VDOT contract C0000124001C01B bid tabulation
Smart scale - pedestrian improvements. Let by Virginia DOT on September 23, 2026, Buena Vista, Staunton. 4 bids received; low bid $624,180 by Richardson-Wayland-Ferreira, LLC.
- Owner
- Virginia DOT
- Letting
- 23 SEP 2026
- Pay items
- 73
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Richardson-Wayland-Ferreira, LLC | $624,180 | Low |
| 2 | Graham Concrete, LLC | $636,824 | +2.0% |
| 3 | F & B Contractors, LTD. | $687,870 | +10% |
| 4 | Lumin8 Transportation Technologies, LLC | $888,156 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Richardson-Wayland-Ferreira, LLC | 2. Graham Concrete, LLC | 3. F & B Contractors, LTD. | 4. Lumin8 Transportation Technologies, LLC |
|---|---|---|---|---|---|---|---|
| 0001-0010 | 15" conc. pipe (302SD20-0025) | LF | 26 | $512.50 | $250.00 | $158.00 | $704.00 |
| 0001-0020 | Drop inlet DI-2B,L=6' (302SD20-0242) | EACH | 1 | $5,125.00 | $16,000 | $12,765 | $19,265 |
| 0001-0030 | Drop inlet DI-2B,L=10' (302SD20-0244) | EACH | 1 | $7,175.00 | $18,000 | $14,562 | $30,503 |
| 0001-0040 | Drop inlet DI-3C,L=6' (302SD20-0329) | EACH | 1 | $6,150.00 | $16,000 | $5,213.00 | $8,860.00 |
| 0001-0050 | Manhole MH-1 or 2 (302SD20-0662) | LF | 6.40 | $2,050.00 | $1,200.00 | $1,124.00 | $2,878.00 |
| 0001-0060 | Frame & cover MH-1 (302SD20-0663) | EACH | 1 | $2,050.00 | $1,500.00 | $777.00 | $2,408.00 |
| 0001-0070 | Grading (303SD20-0004) | LS | 1 | $41,000 | $49,000 | $152,325 | $19,186 |
| 0001-0080 | Siltation control excavation (303SD20-0029) | CY | 108 | $35.88 | $0.01 | $0.25 | $18.40 |
| 0001-0090 | Inlet protection type B (303SD20-0031) | EACH | 9 | $488.81 | $300.00 | $538.00 | $380.00 |
| 0001-0100 | Temp. silt fence type A (303SD20-0034) | LF | 372 | $2.92 | $10.00 | $6.00 | $4.70 |
| 0001-0110 | Aggr. matl. no. 21B (308SD20-0007) | TON | 142 | $205.00 | $100.00 | $99.00 | $144.00 |
| 0001-0120 | Asphalt concrete TY. SM- 12.5A const (315SD20-0001) | TON | 54 | $571.18 | $400.00 | $799.00 | $454.00 |
| 0001-0130 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 14 | $1,542.63 | $400.00 | $1,902.00 | $530.00 |
| 0001-0140 | Saw-cut asphalt concrete full depth (315SD20-0104) | LF | 355 | $10.25 | $25.00 | $11.00 | $11.80 |
| 0001-0150 | Underdrain UD-4 (501SD20-0004) | LF | 108 | $61.50 | $10.00 | $39.00 | $83.00 |
| 0001-0160 | Outlet pipe (501SD20-0009) | LF | 8 | $307.50 | $40.00 | $36.00 | $400.00 |
| 0001-0170 | Curb, STD. CG-2 (502SD20-0011) | LF | 216 | $66.63 | $100.00 | $75.00 | $91.00 |
| 0001-0180 | Curb, radial CG-2 (502SD20-0012) | LF | 91 | $66.63 | $120.00 | $75.00 | $91.00 |
| 0001-0190 | Comb. curb & gutter, STD. CG-6 (502SD20-0022) | LF | 141 | $76.88 | $140.00 | $79.00 | $100.00 |
| 0001-0200 | Comb. curb & gutter, rad. CG-6 (502SD20-0023) | LF | 108 | $76.88 | $140.00 | $79.00 | $100.00 |
| 0001-0210 | R/W monument RM-1 (503SD20-0001) | EACH | 9 | $1,000.57 | $50.00 | $768.00 | $91.00 |
| 0001-0220 | CG-12 detectable warning surface (504SD20-0002) | SY | 9 | $615.00 | $1,400.00 | $636.00 | $871.00 |
| 0001-0230 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 220 | $112.75 | $120.00 | $230.00 | $387.00 |
| 0001-0240 | Remove existing guardrail (505SD20-0073) | LF | 45 | $102.50 | $60.00 | $24.00 | $105.00 |
| 0001-0250 | Demo. of pavement flexible (508SD20-0004) | SY | 39 | $51.25 | $110.00 | $61.00 | $15.20 |
| 0001-0260 | NS remove exist. drop inlet remove drop inlet (510SX20-0026) | EACH | 1 | $1,025.00 | $3,500.00 | $1,470.00 | $9,080.00 |
| 0001-0270 | NS reset exist. junction box (510SX20-0029) | EACH | 1 | $2,567.58 | $1,668.80 | $4,111.00 | $384.00 |
| 0001-0280 | NS modify exist. modify existing controller (510SX20-0031) | EACH | 1 | $5,225.62 | $5,670.40 | $3,241.00 | $247.00 |
| 0001-0290 | NS modify exist. modify existing junction box (510SX20-0031) | EACH | 4 | $2,535.46 | $1,785.70 | $1,711.00 | $375.00 |
| 0001-0300 | NS adjust exist. drop inlet adjust drop inlet (510SX20-0033) | EACH | 1 | $2,562.50 | $1,500.00 | $2,052.00 | $3,199.00 |
| 0001-0310 | NS adjust exist. adjust existing video detection zone (510SX20-0046) | EACH | 1 | $5,746.03 | $3,170.00 | $3,961.00 | $1,366.00 |
| 0001-0320 | Allaying dust (511SD20-0001) | HR | 101 | $0.67 | $0.01 | $130.00 | $99.00 |
| 0001-0330 | Type 3 barricade 8' (512SD20-0013) | EACH | 1 | $820.00 | $800.00 | $394.00 | $825.00 |
| 0001-0340 | Temporary sign (512SD20-0014) | SF | 445 | $41.00 | $35.00 | $32.00 | $183.70 |
| 0001-0350 | Pedestrian barricade device (512SD20-0018) | LF | 84 | $102.50 | $140.00 | $69.00 | $106.00 |
| 0001-0360 | Group 2 channelizing devices (512SD20-0024) | DAY | 7,416 | $1.03 | $2.00 | $1.50 | $8.83 |
| 0001-0370 | Flagger service (512SD20-0027) | HR | 150 | $71.75 | $90.00 | $65.00 | $295.00 |
| 0001-0380 | Eradicate nonlinear PVMT MRKG (512SD20-0043) | SF | 153 | $23.58 | $75.00 | $29.00 | $34.80 |
| 0001-0390 | Temp. PVMT. symb. MRKG SNGL turn arrow TY. A (512SD20-0052) | EACH | 1 | $3,587.50 | $800.00 | $4,201.00 | $5,301.00 |
| 0001-0400 | Mobilization (513SD20-0001) | LS | 1 | $136,742 | $152,000 | $43,504 | $126,604 |
| 0001-0410 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 452 | $38.44 | $17.00 | $29.00 | $3.00 |
| 0001-0420 | Construction surveying constr. (517SD20-0001) | LS | 1 | $14,760 | $15,000 | $24,400 | $52,914 |
| 0001-0430 | Topsoil class B (602SD20-0006) | CY | 32 | $153.75 | $60.00 | $192.00 | $265.00 |
| 0001-0440 | Temporary seed (603SD20-0002) | LB | 8 | $20.50 | $12.00 | $28.00 | $11.60 |
| 0001-0450 | Regular seed (603SD20-0003) | LB | 32 | $15.38 | $12.00 | $22.00 | $11.60 |
| 0001-0460 | Overseeding (603SD20-0004) | LB | 26 | $10.25 | $12.00 | $16.00 | $11.60 |
| 0001-0470 | Hydraulic erosion control product type 1 (603SD20-0007) | SY | 484 | $1.28 | $3.00 | $2.00 | $12.10 |
| 0001-0480 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 387 | $1.54 | $3.00 | $3.00 | $48.50 |
| 0001-0490 | Fertilizer nitrogen - N (603SD20-0014) | LB | 8 | $4.10 | $3.00 | $9.00 | $5.00 |
| 0001-0500 | Fertilizer phosphorous - P (603SD20-0015) | LB | 6 | $4.10 | $3.00 | $9.00 | $4.80 |
| 0001-0510 | Fertilizer potassium - K (603SD20-0016) | LB | 6 | $4.10 | $3.00 | $9.00 | $4.80 |
| 0001-0520 | Lime (603SD20-0017) | TON | 0.44 | $461.25 | $800.00 | $545.00 | $307.60 |
| 0001-0530 | NS landscape landscaping allowance (605SX20-0013) | LS | 1 | $6,150.00 | $1,000.00 | $13,200 | $31,943 |
| 0001-0540 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 3 | $145.40 | $792.00 | $453.00 | $133.00 |
| 0001-0550 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 1 | $474.11 | $466.00 | $209.00 | $152.00 |
| 0001-0560 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 75 | $30.52 | $41.00 | $28.00 | $38.30 |
| 0001-0570 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 6 | $871.02 | $768.00 | $715.00 | $648.00 |
| 0001-0580 | Pedestal pole PF-2, 10' (700SD20-0066) | EACH | 4 | $2,986.51 | $1,958.00 | $2,161.00 | $1,488.00 |
| 0001-0590 | Conc. found. PF-2 (700SD20-0069) | EACH | 4 | $3,627.46 | $1,734.00 | $1,861.00 | $365.00 |
| 0001-0600 | 14/2 conductor cable (700SD20-0110) | LF | 725 | $5.12 | $5.50 | $6.00 | $3.90 |
| 0001-0610 | 14/7 conductor cable (700SD20-0114) | LF | 745 | $6.48 | $5.50 | $8.00 | $5.10 |
| 0001-0620 | 8 conductor cable egc (700SD20-0148) | LF | 110 | $4.62 | $4.42 | $7.00 | $2.40 |
| 0001-0630 | Junction box JB-S2 (700SD20-0178) | EACH | 1 | $3,631.92 | $2,484.00 | $4,021.00 | $1,283.00 |
| 0001-0640 | Conduit PVC 3" (700SD20-0195) | LF | 85 | $11.43 | $19.00 | $19.00 | $21.50 |
| 0001-0650 | Trench excavation eci-1 (700SD20-0197) | LF | 85 | $54.34 | $19.23 | $85.00 | $28.00 |
| 0001-0660 | Sign panel (701SD20-0001) | SF | 53 | $72.58 | $61.50 | $45.00 | $36.50 |
| 0001-0670 | Pedestrian actuation PA-2 (703SD20-0011) | EACH | 4 | $1,781.96 | $1,955.60 | $3,481.00 | $1,485.00 |
| 0001-0680 | Hanger assembly SMB-1, one way (703SD20-0036) | EACH | 4 | $697.05 | $640.38 | $1,171.00 | $725.00 |
| 0001-0690 | Pedestrian signal head SP-8 (703SD20-0060) | EACH | 4 | $1,382.29 | $2,800.50 | $2,521.00 | $958.00 |
| 0001-0700 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 200 | $25.25 | $3.25 | $31.00 | $37.20 |
| 0001-0710 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 188 | $28.78 | $38.00 | $35.00 | $42.50 |
| 0001-0720 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 2 | $362.39 | $575.00 | $425.00 | $535.00 |
| 0001-0730 | PVMT symb MRKG yield 2' X 3' TY B, CL II (704SD20-0087) | EACH | 7 | $60.37 | $575.00 | $72.00 | $89.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of September 23, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.