VDOT contract C0000119190C01 bid tabulation
Smart scale - intersection improvements. Let by Virginia DOT on February 4, 2026, Brunswick, Richmond. 2 bids received; low bid $2,587,778 by Gray and Sons Construction, Inc..
- Owner
- Virginia DOT
- Letting
- 04 FEB 2026
- Pay items
- 87
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Gray and Sons Construction, Inc. | $2,587,778 | Low |
| 2 | W. C. English, Incorporated | $3,476,232 | +34% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gray and Sons Construction, Inc. | 2. W. C. English, Incorporated |
|---|---|---|---|---|---|
| 0001-0010 | Clearing and grubbing (301SD20-0001) | LS | 1 | $10,000 | $6,900.00 |
| 0001-0020 | Reinf. steel (302SD20-0005) | LB | 402 | $10.00 | $3.25 |
| 0001-0030 | Endwall grate & frame EW-11A (302SD20-0012) | EACH | 2 | $6,800.00 | $11,199 |
| 0001-0040 | 15" storm sewer pipe (302SD20-0027) | LF | 10 | $170.00 | $152.00 |
| 0001-0050 | 18" pipe (302SD20-0028) | LF | 139 | $240.00 | $151.50 |
| 0001-0060 | 18" storm sewer pipe (302SD20-0032) | LF | 10 | $210.00 | $202.25 |
| 0001-0070 | 24" end section ES-1 (302SD20-0205) | EACH | 2 | $4,500.00 | $8,849.75 |
| 0001-0080 | Drop inlet DI-7 (302SD20-0447) | EACH | 1 | $7,000.00 | $15,239 |
| 0001-0090 | Frame & cover MH-1 (302SD20-0663) | EACH | 1 | $1,150.00 | $3,902.75 |
| 0001-0100 | Pipe rehabilitation (42", method B, category D) (302SP20-0001) | LF | 86 | $760.00 | $775.00 |
| 0001-0110 | NS drop inlet convert exist. DI to MH (302SX20-0026) | EACH | 1 | $13,500 | $14,600 |
| 0001-0120 | Regular excavation (303SD20-0001) | CY | 2,846 | $60.00 | $131.75 |
| 0001-0130 | Borrow excavation (303SD20-0007) | CY | 5,843 | $65.00 | $70.25 |
| 0001-0140 | Check dam rock TY. II (303SD20-0023) | EACH | 22 | $450.00 | $413.00 |
| 0001-0150 | Siltation control excavation (303SD20-0029) | CY | 324 | $4.86 | $0.01 |
| 0001-0160 | Inlet protection type A (303SD20-0030) | EACH | 3 | $300.00 | $385.00 |
| 0001-0170 | Temp. silt fence type A (303SD20-0034) | LF | 1,600 | $8.00 | $5.25 |
| 0001-0180 | Select matl. TY. I min. CBR- 30 (305SD20-0005) | TON | 3,733 | $65.00 | $56.75 |
| 0001-0190 | Manual shoulders restoration (305SP20-0006) | LF | 220 | $30.00 | $14.50 |
| 0001-0200 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 965 | $68.00 | $59.50 |
| 0001-0210 | Asphalt concrete TY. SM- 12.5E const (315SD20-0003) | TON | 520 | $270.00 | $648.00 |
| 0001-0220 | Asphalt concrete TY. IM- 19.0D const (315SD20-0005) | TON | 380 | $270.00 | $540.00 |
| 0001-0230 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 550 | $195.00 | $516.00 |
| 0001-0240 | NS saw-cut asph conc full depth (315SX20-0011) | LF | 1,820 | $19.00 | $8.75 |
| 0001-0250 | Underdrain UD-4 (501SD20-0004) | LF | 777 | $40.00 | $15.50 |
| 0001-0260 | Outlet pipe (501SD20-0009) | LF | 10 | $40.00 | $61.25 |
| 0001-0270 | Paved ditch PG-2A (502SD20-0003) | SY | 374 | $67.00 | $306.75 |
| 0001-0280 | Median strip MS-1 (502SD20-0053) | SY | 119 | $600.00 | $321.25 |
| 0001-0290 | Median strip MS-1A (502SD20-0056) | SY | 95 | $600.00 | $390.75 |
| 0001-0300 | Concrete class A3 misc. (504SD20-0001) | CY | 4.60 | $860.00 | $807.50 |
| 0001-0310 | Remove EX. guardrail terminal (505SD20-0009) | EACH | 3 | $100.00 | $748.50 |
| 0001-0320 | Guardrail GR-MGS1 (505SD20-0011) | LF | 107 | $70.00 | $39.75 |
| 0001-0330 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 2 | $9,000.00 | $4,350.00 |
| 0001-0340 | Guardrail end anchorage GR-MGS3 (505SD20-0018) | EACH | 1 | $5,600.00 | $3,000.00 |
| 0001-0350 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 5 | $2,000.00 | $1,800.00 |
| 0001-0360 | Guardrail ter.site preparation (505SD20-0039) | EACH | 2 | $1,200.00 | $720.00 |
| 0001-0370 | Cable barricade CR-1 (505SD20-0066) | EACH | 1 | $5,500.00 | $3,000.00 |
| 0001-0380 | Remove existing guardrail (505SD20-0073) | LF | 595 | $15.00 | $7.50 |
| 0001-0390 | Obscuring roadway (508SD20-0001) | UNIT | 5 | $1,500.00 | $977.00 |
| 0001-0400 | Demo. of pavement flexible (508SD20-0004) | SY | 1,943 | $17.00 | $15.75 |
| 0001-0410 | NS remove exist. raised pavement marker (510SX20-0040) | EACH | 95 | $40.00 | $15.50 |
| 0001-0420 | Allaying dust (511SD20-0001) | HR | 200 | $10.00 | $0.01 |
| 0001-0430 | Impact atten.ser. TY. 1 TL- 3, >=40 MPH (512SD20-0007) | EACH | 3 | $13,000 | $11,100 |
| 0001-0440 | Type 3 barricade 8' (512SD20-0013) | EACH | 2 | $600.00 | $400.00 |
| 0001-0450 | Temporary sign (512SD20-0014) | SF | 378 | $45.00 | $34.00 |
| 0001-0460 | Truck mounted attenuator (512SD20-0023) | HR | 140 | $180.00 | $26.50 |
| 0001-0470 | Group 2 channelizing devices (512SD20-0024) | DAY | 11,160 | $3.00 | $0.75 |
| 0001-0480 | Electronic arrow board (512SD20-0026) | HR | 8,640 | $2.10 | $0.50 |
| 0001-0490 | Flagger service (512SD20-0027) | HR | 1,080 | $60.00 | $50.00 |
| 0001-0500 | Warning light TY. B (512SD20-0029) | DAY | 360 | $10.00 | $10.50 |
| 0001-0510 | Traffic barrier ser. conc. MB-7D PC (512SD20-0031) | LF | 2,884 | $45.00 | $46.00 |
| 0001-0520 | Temp. pave. marker 1 way (512SD20-0044) | EACH | 66 | $30.00 | $18.00 |
| 0001-0530 | Temp. PVMT MRKG TY. E, 6" (512SD20-0054) | LF | 1,823 | $4.00 | $4.00 |
| 0001-0540 | Temp. PVMT MRKG TY. D, CL. III, 6" (512SD20-0062) | LF | 2,684 | $4.00 | $3.75 |
| 0001-0550 | Temp. PVMT MRKG TY. D, CL. III, 8" (512SD20-0063) | LF | 2,340 | $4.00 | $4.00 |
| 0001-0560 | Portable temporary rumble strip array (512SP20-0001) | DAY | 1,080 | $11.00 | $20.50 |
| 0001-0570 | Mobilization (513SD20-0001) | LS | 1 | $200,000 | $557,544 |
| 0001-0580 | Field office TY.II (514SD20-0002) | MO | 10 | $8,500.00 | $4,080.00 |
| 0001-0590 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 2,250 | $25.00 | $30.00 |
| 0001-0600 | Construction surveying constr. (517SD20-0001) | LS | 1 | $20,000 | $47,790 |
| 0001-0610 | Mailbox post, multiple (521SD20-0003) | EACH | 4 | $50.00 | $344.00 |
| 0001-0620 | Topsoil class B 2" (602SD20-0003) | ACRE | 0.90 | $20,000 | $16,573 |
| 0001-0630 | Temporary seed (603SD20-0002) | LB | 95 | $25.00 | $5.50 |
| 0001-0640 | Regular seed (603SD20-0003) | LB | 255 | $25.00 | $7.25 |
| 0001-0650 | Overseeding (603SD20-0004) | LB | 204 | $50.00 | $5.50 |
| 0001-0660 | Legume seed (603SD20-0005) | LB | 11 | $50.00 | $26.50 |
| 0001-0670 | Legume overseeding (603SD20-0006) | LB | 9 | $50.00 | $26.50 |
| 0001-0680 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 5,385 | $2.00 | $1.25 |
| 0001-0690 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 4,961 | $2.00 | $1.25 |
| 0001-0700 | Fertilizer nitrogen - N (603SD20-0014) | LB | 95 | $25.00 | $7.25 |
| 0001-0710 | Fertilizer phosphorous - P (603SD20-0015) | LB | 67 | $25.00 | $7.25 |
| 0001-0720 | Fertilizer potassium - K (603SD20-0016) | LB | 67 | $25.00 | $7.25 |
| 0001-0730 | Lime (603SD20-0017) | TON | 5.20 | $90.00 | $168.00 |
| 0001-0740 | Rolled erosion CTRL product EC-2 type 2 (606SD20-0002) | SY | 77 | $1.50 | $2.50 |
| 0001-0750 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 19 | $60.00 | $148.00 |
| 0001-0760 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 187 | $36.00 | $24.00 |
| 0001-0770 | Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036) | LF | 11 | $36.00 | $27.50 |
| 0001-0780 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 66 | $28.00 | $26.50 |
| 0001-0790 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 21 | $400.00 | $474.00 |
| 0001-0800 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 1 | $600.00 | $594.00 |
| 0001-0810 | Sign panel (701SD20-0001) | SF | 169 | $44.00 | $66.50 |
| 0001-0820 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 3,126 | $3.00 | $2.00 |
| 0001-0830 | Type B class I PVMT line MRKG 8" (704SD20-0008) | LF | 133 | $7.00 | $6.00 |
| 0001-0840 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 139 | $100.00 | $51.50 |
| 0001-0850 | Symb MRKG lane reduction arr TY B CL II (704SD20-0060) | EACH | 2 | $500.00 | $414.00 |
| 0001-0860 | PVMT symb MRKG yield 2' X 3' TY B, CL II (704SD20-0087) | EACH | 8 | $600.00 | $36.00 |
| 0001-0870 | Removal of SRPM (704SP20-0001) | EACH | 17 | $100.00 | $300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of February 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.