Pedestrian actuation PA-2, VDOT 703SD20-0011
Low bidders on VDOT contracts carried a median of $1,943.00 per EACH for this item, over the 24 months to 28 OCT 2026, across 8 low bids. Half of all 21 bids fell between $1,781.96 and $2,200.00.
- Owner
- Virginia DOT
- Item
- 703SD20-0011
- Unit
- EACH
- Data through
- 28 OCT 2026
VDOT prints this item as “PEDESTRIAN ACTUATION PA-2”.
VDOT has bid this work under more than one code: 51198 on lettings from 27 JAN 2010 to 26 AUG 2020 (206 bids); 703SD20-0011 on lettings from 24 JUN 2026 to 23 SEP 2026 (21 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2010 | 9 | 10 | $146.00 | 29 | $150.00 |
| 2011 | 8 | 6 | $146.24 | 22 | $150.00 |
| 2012 | 10 | 10 | $157.00 | 27 | $165.00 |
| 2013 | 12 | 12 | $180.00 | 31 | $175.00 |
| 2014 | 6 | 6 | $225.00 | 18 | $177.66 |
| 2015 | 7 | 7 | $227.50 | 16 | $206.94 |
| 2016 | 14 | 13 | $325.00 | 30 | $307.41 |
| 2017 | 3 | 3 | $184.00 | 8 | $189.75 |
| 2018 | 3 | 3 | $275.00 | 9 | $314.00 |
| 2019 | 3 | 3 | $306.26 | 7 | $306.26 |
| 2020 | 3 | 3 | $850.09 | 6 | $1,500.00 |
| 2026 | 8 | 8 | $1,943.00 | 21 | $2,000.00 |
Bid prices as published, not adjusted for inflation.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| B & B Signal Co., L.L.C. | 9 | 5 (56%) |
| A & M Concrete Corp. | 15 | 4 (27%) |
| Fort Myer Construction Corporation | 11 | 4 (36%) |
| Richardson-Wayland Electrical Co. LLC | 9 | 3 (33%) |
| Finley Asphalt & Sealing, Inc. | 6 | 3 (50%) |
| Branscome Inc. | 5 | 3 (60%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 23 SEP 2026 | C0000124001C01B | Staunton | 4 | $1,781.96 | $1,868.78 | 4 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 23 SEP 2026 | C0000128686N01 | Culpeper | 9 | $1,448.18 | $1,454.00 | 3 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 26 AUG 2026 | C0000124094M01 | Salem | 6 | $1,836.00 | $1,836.00 | 3 | Jones Road & Bridge, Inc. | VDOT |
| 26 AUG 2026 | C0000115512C01 | Hampton Roads | 2 | $2,200.00 | $2,132.69 | 3 | Allan Myers Va, Inc. | VDOT |
| 22 JUL 2026 | C0000120697C01 | Salem | 2 | $2,050.00 | $2,050.00 | 3 | Crossroads Bridge Inc | VDOT |
| 22 JUL 2026 | C0000119641C02 | Staunton | 4 | $2,501.00 | $2,376.04 | 2 | G. B. Foltz Contracting, Inc. | VDOT |
| 22 JUL 2026 | C0000120710C01 | Lynchburg | 2 | $1,644.29 | $1,729.64 | 2 | Caton Construction Group, Inc. | VDOT |
| 24 JUN 2026 | C0000119655C01B | Staunton | 10 | $2,226.74 | $2,226.74 | 1 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 26 AUG 2020 | C0000109586N01B | Lynchburg | 1 | $820.00 | $2,000.00 | 3 | MCC Acquisition, LC DBA Virginia-Carolina Paving Co. | VDOT |
| 22 APR 2020 | C0000109507M01 | Bristol | 1 | $850.09 | $850.09 | 1 | Estes Bros. Const., Inc. | VDOT |
| 22 JAN 2020 | C000111370C01B | Salem | 10 | $1,600.00 | $1,500.00 | 2 | Allegheny Construction Company, Inc. | VDOT |
| 26 JUN 2019 | C0000114674N01 | Northern Virginia | 4 | $350.00 | $350.00 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 20 MAR 2019 | C0000111711C01 | Hampton Roads | 52 | $260.00 | $252.50 | 2 | Allan Myers Va, Inc. | VDOT |
| 23 JAN 2019 | C000109437M01B | Bristol | 6 | $306.26 | $317.46 | 2 | W-L Construction & Paving, Inc. | VDOT |
| 19 DEC 2018 | C000103084C501 | Fredericksburg | 2 | $862.50 | $750.00 | 3 | Henderson Construction Co., Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.