Bored conduit 3", VDOT 700SD20-0192

Low bidders on VDOT contracts carried a median of $60.25 per LF for this item, over the 24 months to 28 OCT 2026, across 27 low bids. Half of all 71 bids fell between $54.45 and $76.16.

Owner
Virginia DOT
Item
700SD20-0192
Unit
LF
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 56051 on lettings from 22 NOV 2006 to 27 OCT 2021 (409 bids); 700SD20-0192 on lettings from 22 OCT 2025 to 28 OCT 2026 (71 bids). They are combined here into one trend.

$60.25Low bidder's median, per LF
$62.00Median of all bids, per LF
27Contracts in the window

By year of letting

Bored conduit 3", VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200611$34.423$30.00
200766$26.7612$26.76
200844$21.5412$21.00
200944$23.9512$25.00
20101111$22.8032$25.50
2011109$24.0028$25.75
201277$20.0015$21.00
20131413$28.0035$35.00
20141717$32.0047$32.00
20151313$29.4031$33.88
20161919$37.9744$34.50
20171010$31.8828$32.73
201888$34.5822$34.50
20191212$33.4532$35.49
20201515$30.0039$30.00
202166$39.8916$39.96
202555$70.6916$72.84
20262222$59.0855$60.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Staunton7$68.1818$72.84
Salem6$63.0018$68.00
Lynchburg5$52.7411$58.15
Culpeper3$55.708$56.05
Bored conduit 3", VDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
73 to 2006$56.09
202 to 2567$62.00
270 to 5767$52.74
600 to 4,1507$63.00
Bored conduit 3", VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Fielder'S Choice Enterprises, Inc.209 (45%)
Curtis Contracting, Inc.158 (53%)
Allegheny Construction Company, Inc.127 (58%)
General Excavation, Inc.107 (70%)
B & B Signal Co., L.L.C.176 (35%)
W-L Construction & Paving, Inc.116 (55%)
Bored conduit 3", VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026C0000124205C01BStaunton73$54.00$81.003S. L. Williamson Company, IncorporatedVDOT
23 SEP 2026C0000128686N01Culpeper1,375$55.70$55.703Richardson-Wayland-Ferreira, LLCVDOT
26 AUG 2026C0000124094M01Salem256$62.00$62.003Jones Road & Bridge, Inc.VDOT
26 AUG 2026C0000115512C01Hampton Roads375$50.00$50.003Allan Myers Va, Inc.VDOT
22 JUL 2026C0000120697C01Salem330$62.00$64.003Crossroads Bridge IncVDOT
22 JUL 2026C0000128966N01Fredericksburg730$36.78$54.883Richardson-Wayland-Ferreira, LLCVDOT
22 JUL 2026C0000111704C01Richmond155$69.00$69.001J. L. Kent & Sons, Inc.VDOT
22 JUL 2026C0000119641C02Staunton202$85.00$80.722G. B. Foltz Contracting, Inc.VDOT
22 JUL 2026C0000120611C01Salem1,115$64.00$64.001Branch Civil, Inc.VDOT
22 JUL 2026C0000120748C01Culpeper250$51.00$55.704General Excavation, Inc.VDOT
22 JUL 2026C0000120710C01Lynchburg185$54.02$56.712Caton Construction Group, Inc.VDOT
22 JUL 2026C0000115403C01CRichmond215$60.00$60.003MCC ACQUISITION, LC dba VIRGINIA-CAROLINAVDOT
24 JUN 2026C0000108810C01Staunton1,270$63.00$61.502A & J Development and Excavation, Inc.VDOT
24 JUN 2026C0000123944C01Lynchburg515$40.60$49.052F & B Contractors, LTD.VDOT
24 JUN 2026C0000119655C01BStaunton2,175$43.48$43.481Richardson-Wayland-Ferreira, LLCVDOT
Latest VDOT contracts carrying Bored conduit 3"

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.