VDOT contract C0000119165C01 bid tabulation
Smart scale- intersection improvement. Let by Virginia DOT on April 22, 2026, Pittsylvania, Lynchburg. 2 bids received; low bid $2,063,465 by Haymes Brothers, Inc..
- Owner
- Virginia DOT
- Letting
- 22 APR 2026
- Pay items
- 100
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Haymes Brothers, Inc. | $2,063,465 | Low |
| 2 | F & B Contractors, LTD. | $2,248,929 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Haymes Brothers, Inc. | 2. F & B Contractors, LTD. |
|---|---|---|---|---|---|
| 0001-0010 | Const rec docs SWM facility constr rec docs SWM facility (105SP20-0002) | LS | 1 | $50,000 | $10,000 |
| 0001-0020 | Clearing and grubbing (301SD20-0001) | LS | 1 | $150,000 | $65,550 |
| 0001-0030 | 12" conc. pipe (302SD20-0020) | LF | 4 | $150.00 | $308.00 |
| 0001-0040 | 15" storm sewer pipe (302SD20-0027) | LF | 18 | $150.00 | $168.00 |
| 0001-0050 | 18" storm sewer pipe (302SD20-0032) | LF | 174 | $175.00 | $185.00 |
| 0001-0060 | 23" X 14" elliptical pipe (302SD20-0132) | LF | 107 | $275.00 | $317.00 |
| 0001-0070 | 18" end section ES-1 (302SD20-0201) | EACH | 2 | $2,500.00 | $1,752.00 |
| 0001-0080 | 23" X 14" end section ES-1A (302SD20-0221) | EACH | 1 | $5,000.00 | $3,058.00 |
| 0001-0090 | Drop inlet DI-1 (302SD20-0237) | EACH | 1 | $5,000.00 | $9,351.00 |
| 0001-0100 | Drop inlet DI-3C,L=6' (302SD20-0329) | EACH | 1 | $5,000.00 | $11,750 |
| 0001-0110 | Regular excavation (303SD20-0001) | CY | 315 | $500.00 | $525.00 |
| 0001-0120 | Borrow excavation (303SD20-0007) | CY | 53 | $10.00 | $68.00 |
| 0001-0130 | Check dam rock TY. II (303SD20-0023) | EACH | 13 | $1,500.00 | $768.00 |
| 0001-0140 | Siltation control excavation (303SD20-0029) | CY | 197 | $10.00 | $62.00 |
| 0001-0150 | Inlet protection type A (303SD20-0030) | EACH | 3 | $5,000.00 | $370.00 |
| 0001-0160 | Inlet protection type B (303SD20-0031) | EACH | 1 | $5,000.00 | $580.00 |
| 0001-0170 | Temp. silt fence type A (303SD20-0034) | LF | 1,003 | $5.00 | $7.50 |
| 0001-0180 | NS soil transportation and disposal of petroleum contaminated soil (303SX20-0001) | TON | 36.40 | $50.00 | $350.00 |
| 0001-0190 | Aggr. matl. no. 25 or 26 (305SD20-0011) | TON | 20 | $75.00 | $50.00 |
| 0001-0200 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 1,038 | $80.00 | $57.00 |
| 0001-0210 | Asphalt concrete TY. IM- 19.0D const (315SD20-0005) | TON | 190 | $400.24 | $450.00 |
| 0001-0220 | Asphalt concrete TY. SM- 9.5D const (315SD20-0008) | TON | 505 | $263.18 | $300.00 |
| 0001-0230 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 583 | $319.00 | $330.00 |
| 0001-0240 | NS saw-cut asph conc full depth (315SX20-0011) | LF | 1,469 | $10.00 | $9.00 |
| 0001-0250 | Erosion CTRL. stone CL. A1, EC-1 (414SD20-0002) | SY | 2.60 | $1,000.00 | $481.00 |
| 0001-0260 | Dry riprap CL. AI (414SD20-0008) | TON | 0.60 | $200.00 | $1,992.00 |
| 0001-0270 | Paved ditch PG-5 (502SD20-0004) | SY | 27 | $271.00 | $406.00 |
| 0001-0280 | Comb. curb & gutter, STD. CG-6 (502SD20-0022) | LF | 108 | $56.42 | $115.00 |
| 0001-0290 | Comb. curb & gutter, rad. CG-6 (502SD20-0023) | LF | 108 | $56.42 | $125.00 |
| 0001-0300 | Median strip MS-1 (502SD20-0053) | SY | 126 | $185.00 | $291.00 |
| 0001-0310 | Median strip MS-1A (502SD20-0056) | SY | 93 | $242.00 | $318.00 |
| 0001-0320 | Remove existing guardrail (505SD20-0073) | LF | 527 | $10.00 | $20.00 |
| 0001-0330 | Demo. of pavement flexible (508SD20-0004) | SY | 1,284 | $50.00 | $56.00 |
| 0001-0340 | NS modify exist. modify existing drainage structure (510SX20-0031) | EACH | 1 | $5,000.00 | $2,863.00 |
| 0001-0350 | Allaying dust (511SD20-0001) | HR | 240 | $50.00 | $65.00 |
| 0001-0360 | Type 3 barricade 8' (512SD20-0013) | EACH | 63 | $400.00 | $400.00 |
| 0001-0370 | Temporary sign (512SD20-0014) | SF | 844 | $11.84 | $42.50 |
| 0001-0380 | Truck mounted attenuator (512SD20-0023) | HR | 1,200 | $17.50 | $75.00 |
| 0001-0390 | Group 2 channelizing devices (512SD20-0024) | DAY | 14,288 | $1.10 | $1.75 |
| 0001-0400 | Port.changeable mess. sign (512SD20-0025) | HR | 2,688 | $2.00 | $5.00 |
| 0001-0410 | Electronic arrow board (512SD20-0026) | HR | 840 | $5.00 | $6.00 |
| 0001-0420 | Flagger service (512SD20-0027) | HR | 1,280 | $20.00 | $65.00 |
| 0001-0430 | Warning light TY. B (512SD20-0029) | DAY | 1,800 | $2.00 | $5.00 |
| 0001-0440 | Eradicate linear PVMT MRKG (512SD20-0042) | LF | 3,400 | $2.32 | $3.00 |
| 0001-0450 | Temp. PVMT MRKG TY. D, CL. III, 4" (512SD20-0061) | LF | 4,800 | $4.15 | $5.00 |
| 0001-0460 | Temp. PVMT MRKG TY. D, CL. III, 8" (512SD20-0063) | LF | 1,600 | $6.93 | $8.00 |
| 0001-0470 | Temp. PVMT MRKG TY. D, CL. III, 24" (512SD20-0065) | LF | 24 | $16.37 | $19.00 |
| 0001-0480 | NS police patrol traffic (512SX20-0040) | HR | 360 | $100.00 | $100.00 |
| 0001-0490 | Mobilization (513SD20-0001) | LS | 1 | $100,000 | $139,620 |
| 0001-0500 | Field office TY.I (514SD20-0001) | MO | 6 | $10,000 | $4,500.00 |
| 0001-0510 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 3,686 | $11.83 | $14.00 |
| 0001-0520 | Topsoil class B 2" (602SD20-0003) | ACRE | 0.15 | $25,000 | $34,405 |
| 0001-0530 | Temporary seed (603SD20-0002) | LB | 15 | $4.40 | $25.00 |
| 0001-0540 | Regular seed (603SD20-0003) | LB | 22 | $3.85 | $25.00 |
| 0001-0550 | Overseeding (603SD20-0004) | LB | 17 | $4.40 | $25.00 |
| 0001-0560 | Legume seed (603SD20-0005) | LB | 1 | $16.50 | $50.00 |
| 0001-0570 | Legume overseeding (603SD20-0006) | LB | 1 | $16.50 | $50.00 |
| 0001-0580 | Hydraulic erosion control product type 1 (603SD20-0007) | SY | 363 | $4.40 | $6.10 |
| 0001-0590 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 1,271 | $3.30 | $7.00 |
| 0001-0600 | Fertilizer nitrogen - N (603SD20-0014) | LB | 14 | $6.05 | $7.00 |
| 0001-0610 | Fertilizer phosphorous - P (603SD20-0015) | LB | 20 | $6.05 | $7.00 |
| 0001-0620 | Fertilizer potassium - K (603SD20-0016) | LB | 10 | $6.05 | $7.00 |
| 0001-0630 | Lime (603SD20-0017) | TON | 0.68 | $132.00 | $592.50 |
| 0001-0640 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 8 | $411.40 | $472.00 |
| 0001-0650 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 120 | $17.60 | $24.00 |
| 0001-0660 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 10 | $595.10 | $680.50 |
| 0001-0670 | Conc. found. PF-8 (700SD20-0068) | CY | 40 | $1,119.93 | $1,610.00 |
| 0001-0680 | Signal mast arm pole MP- 3, TY. F (700SD20-0097) | EACH | 2 | $34,057 | $36,629 |
| 0001-0690 | Mast arm 49' (700SD20-0100) | EACH | 1 | $13,202 | $40,000 |
| 0001-0700 | Mast arm 60' (700SD20-0101) | EACH | 3 | $16,656 | $45,000 |
| 0001-0710 | 14/7 conductor cable (700SD20-0114) | LF | 1,330 | $6.51 | $8.50 |
| 0001-0720 | 8 conductor cable egc (700SD20-0148) | LF | 990 | $13.20 | $6.00 |
| 0001-0730 | Junction box JB-S2 (700SD20-0178) | EACH | 2 | $7,700.00 | $4,804.00 |
| 0001-0740 | Conduit PVC 1" (700SD20-0182) | LF | 30 | $7.66 | $14.50 |
| 0001-0750 | Bored conduit 2" (700SD20-0191) | LF | 70 | $49.30 | $69.00 |
| 0001-0760 | Bored conduit 3" (700SD20-0192) | LF | 140 | $58.15 | $75.50 |
| 0001-0770 | Conduit PVC 2" (700SD20-0194) | LF | 20 | $8.51 | $27.00 |
| 0001-0780 | Conduit PVC 3" (700SD20-0195) | LF | 60 | $10.00 | $29.50 |
| 0001-0790 | Trench excavation eci-1 (700SD20-0197) | LF | 100 | $10.53 | $62.00 |
| 0001-0800 | Luminaire arm 24' (700SD20-0228) | EACH | 2 | $11,000 | $3,191.50 |
| 0001-0810 | Sign panel (701SD20-0001) | SF | 121 | $99.56 | $75.00 |
| 0001-0820 | Flexible post delineator (702SD20-0002) | EACH | 7 | $239.34 | $272.00 |
| 0001-0830 | Traf. sig. head sect. 12" HVS backplate (703SD20-0007) | EACH | 38 | $1,100.00 | $523.00 |
| 0001-0840 | Video detection camera (703SD20-0014) | EACH | 4 | $29,013 | $10,754 |
| 0001-0850 | Video detection cable (703SD20-0015) | LF | 670 | $7.06 | $9.00 |
| 0001-0860 | Evp detection system 4- way (703SD20-0023) | EACH | 1 | $14,300 | $13,836 |
| 0001-0870 | Evp detector cable (703SD20-0024) | LF | 670 | $6.50 | $8.60 |
| 0001-0880 | Hanger assembly SM-3, one way (703SD20-0034) | EACH | 12 | $750.00 | $648.00 |
| 0001-0890 | Remove existing pole (703SD20-0044) | EACH | 2 | $3,000.00 | $1,898.00 |
| 0001-0900 | Remove existing foundation (703SD20-0045) | EACH | 2 | $4,662.00 | $2,485.50 |
| 0001-0910 | Remove existing signal head (703SD20-0046) | EACH | 11 | $620.00 | $229.00 |
| 0001-0920 | Relocate existing signal head (703SD20-0049) | EACH | 4 | $1,390.00 | $698.00 |
| 0001-0930 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 4,480 | $2.00 | $2.75 |
| 0001-0940 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 906 | $2.00 | $3.25 |
| 0001-0950 | Type B class I PVMT line MRKG 24" (704SD20-0010) | LF | 156 | $12.91 | $16.00 |
| 0001-0960 | Type B class II PVMT line MRKG 4" (704SD20-0011) | LF | 360 | $7.00 | $9.00 |
| 0001-0970 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 3 | $2,490.00 | $2,834.00 |
| 0001-0980 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 15 | $407.00 | $470.00 |
| 0001-0990 | PVMT symb MRKG TRPL turn arr TY B CL II (704SD20-0054) | EACH | 2 | $700.00 | $800.00 |
| 0001-1000 | NS luminaire conventional luminaires wattage 200 type LLL (705SX20-0001) | EACH | 2 | $1,700.00 | $1,450.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of April 22, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way