $927.10 |
| 0001-0200 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 951 | $95.50 | $83.00 |
| 0001-0210 | Crusher run aggr. no. 25 or 26 (308SX20-0003) | TON | 480 | $59.00 | $96.45 |
| 0001-0220 | Asphalt concrete TY. IM- 19.0D const (315SD20-0005) | TON | 171 | $270.50 | $442.05 |
| 0001-0230 | Asphalt concrete TY. SM- 9.5D const (315SD20-0008) | TON | 228 | $504.50 | $372.05 |
| 0001-0240 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 529 | $208.40 | $204.75 |
| 0001-0250 | NS saw-cut asph conc saw-cut (315SX20-0011) | LF | 919 | $10.00 | $5.90 |
| 0001-0260 | Erosion CTRL. stone CL. A1, EC-1 (414SD20-0001) | TON | 2 | $136.70 | $999.71 |
| 0001-0270 | Underdrain UD-4 (501SD20-0004) | LF | 339 | $42.40 | $63.30 |
| 0001-0280 | Outlet pipe (501SD20-0009) | LF | 9 | $38.30 | $68.00 |
| 0001-0290 | Curb, STD. CG-2 (502SD20-0011) | LF | 94 | $95.00 | $56.45 |
| 0001-0300 | Curb, radial CG-2 (502SD20-0012) | LF | 190 | $95.00 | $56.45 |
| 0001-0310 | Comb. curb & gutter, STD. CG-6 (502SD20-0022) | LF | 363 | $100.00 | $58.85 |
| 0001-0320 | Comb. curb & gutter, rad. CG-6 (502SD20-0023) | LF | 289 | $100.00 | $58.85 |
| 0001-0330 | Median strip MS-1A (502SD20-0056) | SY | 28 | $413.60 | $200.65 |
| 0001-0340 | CG-12 detectable warning surface (504SD20-0002) | SY | 6 | $859.20 | $561.60 |
| 0001-0350 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 130 | $288.30 | $160.60 |
| 0001-0360 | Demo. of pavement flexible (508SD20-0004) | SY | 675 | $62.10 | $28.50 |
| 0001-0370 | NS remove exist. drop inlet drop inlet (510SX20-0026) | EACH | 1 | $1,593.00 | $5,068.70 |
| 0001-0380 | NS modify exist. controller cabinet (510SX20-0031) | EACH | 1 | $3,241.00 | $2,179.50 |
| 0001-0390 | NS modify exist. drop inlet (510SX20-0031) | EACH | 3 | $2,216.00 | $2,770.20 |
| 0001-0400 | NS remove exist. conductor cable (510SX20-0039) | LF | 2,210 | $2.50 | $2.90 |
| 0001-0410 | NS remove exist. pipe (510SX20-0039) | LF | 106 | $10.30 | $60.65 |
| 0001-0420 | NS remove exist. electrical service (510SX20-0040) | EACH | 1 | $1,327.00 | $2,634.40 |
| 0001-0430 | NS remove exist. emergency preemption detector (510SX20-0040) | EACH | 4 | $337.00 | $896.50 |
| 0001-0440 | NS remove exist. pushbutton (510SX20-0040) | EACH | 3 | $259.00 | $627.55 |
| 0001-0450 | NS relocate managed field ethernet switch (510SX20-0042) | EACH | 1 | $1,183.00 | $1,727.65 |
| 0001-0460 | NS relocate video detection camera (510SX20-0042) | EACH | 2 | $1,219.00 | $1,053.00 |
| 0001-0470 | NS adjust exist. water service line (510SX20-0046) | EACH | 1 | $2,752.50 | $6,677.60 |
| 0001-0480 | Allaying dust (511SD20-0001) | HR | 270 | $65.00 | $0.01 |
| 0001-0490 | Type 3 barricade 8' (512SD20-0013) | EACH | 2 | $393.90 | $336.00 |
| 0001-0500 | Temporary sign (512SD20-0014) | SF | 1,041 | $33.30 | $25.20 |
| 0001-0510 | Pedestrian barricade device (512SD20-0018) | LF | 10 | $53.00 | $811.45 |
| 0001-0520 | Truck mounted attenuator (512SD20-0023) | HR | 6,630 | $75.00 | $4.30 |
| 0001-0530 | Group 2 channelizing devices (512SD20-0024) | DAY | 16,000 | $1.50 | $1.15 |
| 0001-0540 | Port.changeable mess. sign (512SD20-0025) | HR | 1,863 | $8.40 | $7.05 |
| 0001-0550 | Electronic arrow board (512SD20-0026) | HR | 5,850 | $4.40 | $4.65 |
| 0001-0560 | Warning light TY. B (512SD20-0029) | DAY | 60 | $6.00 | $2.40 |
| 0001-0570 | Eradicate linear PVMT MRKG (512SD20-0042) | LF | 25 | $60.20 | $30.25 |
| 0001-0580 | NS modify signal pedestrian shuttle service (512SX20-0020) | LS | 1 | $63,970 | $63,413 |
| 0001-0590 | NS police patrol uniformed flaggers (512SX20-0040) | HR | 360 | $100.00 | $120.00 |
| 0001-0600 | Mobilization (513SD20-0001) | LS | 1 | $62,552 | $497,008 |
| 0001-0610 | Mobilization (513SD20-0001) | LS | 1 | $74,444 | $497,008 |
| 0001-0620 | Mobilization (513SD20-0001) | LS | 1 | $65,133 | $497,008 |
| 0001-0630 | Field office TY.III (514SD20-0003) | MO | 9 | $3,686.70 | $5,506.00 |
| 0001-0640 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 1,215 | $49.40 | $46.95 |
| 0001-0650 | Flexible pave. planing above 2"-4" (515SD20-0005) | SY | 246 | $49.40 | $71.20 |
| 0001-0660 | Topsoil class B 2" (602SD20-0003) | ACRE | 0.05 | $37,242 | $49,261 |
| 0001-0670 | Temporary seed (603SD20-0002) | LB | 5 | $23.40 | $36.00 |
| 0001-0680 | Regular seed (603SD20-0003) | LB | 10 | $24.60 | $36.00 |
| 0001-0690 | Overseeding (603SD20-0004) | LB | 8 | $24.60 | $36.00 |
| 0001-0700 | Hydraulic erosion control product type 1 (603SD20-0007) | SY | 338 | $1.80 | $12.00 |
| 0001-0710 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 344 | $2.30 | $12.00 |
| 0001-0720 | Fertilizer nitrogen - N (603SD20-0014) | LB | 5 | $6.90 | $9.00 |
| 0001-0730 | Fertilizer phosphorous - P (603SD20-0015) | LB | 8 | $6.90 | $9.00 |
| 0001-0740 | Fertilizer potassium - K (603SD20-0016) | LB | 5 | $6.90 | $9.00 |
| 0001-0750 | Lime (603SD20-0017) | TON | 0.30 | $544.70 | $900.00 |
| 0001-0760 | Rolled erosion CTRL product EC-2 type 2 (606SD20-0002) | SY | 305 | $10.50 | $12.00 |
| 0001-0770 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 7 | $453.00 | $152.80 |
| 0001-0780 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 60 | $24.90 | $23.65 |
| 0001-0790 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 49 | $27.70 | $32.75 |
| 0001-0800 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 10 | $714.60 | $647.45 |
| 0001-0810 | Electrical service SE-5 (700SD20-0060) | EACH | 1 | $6,385.00 | $10,177 |
| 0001-0820 | Pedestal pole PF-2, 12' (700SD20-0067) | EACH | 3 | $2,071.00 | $2,166.55 |
| 0001-0830 | Conc. found. PF-8 (700SD20-0068) | CY | 46 | $1,303.00 | $1,241.80 |
| 0001-0840 | Conc. found. PF-2 (700SD20-0069) | EACH | 3 | $1,279.00 | $2,168.10 |
| 0001-0850 | Signal mast arm pole MP- 3, TY. A (700SD20-0090) | EACH | 1 | $27,883 | $24,341 |
| 0001-0860 | Signal mast arm pole MP- 3, TY. D (700SD20-0094) | EACH | 3 | $21,481 | $24,341 |
| 0001-0870 | Signal mast arm pole MP- 3, TY. E1 (700SD20-0095) | EACH | 1 | $30,259 | $32,736 |
| 0001-0880 | Mast arm 40' (700SD20-0099) | EACH | 1 | $8,245.00 | $11,569 |
| 0001-0890 | Mast arm 49' (700SD20-0100) | EACH | 2 | $9,607.00 | $12,912 |
| 0001-0900 | Mast arm 60' (700SD20-0101) | EACH | 1 | $15,439 | $17,648 |
| 0001-0910 | Mast arm 65' (700SD20-0102) | EACH | 1 | $17,167 | $17,984 |
| 0001-0920 | 14/4 conductor cable (700SD20-0112) | LF | 2,885 | $5.80 | $6.30 |
| 0001-0930 | 14/7 conductor cable (700SD20-0114) | LF | 2,040 | $6.10 | $7.10 |
| 0001-0940 | 14/2 conductor cable shielded (700SD20-0120) | LF | 3,265 | $5.20 | $6.45 |
| 0001-0950 | 8 conductor cable (700SD20-0144) | LF | 1,825 | $4.30 | $6.45 |
| 0001-0960 | 8 conductor cable egc (700SD20-0148) | LF | 2,910 | $4.30 | $4.25 |
| 0001-0970 | Electrical service work pad (700SD20-0174) | EACH | 1 | $3,121.00 | $2,538.00 |
| 0001-0980 | Junction box JB-S2 (700SD20-0178) | EACH | 8 | $1,405.00 | $2,945.55 |
| 0001-0990 | Junction box JB-S3 (700SD20-0179) | EACH | 4 | $1,693.00 | $3,292.75 |
| 0001-1000 | Elect. ser. GRD. electrode 10' (700SD20-0181) | EACH | 5 | $145.00 | $234.55 |
| 0001-1010 | Bored conduit 3" (700SD20-0192) | LF | 515 | $40.60 | $57.50 |
| 0001-1020 | Bored conduit 4" (700SD20-0193) | LF | 960 | $43.00 | $73.40 |
| 0001-1030 | Conduit PVC 2" (700SD20-0194) | LF | 355 | $9.40 | $9.35 |
| 0001-1040 | Conduit PVC 3" (700SD20-0195) | LF | 450 | $11.20 | $10.95 |
| 0001-1050 | Trench excavation eci-1 (700SD20-0197) | LF | 460 | $16.60 | $10.95 |
| 0001-1060 | Test bore (700SD20-0199) | EACH | 5 | $5,761.00 | $8,337.20 |
| 0001-1070 | NS conductor cable cat 5E gel filled shielded direct burial cable (700SX20-0007) | LF | 1,560 | $3.10 | $5.90 |
| 0001-1080 | NS conductor cable evp detector cable (infrared) (700SX20-0007) | LF | 2,015 | $5.20 | $7.30 |
| 0001-1090 | NS traffic signalization APS pedestrian actuation PA-2 (700SX20-0010) | EACH | 6 | $1,381.00 | $2,192.55 |
| 0001-1100 | NS traffic signalization atc cabinet - type II (32 outputs) (700SX20-0010) | EACH | 1 | $54,721 | $67,942 |
| 0001-1110 | NS traffic signalization auxiliary communications cabinet (700SX20-0010) | EACH | 1 | $4,381.00 | $5,490.65 |
| 0001-1120 | NS traffic signalization evp detection system infrared 4-way (700SX20-0010) | EACH | 1 | $16,561 | $19,293 |
| 0001-1130 | NS traffic signalization LED blankout sign (700SX20-0010) | EACH | 1 | $4,441.00 | $12,565 |
| 0001-1140 | NS traffic signalization local controller (atc) (700SX20-0010) | EACH | 1 | $10,171 | $11,435 |
| 0001-1150 | NS conc foundation CF-5 (700SX20-0022) | EACH | 1 | $6,541.00 | $3,927.00 |
| 0001-1160 | NS remove existing sign panel - (700SX20-0028) | EACH | 2 | $145.00 | $3,400.00 |
| 0001-1170 | Sign panel (701SD20-0001) | SF | 292 | $45.00 | $160.20 |
| 0001-1180 | Traf. sig. head sect. 12" HVS backplate (703SD20-0007) | EACH | 46 | $427.00 | $604.75 |
| 0001-1190 | Hanger assembly SMB-3, one way (703SD20-0039) | EACH | 6 | $349.00 | $632.95 |
| 0001-1200 | Remove existing pole (703SD20-0044) | EACH | 5 | $739.00 | $3,168.80 |
| 0001-1210 | Remove existing foundation (703SD20-0045) | EACH | 6 | $1,417.00 | $3,672.50 |
| 0001-1220 | Remove existing signal head (703SD20-0046) | EACH | 14 | $157.00 | $269.00 |
| 0001-1230 | Remove existing controller (703SD20-0047) | EACH | 1 | $211.00 | $837.90 |
| 0001-1240 | Remove existing manhole/junction box (703SD20-0048) | EACH | 9 | $493.00 | $663.85 |
| 0001-1250 | Uninterrupt. PWR supply type 2 (703SD20-0053) | EACH | 1 | $9,553.00 | $12,531 |
| 0001-1260 | Uninterrupt. PWR supply battery pac (703SD20-0054) | EACH | 1 | $4,441.00 | $5,342.00 |
| 0001-1270 | Uninterrupt. PWR supply cabinet att (703SD20-0055) | EACH | 1 | $8,587.00 | $9,663.00 |
| 0001-1280 | Pedestrian signal head SP-8 (703SD20-0060) | EACH | 3 | $1,753.00 | $1,262.90 |
| 0001-1290 | NS detector video detection camera (traditional advanced type III) (703SX20-0003) | EACH | 2 | $5,035.00 | $5,082.70 |
| 0001-1300 | NS detector video detection system TY. III (703SX20-0003) | EACH | 1 | $34,693 | $36,694 |
| 0001-1310 | NS hanger assembly mast arm hanger assembly SM- 3 (inline) (703SX20-0004) | EACH | 14 | $421.00 | $786.75 |
| 0001-1320 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 610 | $5.00 | $10.80 |
| 0001-1330 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 770 | $7.40 | $10.80 |
| 0001-1340 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 345 | $36.20 | $23.15 |
| 0001-1350 | PVMT MSG. mark. "only" TY B, CL II, 6' (704SD20-0036) | EACH | 1 | $1,441.00 | $530.90 |
| 0001-1360 | PVMT symb MRKG thru arrow TY B, CL II (704SD20-0045) | EACH | 2 | $541.00 | $406.60 |
| 0001-1370 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 8 | $541.00 | $387.50 |
| 0001-1380 | DBL turn arr.thru/LT or RT TY B, CL II (704SD20-0051) | EACH | 2 | $961.00 | $676.20 |
| 0001-1390 | NS communication equip. 5.8 GHZ wireless broadband radio dual (801SX20-0001) | EACH | 1 | $5,473.00 | $12,481 |
| 0001-1400 | NS communication equip. install field router (801SX20-0001) | EACH | 1 | $3,301.00 | $1,560.00 |
| 0001-1410 | NS communication equip. pre-terminated fiber patch panel (compact) (801SX20-0001) | EACH | 1 | $3,601.00 | $2,808.00 |
| 0001-1420 | Bored ITS conduit HDPE 3" (812SD20-0003) | LF | 125 | $40.60 | $63.75 |
| 0001-1430 | NS ITS conduit HDPE 3" (812SX20-0008) | LF | 25 | $14.20 | $49.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of June 24, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.