VDOT contract C0000119452C50 bid tabulation
Smart scale - intersection improvements/ lane addition. Let by Virginia DOT on December 17, 2025, Botetourt, Salem. 5 bids received; low bid $2,487,557 by Crossroads Bridge Inc.
- Owner
- Virginia DOT
- Letting
- 17 DEC 2025
- Pay items
- 101
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Crossroads Bridge Inc | $2,487,557 | Low |
| 2 | Haymes Brothers, Inc. | $2,593,499 | +4.0% |
| 3 | Allegheny Construction Company, Inc. | $3,017,177 | +21% |
| 4 | F & B Contractors, LTD. | $3,250,000 | +31% |
| 5 | W. C. English, Incorporated | $3,455,500 | +39% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Crossroads Bridge Inc | 2. Haymes Brothers, Inc. | 3. Allegheny Construction Company, Inc. | 4. F & B Contractors, LTD. | 5. W. C. English, Incorporated |
|---|---|---|---|---|---|---|---|---|
| 0001-0010 | Baseline progress schedule (108SP20-0001) | LS | 1 | $21,000 | $6,000.00 | $12,000 | $30,000 | $9,150.00 |
| 0001-0020 | Progress schedule updates (108SP20-0002) | EACH | 9 | $1,000.00 | $1,200.00 | $1,200.00 | $1,150.00 | $854.00 |
| 0001-0030 | Clearing and grubbing (301SD20-0001) | LS | 1 | $75,000 | $50,000 | $100,000 | $75,000 | $239,147 |
| 0001-0040 | Concrete class A4 box culvert (302SD20-0004) | CY | 35.20 | $3,200.00 | $6,200.00 | $4,570.00 | $3,950.00 | $3,650.00 |
| 0001-0050 | Corrosion resistant reinf.steel CL. I (302SD20-0006) | LB | 3,679 | $4.50 | $3.50 | $7.00 | $10.00 | $5.40 |
| 0001-0060 | 15" storm sewer pipe (302SD20-0027) | LF | 48 | $175.00 | $200.00 | $265.00 | $137.00 | $130.00 |
| 0001-0070 | 18" conc. pipe (302SD20-0030) | LF | 13 | $200.00 | $300.00 | $720.00 | $209.00 | $250.00 |
| 0001-0080 | 18" storm sewer pipe (302SD20-0032) | LF | 94 | $150.00 | $200.00 | $200.00 | $152.00 | $174.00 |
| 0001-0090 | 24" storm sewer pipe (302SD20-0041) | LF | 18 | $200.00 | $225.00 | $340.00 | $195.00 | $184.00 |
| 0001-0100 | 30" conc. pipe (302SD20-0049) | LF | 126 | $220.00 | $250.00 | $290.00 | $340.00 | $236.00 |
| 0001-0110 | Drop inlet DI-2B,L=10' (302SD20-0244) | EACH | 1 | $10,500 | $9,500.00 | $15,000 | $14,634 | $10,969 |
| 0001-0120 | Drop inlet DI-3B,L=10' (302SD20-0314) | EACH | 1 | $10,000 | $7,800.00 | $13,500 | $12,268 | $10,650 |
| 0001-0130 | Drop inlet DI-3CC,L=6' (302SD20-0337) | EACH | 1 | $11,000 | $12,500 | $15,000 | $14,289 | $9,098.00 |
| 0001-0140 | Manhole MH-1 or 2 (302SD20-0662) | LF | 23.50 | $850.00 | $1,050.00 | $2,000.00 | $1,539.00 | $1,045.00 |
| 0001-0150 | Frame & cover MH-1 (302SD20-0663) | EACH | 4 | $3,500.00 | $625.00 | $1,800.00 | $850.00 | $1,730.00 |
| 0001-0160 | NS bedding matl. aggr. no. 3 (302SX20-0004) | TON | 51.60 | $80.00 | $100.00 | $225.00 | $100.00 | $77.90 |
| 0001-0170 | NS precast box culvert (86' - 8' X 6') (302SX20-0005) | LF | 86 | $2,000.00 | $5,000.00 | $6,300.00 | $2,750.00 | $7,000.00 |
| 0001-0180 | Regular excavation (303SD20-0001) | CY | 717 | $165.00 | $75.00 | $175.00 | $200.00 | $113.00 |
| 0001-0190 | Borrow excavation (303SD20-0007) | CY | 510 | $85.00 | $75.00 | $100.00 | $100.00 | $101.00 |
| 0001-0200 | Geotextile embankment stab. (303SD20-0013) | SY | 79 | $15.00 | $12.00 | $10.00 | $13.00 | $15.20 |
| 0001-0210 | Minor STR. excav. box culvert (303SD20-0017) | CY | 942 | $65.00 | $110.00 | $130.00 | $171.00 | $36.00 |
| 0001-0220 | Check dam rock TY. II (303SD20-0023) | EACH | 1 | $850.00 | $1,000.00 | $900.00 | $812.00 | $436.35 |
| 0001-0230 | Dewatering basin EC-8 (303SD20-0028) | EACH | 4 | $6,000.00 | $1,000.00 | $5,000.00 | $3,400.00 | $1,096.00 |
| 0001-0240 | Siltation control excavation (303SD20-0029) | CY | 168 | $0.01 | $10.00 | $35.00 | $4.50 | $0.01 |
| 0001-0250 | Inlet protection type B (303SD20-0031) | EACH | 6 | $900.00 | $350.00 | $500.00 | $400.00 | $443.40 |
| 0001-0260 | Temp. silt fence type A (303SD20-0034) | LF | 813 | $7.00 | $6.00 | $5.00 | $6.00 | $7.55 |
| 0001-0270 | NS embankment clay plug (303SX20-0007) | CY | 31 | $150.00 | $400.00 | $400.00 | $450.00 | $592.80 |
| 0001-0280 | NS geotextile fabric geogrid (303SX20-0008) | SY | 572 | $7.50 | $5.00 | $17.00 | $8.50 | $15.55 |
| 0001-0290 | Aggr. matl. no. 25 or 26 (305SD20-0011) | TON | 746.40 | $80.00 | $95.00 | $90.00 | $50.00 | $51.30 |
| 0001-0300 | Aggr. matl. no. 1 (308SD20-0001) | TON | 67 | $80.00 | $100.00 | $90.00 | $100.00 | $90.20 |
| 0001-0310 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 485 | $75.00 | $90.00 | $70.00 | $50.00 | $58.60 |
| 0001-0320 | Asphalt concrete TY. SM- 9.5D const (315SD20-0008) | TON | 321 | $250.00 | $192.00 | $250.00 | $350.00 | $252.55 |
| 0001-0330 | Asphalt concrete TY. BM- 25.0D const (315SD20-0011) | TON | 411 | $220.00 | $165.00 | $210.00 | $300.00 | $196.45 |
| 0001-0340 | NS saw-cut asph conc full depth sawcut (315SX20-0011) | LF | 588 | $5.00 | $18.00 | $10.00 | $6.00 | $9.30 |
| 0001-0350 | Cofferdam (401SD20-0007) | EACH | 4 | $75,000 | $15,000 | $30,000 | $15,000 | $20,000 |
| 0001-0360 | NS bridge substructure temporary shoring (401SX20-0011) | LS | 1 | $100,000 | $250,000 | $200,000 | $539,595 | $303,400 |
| 0001-0370 | Concrete parapet SSCP-1 (410SD20-0058) | LF | 53 | $750.00 | $900.00 | $890.00 | $1,590.00 | $890.00 |
| 0001-0380 | NS dism. & rem. exist. STR. 011-6246 (413SX20-0002) | LS | 1 | $40,000 | $125,000 | $145,000 | $25,500 | $434,000 |
| 0001-0390 | NS dism. & rem. exist. STR. headwall & wingwalls only (413SX20-0002) | LS | 1 | $35,000 | $65,000 | $60,000 | $77,000 | $218,000 |
| 0001-0400 | Erosion CTRL. stone CL. I, EC-1 (414SD20-0003) | TON | 237 | $85.00 | $100.00 | $95.00 | $90.00 | $69.25 |
| 0001-0410 | Dry riprap CL.I 26" (414SD20-0011) | SY | 490 | $120.00 | $150.00 | $100.00 | $100.00 | $79.55 |
| 0001-0420 | Comb. curb & gutter, STD. CG-6 (502SD20-0022) | LF | 240 | $90.00 | $62.00 | $115.00 | $125.00 | $97.80 |
| 0001-0430 | Concrete class A3 misc. (504SD20-0001) | CY | 3.20 | $4,000.00 | $500.00 | $2,600.00 | $2,000.00 | $1,644.30 |
| 0001-0440 | Guardrail GR-MGS1 (505SD20-0011) | LF | 188 | $45.00 | $41.00 | $40.00 | $52.00 | $42.70 |
| 0001-0450 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 2 | $5,000.00 | $4,600.00 | $4,500.00 | $5,500.00 | $4,880.00 |
| 0001-0460 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 2 | $2,000.00 | $1,800.00 | $1,750.00 | $2,500.00 | $1,830.00 |
| 0001-0470 | Alt.breakaway cable term. GR-9 (505SD20-0038) | EACH | 1 | $5,000.00 | $4,600.00 | $4,500.00 | $5,500.00 | $4,880.00 |
| 0001-0480 | Guardrail GR-10 (505SD20-0040) | LF | 25 | $50.00 | $46.00 | $50.00 | $55.00 | $48.80 |
| 0001-0490 | Fixed object attach. GR- foa-1 TY. I (505SD20-0045) | EACH | 4 | $4,000.00 | $3,400.00 | $3,500.00 | $4,000.00 | $3,660.00 |
| 0001-0500 | Remove existing guardrail (505SD20-0073) | LF | 520 | $10.00 | $12.00 | $12.00 | $20.00 | $12.20 |
| 0001-0510 | NS guardrail rad GR-2, 8' post (505SX20-0057) | LF | 38 | $55.00 | $52.00 | $55.00 | $65.00 | $54.90 |
| 0001-0520 | Demo. of pavement flexible (508SD20-0004) | SY | 482 | $40.00 | $25.00 | $27.00 | $80.00 | $25.05 |
| 0001-0530 | Relocate existing signal equipment relocate video detection zone (510SD20-0057) | LS | 1 | $20,000 | $15,000 | $8,000.00 | $5,500.00 | $5,326.30 |
| 0001-0540 | Allaying dust (511SD20-0001) | HR | 150 | $0.01 | $10.00 | $80.00 | $45.00 | $0.01 |
| 0001-0550 | Traffic barrier service MB-11A (512SD20-0003) | LF | 510 | $90.00 | $80.00 | $60.00 | $120.00 | $92.00 |
| 0001-0560 | Impact atten.ser. TY. 1 TL- 3, >=40 MPH (512SD20-0007) | EACH | 2 | $25,000 | $35,000 | $17,000 | $30,000 | $26,840 |
| 0001-0570 | Type 3 barricade 4' (512SD20-0012) | EACH | 2 | $650.00 | $500.00 | $400.00 | $375.00 | $848.20 |
| 0001-0580 | Type 3 barricade 8' (512SD20-0013) | EACH | 5 | $750.00 | $500.00 | $500.00 | $475.00 | $1,036.00 |
| 0001-0590 | Temporary sign (512SD20-0014) | SF | 693 | $40.00 | $28.00 | $22.00 | $42.50 | $22.00 |
| 0001-0600 | Truck mounted attenuator (512SD20-0023) | HR | 80 | $70.00 | $100.00 | $80.00 | $65.00 | $18.80 |
| 0001-0610 | Group 2 channelizing devices (512SD20-0024) | DAY | 3,782 | $4.00 | $3.00 | $3.00 | $1.75 | $1.85 |
| 0001-0620 | Port.changeable mess. sign (512SD20-0025) | HR | 3,936 | $20.00 | $3.00 | $5.00 | $10.00 | $3.90 |
| 0001-0630 | Electronic arrow board (512SD20-0026) | HR | 80 | $12.00 | $50.00 | $12.00 | $17.50 | $12.60 |
| 0001-0640 | Warning light TY. B (512SD20-0029) | DAY | 1,104 | $4.00 | $5.00 | $4.00 | $6.50 | $4.00 |
| 0001-0650 | Traffic barrier ser. conc. MB-7D PC (512SD20-0031) | LF | 30 | $110.00 | $100.00 | $70.00 | $120.00 | $142.40 |
| 0001-0660 | Eradicate linear PVMT MRKG (512SD20-0042) | LF | 465 | $2.35 | $2.20 | $2.20 | $5.00 | $7.10 |
| 0001-0670 | Temp. pave. marker 1 way (512SD20-0044) | EACH | 7 | $35.00 | $33.00 | $35.00 | $42.00 | $976.80 |
| 0001-0680 | Temp. PVMT MRKG TY. E, 6" (512SD20-0054) | LF | 1,680 | $5.85 | $5.50 | $6.00 | $6.30 | $8.45 |
| 0001-0690 | Temp. PVMT MRKG TY. D, CL. III, 4" (512SD20-0061) | LF | 1,150 | $4.40 | $4.10 | $5.00 | $4.75 | $7.65 |
| 0001-0700 | Temp. PVMT MRKG TY. D, CL. III, 6" (512SD20-0062) | LF | 325 | $5.25 | $4.80 | $5.40 | $5.60 | $8.80 |
| 0001-0710 | Temp. PVMT MRKG TY. D, CL. III, 8" (512SD20-0063) | LF | 530 | $6.20 | $5.65 | $6.00 | $6.60 | $16.00 |
| 0001-0720 | NS safety uniformed flaggers (512SX20-0045) | HR | 50 | $100.00 | $60.00 | $100.00 | $65.00 | $122.00 |
| 0001-0730 | Mobilization (513SD20-0001) | LS | 1 | $150,000 | $120,000 | $180,000 | $192,000 | $200,000 |
| 0001-0740 | Field office TY.I (514SD20-0001) | MO | 9 | $6,000.00 | $3,600.00 | $4,600.00 | $4,750.00 | $3,864.00 |
| 0001-0750 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 2,491 | $20.00 | $10.15 | $20.00 | $55.00 | $15.85 |
| 0001-0760 | Construction surveying constr. (517SD20-0001) | LS | 1 | $65,000 | $50,000 | $65,000 | $150,000 | $44,000 |
| 0001-0770 | Topsoil class B 3" (602SD20-0004) | CY | 121 | $150.00 | $160.00 | $175.00 | $150.00 | $124.00 |
| 0001-0780 | Temporary seed (603SD20-0002) | LB | 87 | $25.00 | $19.00 | $22.00 | $25.50 | $20.75 |
| 0001-0790 | Regular seed (603SD20-0003) | LB | 101 | $25.00 | $19.00 | $20.00 | $27.00 | $21.95 |
| 0001-0800 | Overseeding (603SD20-0004) | LB | 81 | $15.00 | $19.00 | $8.00 | $27.00 | $21.95 |
| 0001-0810 | Legume seed (603SD20-0005) | LB | 2 | $100.00 | $66.00 | $50.00 | $80.00 | $73.20 |
| 0001-0820 | Legume overseeding (603SD20-0006) | LB | 2 | $60.00 | $66.00 | $50.00 | $80.00 | $73.20 |
| 0001-0830 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 1,331 | $3.00 | $1.25 | $1.00 | $3.00 | $1.15 |
| 0001-0840 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 1,936 | $6.50 | $1.50 | $1.50 | $3.50 | $1.35 |
| 0001-0850 | Fertilizer nitrogen - N (603SD20-0014) | LB | 30 | $4.00 | $8.80 | $3.00 | $7.00 | $2.45 |
| 0001-0860 | Fertilizer phosphorous - P (603SD20-0015) | LB | 21 | $4.00 | $8.80 | $3.00 | $7.00 | $2.45 |
| 0001-0870 | Fertilizer potassium - K (603SD20-0016) | LB | 21 | $4.00 | $8.80 | $3.00 | $7.00 | $2.45 |
| 0001-0880 | Lime (603SD20-0017) | TON | 1.65 | $350.00 | $605.00 | $300.00 | $300.00 | $183.00 |
| 0001-0890 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 10 | $500.00 | $380.00 | $400.00 | $475.00 | $417.05 |
| 0001-0900 | Remove existing 1 post sign panel (700SD20-0007) | EACH | 10 | $350.00 | $285.00 | $300.00 | $192.00 | $301.70 |
| 0001-0910 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 66 | $55.00 | $50.00 | $50.00 | $25.00 | $53.25 |
| 0001-0920 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 6 | $1,750.00 | $1,600.00 | $1,600.00 | $1,118.00 | $1,687.80 |
| 0001-0930 | 14/7 conductor cable (700SD20-0114) | LF | 300 | $7.00 | $7.00 | $7.00 | $12.00 | $7.20 |
| 0001-0940 | Sign panel (701SD20-0001) | SF | 46.63 | $100.00 | $86.00 | $90.00 | $50.00 | $94.95 |
| 0001-0950 | Traf. sig. head sect. 12" HVS backplate (703SD20-0007) | EACH | 5 | $750.00 | $600.00 | $650.00 | $650.00 | $627.10 |
| 0001-0960 | Hanger assembly SM-3, one way (703SD20-0034) | EACH | 1 | $3,200.00 | $960.00 | $1,000.00 | $1,100.00 | $1,062.50 |
| 0001-0970 | Hanger assembly SMB-2, one way (703SD20-0037) | EACH | 3 | $3,200.00 | $665.00 | $700.00 | $760.00 | $737.10 |
| 0001-0980 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 2,500 | $3.50 | $3.25 | $3.50 | $4.00 | $18.85 |
| 0001-0990 | Type B class I PVMT line MRKG 24" (704SD20-0010) | LF | 100 | $30.00 | $27.50 | $30.00 | $35.00 | $35.80 |
| 0001-1000 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 13 | $600.00 | $550.00 | $600.00 | $650.00 | $231.10 |
| 0001-1010 | PVMT symb MRKG SGL turn arr. TY B CL I (704SD20-0047) | EACH | 7 | $400.00 | $342.00 | $400.00 | $400.00 | $346.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of December 17, 2025. Compiled by Mirage Metrics.