Flexible post delineator, VDOT 702SD20-0002

Low bidders on VDOT contracts carried a median of $236.67 per EACH for this item, over the 24 months to 28 OCT 2026, across 4 low bids. Half of all 12 bids fell between $97.25 and $235.34.

Owner
Virginia DOT
Item
702SD20-0002
Unit
EACH
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 24286 on lettings from 26 FEB 2002 to 15 DEC 2021 (153 bids); 702SD20-0002 on lettings from 22 OCT 2025 to 26 AUG 2026 (12 bids). They are combined here into one trend.

$236.67Low bidder's median, per EACH
$175.00Median of all bids, per EACH
4Contracts in the window

By year of letting

Flexible post delineator, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200244$55.5012$51.75
200344$46.0410$50.00
200422$43.756$57.18
200522$45.006$40.00
200611$35.003$35.00
200766$35.7518$37.50
200844$104.0512$86.28
200922$64.894$64.89
201022$72.286$68.70
201155$60.0015$60.00
201244$101.0010$111.00
201344$150.0011$150.00
201444$112.5011$142.03
201522$105.005$125.00
201633$61.048$90.00
201744$116.159$102.29
202011$28.801$28.80
202122$89.345$125.00
202511$234.005$200.00
202633$239.347$145.26

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Hampton Roads14$72.0036$69.73
Salem12$87.5035$105.00
Richmond6$93.5016$80.62
Bristol5$50.0015$49.15
Northern Virginia6$66.7014$57.00
Culpeper5$73.1614$111.00
Staunton4$115.0012$87.50
Lynchburg4$69.0011$82.00
Fredericksburg4$55.0011$60.00
Flexible post delineator, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (EACH)Low bidsLow-bid median
3 to 1215$105.00
12 to 2815$133.16
30 to 9515$51.51
100 to 1,50015$51.08
Flexible post delineator, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Branscome Inc.83 (38%)
Elk Knob, Inc.52 (40%)
DLB, Inc.51 (20%)
Flexible post delineator, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
26 AUG 2026C0000115512C01Hampton Roads125$89.00$100.003Allan Myers Va, Inc.VDOT
22 JUL 2026C0000115116C01Fredericksburg19$275.00$162.502J. L. Kent & Sons, Inc.VDOT
22 APR 2026C0000119165C01Lynchburg7$239.34$255.672Haymes Brothers, Inc.VDOT
22 OCT 2025C0000125954C01Salem24$234.00$200.005Jones Road & Bridge, Inc.VDOT
15 DEC 2021C0000117347B23Bristol1,067$50.00$50.003Triton Construction Inc. of VirginiaVDOT
24 MAR 2021CM521PME117403Hampton Roads3$128.69$126.842Branscome Inc.VDOT
26 FEB 2020CM220PME115958Salem20$28.80$28.801Adams Construction CompanyVDOT
21 JUN 2017C000107660N01BHampton Roads12$347.42$347.421Branscome Inc.VDOT
21 JUN 2017C00109380C01Culpeper8$130.00$127.502General Excavation, Inc.VDOT
22 MAR 2017CM517PME108931Hampton Roads10$102.29$102.293Branscome Inc.VDOT
25 JAN 2017C0000110146B22Lynchburg50$85.00$85.003Burleigh Construction Co., Inc.VDOT
21 DEC 2016C0000099542M01Salem4$61.04$132.003Phillips Construction, LLCVDOT
22 JUN 2016C000106738N01BHampton Roads20$42.00$36.002Jireh Construction Company, Inc.VDOT
27 APR 2016C00090346C01Richmond14$112.00$110.003Blakemore Construction CorporationVDOT
25 FEB 2015C00075910C02Salem6$105.00$150.003Branch Highways, Inc.VDOT
Latest VDOT contracts carrying Flexible post delineator

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.