VDOT contract C0000125954C01 bid tabulation
Parking lot improvements. Let by Virginia DOT on October 22, 2025, Roanoke, Salem. 5 bids received; low bid $735,731 by Jones Road & Bridge, Inc..
- Owner
- Virginia DOT
- Letting
- 22 OCT 2025
- Pay items
- 82
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jones Road & Bridge, Inc. | $735,731 | Low |
| 2 | Allegheny Construction Company, Inc. | $818,103 | +11% |
| 3 | F & B Contractors, LTD. | $819,138 | +11% |
| 4 | Hammond-Mitchell, Inc. | $833,595 | +13% |
| 5 | Stonewall Bridge, Inc. | $925,488 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jones Road & Bridge, Inc. | 2. Allegheny Construction Company, Inc. | 3. F & B Contractors, LTD. | 4. Hammond-Mitchell, Inc. | 5. Stonewall Bridge, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001-0010 | Clearing and grubbing (301SD20-0001) | LS | 1 | $100,000 | $45,000 | $59,000 | $24,288 | $40,000 |
| 0001-0020 | 15" storm sewer pipe (302SD20-0027) | LF | 69 | $300.00 | $300.00 | $250.00 | $339.60 | $300.00 |
| 0001-0030 | 15" end section ES-1 or 2 (302SD20-0198) | EACH | 1 | $1,500.00 | $760.00 | $1,670.00 | $2,832.00 | $2,500.00 |
| 0001-0040 | Drop inlet DI-3A (302SD20-0309) | EACH | 1 | $8,000.00 | $11,000 | $10,845 | $12,240 | $10,000 |
| 0001-0050 | Drop inlet DI-7 (302SD20-0447) | EACH | 1 | $9,000.00 | $12,000 | $9,057.50 | $7,644.00 | $10,000 |
| 0001-0060 | Manhole MH-2 (302SD20-0661) | LF | 3.40 | $900.00 | $3,000.00 | $1,540.00 | $7,230.00 | $1,500.00 |
| 0001-0070 | Frame & cover MH-1 (302SD20-0663) | EACH | 1 | $1,000.00 | $1,000.00 | $811.00 | $2,952.00 | $500.00 |
| 0001-0080 | Regular excavation (303SD20-0001) | CY | 562 | $85.70 | $130.00 | $208.00 | $99.60 | $125.00 |
| 0001-0090 | Borrow excavation (303SD20-0007) | CY | 131 | $65.00 | $80.00 | $55.00 | $176.40 | $200.00 |
| 0001-0100 | Siltation control excavation (303SD20-0029) | CY | 86 | $0.01 | $1.00 | $16.00 | $0.01 | $1.00 |
| 0001-0110 | Inlet protection type A (303SD20-0030) | EACH | 1 | $600.00 | $525.00 | $450.00 | $780.00 | $2,500.00 |
| 0001-0120 | Inlet protection type B (303SD20-0031) | EACH | 3 | $650.00 | $525.00 | $400.00 | $660.00 | $2,000.00 |
| 0001-0130 | Geotextile fabric (303SD20-0032) | SY | 409 | $3.00 | $8.00 | $5.00 | $6.60 | $15.00 |
| 0001-0140 | Temp. silt fence type A (303SD20-0034) | LF | 328 | $8.00 | $8.00 | $7.50 | $7.20 | $10.00 |
| 0001-0150 | Aggregate material no.3 (303SP20-0001) | TON | 387 | $81.00 | $60.00 | $53.50 | $76.80 | $100.00 |
| 0001-0160 | Aggr. matl. no. 1 (305SD20-0010) | TON | 21 | $80.00 | $65.00 | $75.00 | $106.80 | $200.00 |
| 0001-0170 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 230 | $60.00 | $190.00 | $137.00 | $81.60 | $150.00 |
| 0001-0180 | Asphalt concrete TY. SM- 9.5D const (315SD20-0008) | TON | 154 | $174.00 | $185.00 | $185.50 | $354.00 | $250.00 |
| 0001-0190 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 410 | $186.00 | $195.00 | $225.00 | $187.20 | $200.00 |
| 0001-0200 | Saw-cut asphalt concrete full depth (315SD20-0104) | LF | 290 | $10.00 | $14.00 | $8.00 | $7.68 | $15.00 |
| 0001-0210 | NS pavement integrally colored and textured concrete (316SX20-0004) | SY | 13 | $650.00 | $770.00 | $400.00 | $480.00 | $1,000.00 |
| 0001-0220 | Erosion CTRL. stone CL. A1, EC-1 (414SD20-0002) | SY | 1.60 | $2,000.00 | $125.00 | $350.00 | $726.60 | $10,000 |
| 0001-0230 | Curb, STD. CG-2 (502SD20-0011) | LF | 155 | $93.00 | $175.00 | $115.00 | $114.00 | $100.00 |
| 0001-0240 | Curb, radial CG-2 (502SD20-0012) | LF | 30 | $93.00 | $175.00 | $120.00 | $144.00 | $110.00 |
| 0001-0250 | Curb, STD. CG-3 (502SD20-0014) | LF | 58 | $93.00 | $175.00 | $115.00 | $126.00 | $100.00 |
| 0001-0260 | Curb, radial CG-3 (502SD20-0015) | LF | 49 | $93.00 | $175.00 | $120.00 | $156.00 | $110.00 |
| 0001-0270 | Comb. curb & gutter, STD. CG-6 (502SD20-0022) | LF | 10 | $95.00 | $175.00 | $150.00 | $138.00 | $110.00 |
| 0001-0280 | Comb. curb & gutter, STD. CG-7 (502SD20-0024) | LF | 20 | $95.00 | $175.00 | $150.00 | $150.00 | $110.00 |
| 0001-0290 | Comb. curb & gutter, rad. CG-7 (502SD20-0025) | LF | 30 | $95.00 | $175.00 | $155.00 | $180.00 | $110.00 |
| 0001-0300 | NS median strip median strip (502SX20-0012) | SY | 115 | $300.00 | $270.00 | $350.00 | $180.00 | $300.00 |
| 0001-0310 | CG-12 detectable warning surface (504SD20-0002) | SY | 17 | $1,000.00 | $1,300.00 | $725.00 | $1,680.00 | $750.00 |
| 0001-0320 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 53 | $120.00 | $300.00 | $250.00 | $180.00 | $130.00 |
| 0001-0330 | NS concrete wheel stop (504SX20-0007) | EACH | 11 | $100.00 | $240.00 | $200.00 | $532.80 | $500.00 |
| 0001-0340 | Demo. of pavement rigid (508SD20-0003) | SY | 17 | $30.00 | $100.00 | $85.00 | $244.80 | $200.00 |
| 0001-0350 | Demo. of pavement flexible (508SD20-0004) | SY | 132 | $10.00 | $30.00 | $49.00 | $34.50 | $100.00 |
| 0001-0360 | Adjust exist frame & cover (510SD20-0050) | EACH | 2 | $550.00 | $4,200.00 | $1,540.00 | $2,880.00 | $1,000.00 |
| 0001-0370 | Remove comb. curb and gutter (510SX20-0002) | LF | 146 | $20.00 | $30.00 | $25.00 | $35.70 | $50.00 |
| 0001-0380 | NS remove exist. fence wood (510SX20-0016) | LF | 50 | $30.00 | $20.00 | $25.00 | $20.40 | $30.00 |
| 0001-0390 | Allaying dust (511SD20-0001) | HR | 130 | $20.00 | $50.00 | $10.00 | $84.00 | $1.00 |
| 0001-0400 | Type 3 barricade 4' (512SD20-0012) | EACH | 5 | $500.00 | $600.00 | $400.00 | $720.00 | $350.00 |
| 0001-0410 | Type 3 barricade 8' (512SD20-0013) | EACH | 6 | $600.00 | $640.00 | $450.00 | $960.00 | $400.00 |
| 0001-0420 | Temporary sign (512SD20-0014) | SF | 104 | $25.00 | $28.00 | $37.00 | $48.00 | $30.00 |
| 0001-0430 | Temporary detectable warning surface (512SD20-0017) | LF | 10 | $120.00 | $200.00 | $200.00 | $240.00 | $100.00 |
| 0001-0440 | Group 2 longitudinal channelizing device (512SD20-0022) | LF | 246 | $66.00 | $70.00 | $100.00 | $48.00 | $100.00 |
| 0001-0450 | Group 2 channelizing devices (512SD20-0024) | DAY | 5,500 | $1.00 | $2.40 | $1.75 | $2.40 | $2.00 |
| 0001-0460 | Flagger service (512SD20-0027) | HR | 342 | $30.00 | $60.00 | $65.00 | $78.00 | $110.00 |
| 0001-0470 | Eradicate nonlinear PVMT MRKG (512SD20-0043) | SF | 195 | $22.00 | $20.00 | $13.00 | $21.60 | $21.00 |
| 0001-0480 | Portable temporary rumble strip array (512SP20-0001) | DAY | 10 | $110.00 | $300.00 | $150.00 | $360.00 | $1,250.00 |
| 0001-0490 | Mobilization (513SD20-0001) | LS | 1 | $58,000 | $65,000 | $66,435 | $66,000 | $90,000 |
| 0001-0500 | Flexible pave.planing 0"-2" (515SD20-0013) | SY | 256 | $80.00 | $100.00 | $98.00 | $112.80 | $30.00 |
| 0001-0510 | Construction surveying constr. (517SD20-0001) | LS | 1 | $60,000 | $32,000 | $30,000 | $29,760 | $40,000 |
| 0001-0520 | Mailbox post, multiple (521SD20-0003) | EACH | 1 | $800.00 | $3,400.00 | $275.00 | $3,504.00 | $500.00 |
| 0001-0530 | Topsoil class B (602SD20-0004) | CY | 40 | $120.00 | $475.00 | $191.00 | $177.60 | $500.00 |
| 0001-0540 | Temporary seed (603SD20-0002) | LB | 27 | $42.00 | $24.00 | $1.00 | $42.00 | $39.00 |
| 0001-0550 | Regular seed (603SD20-0003) | LB | 34 | $60.00 | $20.00 | $67.00 | $60.00 | $55.00 |
| 0001-0560 | Overseeding (603SD20-0004) | LB | 27 | $60.00 | $9.00 | $67.00 | $60.00 | $55.00 |
| 0001-0570 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 605 | $3.60 | $1.50 | $4.90 | $3.60 | $5.00 |
| 0001-0580 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 484 | $6.00 | $2.00 | $7.00 | $6.00 | $7.50 |
| 0001-0590 | Fertilizer nitrogen - N (603SD20-0014) | LB | 10 | $6.00 | $5.00 | $30.00 | $6.00 | $6.00 |
| 0001-0600 | Fertilizer phosphorous - P (603SD20-0015) | LB | 7 | $6.00 | $5.00 | $19.75 | $6.00 | $6.00 |
| 0001-0610 | Fertilizer potassium - K (603SD20-0016) | LB | 7 | $6.00 | $5.00 | $19.75 | $6.00 | $6.00 |
| 0001-0620 | Lime (603SD20-0017) | TON | 0.60 | $360.00 | $240.00 | $545.00 | $360.00 | $330.00 |
| 0001-0630 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 12 | $450.00 | $410.00 | $475.00 | $900.00 | $500.00 |
| 0001-0640 | Remove existing 2 post sign structure (700SD20-0004) | EACH | 1 | $900.00 | $825.00 | $950.00 | $1,200.00 | $1,000.00 |
| 0001-0650 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 10 | $90.00 | $100.00 | $128.00 | $420.00 | $1,000.00 |
| 0001-0660 | Relocate EX. 2 post GRND mount SGN panel (700SD20-0013) | EACH | 1 | $416.40 | $400.00 | $450.00 | $600.00 | $2,000.00 |
| 0001-0670 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 66 | $18.00 | $18.00 | $25.00 | $43.20 | $100.00 |
| 0001-0680 | Sign post STP-1, 2 3/16", 10 gauge (700SD20-0035) | LF | 12 | $21.60 | $20.00 | $28.50 | $120.00 | $100.00 |
| 0001-0690 | Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036) | LF | 139 | $21.60 | $20.00 | $28.50 | $72.00 | $100.00 |
| 0001-0700 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 54 | $19.20 | $18.00 | $29.00 | $60.00 | $100.00 |
| 0001-0710 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 10 | $614.40 | $570.00 | $650.00 | $1,320.00 | $850.00 |
| 0001-0720 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 11 | $968.40 | $890.00 | $1,066.00 | $1,440.00 | $850.00 |
| 0001-0730 | NS conc foundation concrete foundation (700SX20-0022) | EACH | 1 | $877.20 | $800.00 | $950.00 | $1,440.00 | $850.00 |
| 0001-0740 | Sign panel (701SD20-0001) | SF | 114 | $33.60 | $32.00 | $45.00 | $48.00 | $80.00 |
| 0001-0750 | Flexible post delineator (702SD20-0002) | EACH | 24 | $234.00 | $225.00 | $150.00 | $28.80 | $200.00 |
| 0001-0760 | Type B class II PVMT line MRKG 4" (704SD20-0011) | LF | 8 | $26.40 | $25.00 | $32.50 | $26.40 | $25.00 |
| 0001-0770 | Type B class II PVMT line MRKG 12" (704SD20-0014) | LF | 231 | $26.40 | $25.00 | $20.00 | $26.40 | $25.00 |
| 0001-0780 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 80 | $42.00 | $38.00 | $40.00 | $42.00 | $40.00 |
| 0001-0790 | PVMT symb MRKG thru arrow TY B, CL II (704SD20-0045) | EACH | 4 | $600.00 | $550.00 | $520.00 | $600.00 | $600.00 |
| 0001-0800 | MRKG fish hook LFT/thru/RGHT TY B CL II (704SD20-0072) | EACH | 1 | $1,500.00 | $1,400.00 | $1,550.00 | $1,500.00 | $1,500.00 |
| 0001-0810 | MRKG int'L accessibility symb TY B CL II (704SD20-0093) | EACH | 2 | $600.00 | $525.00 | $535.00 | $600.00 | $600.00 |
| 0001-0820 | Type A class I PVMT line MRKG 4" (704SD20-0112) | LF | 1,193 | $5.53 | $5.00 | $3.50 | $5.53 | $5.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of October 22, 2025. Compiled by Mirage Metrics.