Bored conduit 4", VDOT 700SD20-0193
Low bidders on VDOT contracts carried a median of $64.70 per LF for this item, over the 24 months to 28 OCT 2026, across 8 low bids. Half of all 25 bids fell between $64.40 and $125.00.
- Owner
- Virginia DOT
- Item
- 700SD20-0193
- Unit
- LF
- Data through
- 28 OCT 2026
VDOT has bid this work under more than one code: 56052 on lettings from 22 NOV 2006 to 17 NOV 2021 (224 bids); 700SD20-0193 on lettings from 17 DEC 2025 to 23 SEP 2026 (25 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2006 | 1 | 1 | $22.95 | 3 | $26.40 |
| 2007 | 6 | 6 | $32.05 | 12 | $33.05 |
| 2008 | 4 | 4 | $32.50 | 12 | $30.50 |
| 2009 | 1 | 1 | $34.02 | 3 | $34.02 |
| 2010 | 8 | 8 | $25.38 | 23 | $28.00 |
| 2011 | 7 | 6 | $25.50 | 19 | $26.00 |
| 2012 | 7 | 7 | $34.79 | 21 | $34.79 |
| 2013 | 12 | 12 | $35.00 | 32 | $35.50 |
| 2014 | 8 | 8 | $24.30 | 24 | $27.94 |
| 2015 | 4 | 4 | $41.52 | 10 | $44.00 |
| 2016 | 4 | 3 | $45.00 | 8 | $33.63 |
| 2017 | 4 | 4 | $42.50 | 11 | $50.00 |
| 2018 | 3 | 3 | $30.00 | 9 | $40.99 |
| 2019 | 4 | 4 | $43.60 | 11 | $49.20 |
| 2020 | 7 | 7 | $32.50 | 19 | $39.00 |
| 2021 | 2 | 2 | $49.64 | 6 | $45.38 |
| 2025 | 1 | 1 | $65.00 | 3 | $139.20 |
| 2026 | 7 | 7 | $64.40 | 22 | $76.88 |
Bid prices as published, not adjusted for inflation.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Richardson-Wayland Electrical Co. LLC | 14 | 7 (50%) |
| A & M Concrete Corp. | 19 | 6 (32%) |
| B & B Signal Co., L.L.C. | 15 | 6 (40%) |
| Fort Myer Construction Corporation | 12 | 5 (42%) |
| Ardent Company, LLC | 7 | 5 (71%) |
| General Excavation, Inc. | 6 | 5 (83%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 23 SEP 2026 | C0000128686N01 | Culpeper | 400 | $69.20 | $69.20 | 3 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 22 JUL 2026 | C0000115116C01 | Fredericksburg | 2,000 | $64.40 | $47.20 | 2 | J. L. Kent & Sons, Inc. | VDOT |
| 22 JUL 2026 | C0000120611C01 | Salem | 75 | $73.75 | $73.75 | 1 | Branch Civil, Inc. | VDOT |
| 24 JUN 2026 | C0000123944C01 | Lynchburg | 960 | $43.00 | $58.20 | 2 | F & B Contractors, LTD. | VDOT |
| 27 MAY 2026 | C0000119206C01 | Culpeper | 300 | $129.00 | $132.00 | 6 | J. L. Kent & Sons, Inc. | VDOT |
| 27 MAY 2026 | C000113172C01D | Fredericksburg | 955 | $25.00 | $102.50 | 4 | Ardent Company, LLC | VDOT |
| 04 FEB 2026 | C0000127373N01 | Northern Virginia | 1,150 | $50.00 | $85.00 | 4 | Creative Design Concepts, Inc. | VDOT |
| 17 DEC 2025 | C0000118871C01B | Culpeper | 100 | $65.00 | $139.20 | 3 | S. L. Williamson Company, Incorporated | VDOT |
| 17 NOV 2021 | C0000106670C01 | Fredericksburg | 850 | $59.28 | $58.00 | 3 | J. L. Kent & Sons, Inc. | VDOT |
| 28 JUL 2021 | C0000000688C02 | Salem | 405 | $40.00 | $45.00 | 3 | Allegheny Construction Company, Inc. | VDOT |
| 16 DEC 2020 | C0000117400N01 | Hampton Roads | 200 | $33.00 | $36.00 | 3 | Bryant-Ritter Electric Corporation | VDOT |
| 18 NOV 2020 | C0000109814C01 | Northern Virginia | 420 | $52.00 | $52.00 | 3 | Tavares Concrete Co., Inc. | VDOT |
| 23 SEP 2020 | C0000117245N01 | Richmond | 100 | $50.38 | $50.38 | 1 | Richardson-Wayland Electrical Co. LLC | VDOT |
| 22 APR 2020 | C0000109471C01 | Fredericksburg | 300 | $32.50 | $32.50 | 3 | Shamrock Construction Corporation | VDOT |
| 22 APR 2020 | C0000116081N01 | Northern Virginia | 4,102 | $20.00 | $39.00 | 3 | B & B Signal Co., L.L.C. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.