VDOT contract C0000107309M01 bid tabulation
Retaining wall and road safety improvements. Let by Virginia DOT on May 27, 2026, Roanoke, Salem. 4 bids received; low bid $2,475,173 by Burleigh Construction Co., Inc..
- Owner
- Virginia DOT
- Letting
- 27 MAY 2026
- Pay items
- 67
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Burleigh Construction Co., Inc. | $2,475,173 | Low |
| 2 | Archer Western Construction, LLC | $2,697,584 | +9.0% |
| 3 | Brayman Construction Corporation | $2,991,896 | +21% |
| 4 | King General Contractors, Inc. | $3,699,989 | +49% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Burleigh Construction Co., Inc. | 2. Archer Western Construction, LLC | 3. Brayman Construction Corporation | 4. King General Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 0001-0010 | 6" pipe (302SD20-0014) | LF | 39 | $137.00 | $60.75 | $330.00 | $16.61 |
| 0001-0020 | 8" pipe (302SD20-0016) | LF | 42 | $137.00 | $71.85 | $330.00 | $21.09 |
| 0001-0030 | 24" conc. pipe (302SD20-0039) | LF | 49 | $365.00 | $360.00 | $500.00 | $259.43 |
| 0001-0040 | 24" end section ES-1 (302SD20-0205) | EACH | 1 | $2,750.00 | $3,708.00 | $8,500.00 | $2,254.98 |
| 0001-0050 | Regular excavation (303SD20-0001) | CY | 313 | $55.00 | $80.19 | $225.00 | $217.26 |
| 0001-0060 | Check dam rock TY. II (303SD20-0023) | EACH | 17 | $2,000.00 | $370.00 | $860.00 | $681.21 |
| 0001-0070 | Dewatering basin EC-8 (303SD20-0028) | EACH | 2 | $2,000.00 | $800.00 | $13,000 | $2,180.92 |
| 0001-0080 | Siltation control excavation (303SD20-0029) | CY | 216 | $1.00 | $66.36 | $10.00 | $25.56 |
| 0001-0090 | Geotextile fabric (303SD20-0032) | SY | 66 | $27.50 | $8.78 | $35.00 | $13.74 |
| 0001-0100 | Temp. silt fence type B (303SD20-0033) | LF | 819 | $10.00 | $5.88 | $50.00 | $13.42 |
| 0001-0110 | Temp. silt fence type A (303SD20-0034) | LF | 421 | $11.00 | $5.69 | $50.00 | $11.82 |
| 0001-0120 | NS access road (temporary construction access) (303SX20-0010) | LS | 1 | $69,500 | $489,601 | $203,600 | $170,741 |
| 0001-0130 | Aggr.base mat.TY. I no.21A or 21B (305SD20-0012) | TON | 307 | $65.00 | $80.20 | $125.00 | $171.02 |
| 0001-0140 | Lime (306SD20-0001) | TON | 2.64 | $200.00 | $38.42 | $150.00 | $288.13 |
| 0001-0150 | Crusher run aggr. no. 25 or 26 (308SX20-0003) | TON | 165 | $63.00 | $105.49 | $260.00 | $79.01 |
| 0001-0160 | Asphalt concrete TY. IM- 19.0A const (315SD20-0004) | TON | 163 | $270.00 | $265.00 | $210.00 | $412.99 |
| 0001-0170 | Asphalt concrete TY. SM- 9.5D const (315SD20-0008) | TON | 71 | $500.00 | $415.00 | $312.00 | $451.40 |
| 0001-0180 | Saw-cut asphalt concrete (full depth) (315SD20-0104) | LF | 400 | $14.00 | $5.00 | $41.15 | $22.37 |
| 0001-0190 | Cofferdam (401SD20-0007) | EACH | 2 | $24,000 | $50,000 | $40,000 | $21,726 |
| 0001-0200 | NS bridge substructure (grouted anchors) (401SX20-0008) | EACH | 12 | $17,633 | $11,500 | $17,500 | $32,280 |
| 0001-0210 | NS pile (micropiles) (403SX20-0018) | LF | 324 | $845.00 | $860.26 | $190.00 | $607.05 |
| 0001-0220 | Concrete class A4, substruct. const. (404SD20-0012) | CY | 67 | $6,300.00 | $2,591.10 | $6,500.00 | $1,705.17 |
| 0001-0230 | NS bridge superstructure (precast moment slabs) (410SX20-0008) | LF | 150 | $3,775.00 | $3,323.86 | $3,500.00 | $7,736.60 |
| 0001-0240 | NS parapet SSCP-1 (410SX20-0020) | LF | 150 | $425.00 | $893.60 | $1,250.00 | $408.96 |
| 0001-0250 | Erosion CTRL. stone CL. I, EC-1 (414SD20-0003) | TON | 7 | $410.00 | $305.14 | $800.00 | $225.69 |
| 0001-0260 | Dry riprap CL.I 26" (414SD20-0012) | TON | 32 | $140.00 | $181.81 | $170.00 | $172.02 |
| 0001-0270 | Dry riprap CL.II 38" (414SD20-0057) | TON | 141 | $110.00 | $184.42 | $190.00 | $168.86 |
| 0001-0280 | Curb, STD. CG-2 (502SD20-0011) | LF | 73 | $89.00 | $150.00 | $330.00 | $127.80 |
| 0001-0290 | Curb, radial CG-2 (502SD20-0012) | LF | 19 | $96.00 | $280.00 | $330.00 | $89.46 |
| 0001-0300 | Curb, STD. CG-3 (502SD20-0014) | LF | 27 | $103.00 | $270.00 | $330.00 | $95.85 |
| 0001-0310 | Concrete class A3 misc. (504SD20-0001) | CY | 2 | $2,050.00 | $2,035.00 | $3,500.00 | $1,868.72 |
| 0001-0320 | Guardrail GR-MGS1 (505SD20-0011) | LF | 25 | $110.00 | $41.10 | $32.00 | $153.67 |
| 0001-0330 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 1 | $3,425.00 | $2,568.53 | $2,000.00 | $4,802.09 |
| 0001-0340 | Fixed object attach. GR- foa-5 (505SD20-0055) | EACH | 1 | $8,900.00 | $9,827.41 | $8,000.00 | $14,406 |
| 0001-0350 | Remove existing guardrail (505SD20-0073) | LF | 37 | $62.00 | $15.00 | $10.00 | $51.12 |
| 0001-0360 | NS wall (precast modular retaining wall) (506SX20-0002) | SF | 213 | $320.00 | $244.98 | $630.00 | $2,052.46 |
| 0001-0370 | Fence FE-W1 (507SD20-0001) | LF | 191 | $50.00 | $56.65 | $60.00 | $92.66 |
| 0001-0380 | Corner brace unit FE-W1 or FE-W2 (507SD20-0004) | EACH | 6 | $685.00 | $1,000.00 | $800.00 | $1,214.10 |
| 0001-0390 | Demo. of pavement flexible (508SD20-0004) | SY | 300 | $27.50 | $50.00 | $35.00 | $35.15 |
| 0001-0400 | NS remove exist. fence . (510SX20-0016) | LF | 209 | $20.50 | $25.00 | $8.00 | $12.78 |
| 0001-0410 | Type 3 barricade 8' (512SD20-0013) | EACH | 2 | $480.00 | $5.00 | $2,500.00 | $415.35 |
| 0001-0420 | Temporary sign (512SD20-0014) | SF | 250 | $27.50 | $60.00 | $20.00 | $38.34 |
| 0001-0430 | Group 2 channelizing devices (512SD20-0024) | DAY | 4,872 | $1.50 | $0.08 | $0.15 | $1.92 |
| 0001-0440 | Port.changeable mess. sign (512SD20-0025) | HR | 6,048 | $9.50 | $2.17 | $12.00 | $15.34 |
| 0001-0450 | Flagger service (512SD20-0027) | HR | 1,272 | $41.00 | $49.23 | $75.00 | $109.49 |
| 0001-0460 | Temp. PVMT MRKG TY. A, 4" (512SD20-0046) | LF | 1,420 | $6.85 | $4.50 | $5.00 | $9.61 |
| 0001-0470 | Mobilization (513SD20-0001) | LS | 1 | $150,000 | $164,553 | $170,000 | $203,202 |
| 0001-0480 | Field office TY.I (514SD20-0001) | MO | 14 | $4,100.00 | $4,100.00 | $3,000.00 | $6,390.00 |
| 0001-0490 | Flex. pave.tie-in planing above 2"-4" (515SD20-0003) | SY | 374 | $45.00 | $40.00 | $32.00 | $54.32 |
| 0001-0500 | Construction surveying min. plan (517SD20-0002) | LS | 1 | $33,000 | $140,000 | $165,000 | $53,676 |
| 0001-0510 | Topsoil class B (602SD20-0004) | CY | 194 | $82.00 | $109.52 | $175.29 | $149.53 |
| 0001-0520 | Temporary seed (603SD20-0002) | LB | 106 | $1.00 | $4.15 | $16.00 | $30.74 |
| 0001-0530 | Regular seed (603SD20-0003) | LB | 132 | $82.25 | $4.15 | $17.00 | $32.65 |
| 0001-0540 | Overseeding (603SD20-0004) | LB | 106 | $1.00 | $4.15 | $17.00 | $32.65 |
| 0001-0550 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 2,239 | $1.25 | $0.75 | $0.90 | $1.73 |
| 0001-0560 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 2,323 | $1.50 | $1.35 | $1.05 | $2.02 |
| 0001-0570 | Hydraulic erosion control product type 4 (603SD20-0010) | SY | 666 | $1.75 | $1.80 | $1.25 | $2.40 |
| 0001-0580 | Fertilizer nitrogen - N (603SD20-0014) | LB | 48 | $3.00 | $1.30 | $2.25 | $4.32 |
| 0001-0590 | Fertilizer phosphorous - P (603SD20-0015) | LB | 34 | $3.00 | $1.30 | $2.25 | $4.32 |
| 0001-0600 | Fertilizer potassium - K (603SD20-0016) | LB | 34 | $3.00 | $1.30 | $2.25 | $4.32 |
| 0001-0610 | Rolled erosion CTRL product EC-2 type 1 (606SD20-0001) | SY | 20 | $7.00 | $6.15 | $5.00 | $9.61 |
| 0001-0620 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 6 | $192.00 | $446.00 | $140.00 | $319.50 |
| 0001-0630 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 105 | $35.00 | $20.50 | $25.00 | $48.03 |
| 0001-0640 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 7 | $685.00 | $705.00 | $500.00 | $960.42 |
| 0001-0650 | Sign panel (701SD20-0001) | SF | 36 | $75.00 | $29.00 | $55.00 | $105.65 |
| 0001-0660 | Type A PVMT line MRKG 4" (704SD20-0001) | LF | 1,290 | $6.85 | $4.45 | $5.00 | $9.61 |
| 0001-0670 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 22 | $220.00 | $75.00 | $160.00 | $307.33 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of May 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.