Estes Bros. Const., Inc.: VDOT bid record

Estes Bros. Const., Inc. submitted 85 bids on Virginia DOT contracts in the data, from 22 OCT 2002 to 25 FEB 2026, and was the low bidder on 43 of them (51%). When it was not low, its total sat a median +10% above the low bid.

Owner
Virginia DOT
Low bid volume
$31,077,123
Latest bid
25 FEB 2026
Data through
28 OCT 2026

VDOT's 2002 to 2021 workbooks list only the three lowest bids on each contract, so a firm's bids that ranked fourth or lower in those years are missing: bid counts are understated and win rates overstated for those years.

85Bids
43Low bids
51Win rate, percent
+10%Median gap to the low bid when not low, 42 bids

By year

YearBidsLow bidsWin rate
20025120%
200311545%
200411100%
20054375%
200614536%
2007200%
20082150%
20092150%
20102150%
2011100%
20136467%
20149556%
201511100%
20168563%
20173267%
20182150%
20195240%
202044100%
20212150%
2026100%
Estes Bros. Const., Inc., VDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
Bristol844351%
Salem100%
Estes Bros. Const., Inc., VDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Siltation control excavation303SD20-0029CY5349 (92%)$1.00$3.50
Group 2 channelizing devices512SD20-0024DAY5844 (76%)$0.43$1.00
Temp. silt fence type A303SD20-0034LF7040 (57%)$2.58$3.00
Lime603SD20-0017TON4235 (83%)$100.00$200.00
Flagger service512SD20-0027HR5234 (65%)$8.00$20.00
Overseeding603SD20-0004LB3931 (79%)$3.00$5.00
Regular seed603SD20-0003LB4229 (69%)$8.00$13.50
Alt.breakaway cable term. GR-9505SD20-0038EACH4027 (68%)$2,500.00$2,425.00
Allaying dust511SD20-0001HR3526 (74%)$8.00$22.00
Legume overseeding603SD20-0006LB3225 (78%)$9.00$17.32
Aggr. base matl. TY. I no. 21B308SD20-0012TON6624 (36%)$19.24$26.00
Guardrail GR-2505SD20-0030LF4023 (57%)$18.89$18.00
Estes Bros. Const., Inc., VDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Elk Knob, Inc.4315 of 43
Glass Machinery and Excavation, Inc.3215 of 32
Patrick Construction, Inc.207 of 20
Ken Construction Co., Inc.165 of 16
W-L Construction & Paving, Inc.133 of 13
Cleco Corporation72 of 7
Boring Contractors, Inc.50 of 5
Rogers Group, Inc.20 of 2
Crossroads Bridge Inc22 of 2
Bush & Burchett, Inc.20 of 2
Estes Bros. Const., Inc., VDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
25 FEB 2026CM226PMP128572Salem2026 plant mix pilot - vtti2 of 2$494,025+175%
17 NOV 2021CM119LMA115175BristolBridge deck replacement over norfolk southern railroad3 of 3$1,847,020+45%
28 APR 2021C0000071874B03BristolSgr-bridge replacement over south fork powell river1 of 3$965,735Low, 39% under the second
22 JUL 2020C00000109438C01BristolSmart scale- intersection access management with park & ride1 of 3$2,562,964Low, 29% under the second
24 JUN 2020C0000111272C01BristolSmart scale -truck climbing lane phase 21 of 3$2,186,122Low, 113% under the second
22 APR 2020C0000109507M01BristolPedestrian safety improvement1 of 1$98,653Low
22 APR 2020C0000112709N01BristolPedestrian safety improvements1 of 1$69,710Low
18 DEC 2019C0000086601B61BristolBridge replacement over powell river3 of 3$6,447,245+14%
13 NOV 2019C0000110952B50BristolSuperstructure replacement over hardy creek3 of 3$473,894+6.0%
21 AUG 2019C000110011B49BristolSgr - superstructure replacement over copper creek1 of 3$731,407Low, 4.0% under the second
20 MAR 2019C000112279N01BBristolOn-call ada compliance curb ramp improvements2 of 2$187,789+6.0%
23 JAN 2019C0000086294B42BristolSuperstructure replacement over indian creek1 of 3$495,632Low, 26% under the second
22 AUG 2018C0000104826B51BristolSgr - superstructure replacement over little toms creek1 of 2$291,178Low, 34% under the second
25 JUL 2018C0000000104189BristolSafety improvements via road re-alignment2 of 3$1,494,671+36%
23 AUG 2017C0000086726M01BristolRte 649 - spot widen curves1 of 3$1,090,770Low, 8.0% under the second
26 APR 2017C000109861N01BristolOn-call ada compliance curb ramp improvements1 of 3$148,517Low, 14% under the second
25 JAN 2017C0000108109B06BristolDistrict wide bridge washing2 of 3$414,482+13%
16 NOV 2016C0000086594B45BristolBros-5404(120)(nfo)0687-084-658, b6452 of 3$390,433+1.0%
16 NOV 2016C000104458B49BristolSuperstructure replacement on rte. 672 over martin creek1 of 3$247,142Low, 6.0% under the second
24 AUG 2016C00090176B44BristolBridge on rte. 158 (east front street) over toms creek1 of 3$1,265,300Low, 19% under the second
23 MAR 2016C0000101386C01BristolBridge replacement on rte. 661 over long hollow branch2 of 3$625,430+5.0%
24 FEB 2016C0000087907C01BristolWiden to 3 lanes1 of 3$5,118,122Low, 11% under the second
03 FEB 2016C0000086479B64BristolSuperstructure replacement on route 6111 of 3$433,653Low, 15% under the second
03 FEB 2016C0000103558B63BristolSuperstructure replacement over martins creek1 of 3$239,144Low, 15% under the second
03 FEB 2016C000086295B58BristolSuperstructure replacement on rte. 619 over n.f. holston riv2 of 3$341,265+8.0%
Estes Bros. Const., Inc.: latest VDOT bids in the data

How this record was read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Every bid counted here matched its published total to within one dollar; VDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy