Dry riprap CL.II 38", VDOT 414SD20-0057
Low bidders on VDOT contracts carried a median of $110.00 per TON for this item, over the 24 months to 28 OCT 2026, across 7 low bids. Half of all 36 bids fell between $121.25 and $196.25.
- Owner
- Virginia DOT
- Item
- 414SD20-0057
- Unit
- TON
- Data through
- 28 OCT 2026
VDOT prints this item as “DRY RIPRAP CL.II 38"”.
VDOT has bid this work under more than one code: 66239 on lettings from 26 FEB 2002 to 25 AUG 2021 (389 bids); 414SD20-0057 on lettings from 19 NOV 2025 to 22 JUL 2026 (36 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 10 | 10 | $34.75 | 29 | $35.00 |
| 2003 | 3 | 3 | $37.00 | 9 | $37.50 |
| 2004 | 9 | 9 | $42.90 | 24 | $43.95 |
| 2005 | 5 | 5 | $40.00 | 14 | $39.80 |
| 2006 | 8 | 8 | $36.14 | 24 | $40.00 |
| 2007 | 5 | 5 | $45.00 | 14 | $45.00 |
| 2009 | 7 | 7 | $36.52 | 21 | $38.00 |
| 2010 | 5 | 5 | $32.00 | 14 | $46.25 |
| 2011 | 6 | 6 | $65.00 | 18 | $68.00 |
| 2012 | 7 | 7 | $60.00 | 21 | $53.00 |
| 2013 | 10 | 10 | $48.50 | 30 | $50.00 |
| 2014 | 10 | 10 | $59.00 | 26 | $58.26 |
| 2015 | 11 | 11 | $62.00 | 26 | $58.50 |
| 2016 | 11 | 10 | $52.00 | 31 | $54.00 |
| 2017 | 4 | 4 | $65.00 | 12 | $60.60 |
| 2018 | 5 | 5 | $70.00 | 15 | $65.00 |
| 2019 | 10 | 10 | $75.00 | 30 | $78.40 |
| 2020 | 6 | 6 | $69.20 | 18 | $79.70 |
| 2021 | 4 | 4 | $56.13 | 12 | $78.00 |
| 2025 | 1 | 1 | $85.00 | 3 | $92.00 |
| 2026 | 6 | 6 | $122.50 | 33 | $169.01 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Staunton | 39 | $55.00 | 114 | $60.00 |
| Bristol | 30 | $30.00 | 90 | $35.00 |
| Lynchburg | 20 | $47.50 | 57 | $50.00 |
| Salem | 15 | $49.00 | 46 | $51.00 |
| Culpeper | 11 | $71.16 | 41 | $80.00 |
| Richmond | 14 | $66.12 | 36 | $72.00 |
| Fredericksburg | 6 | $73.00 | 18 | $74.00 |
| Hampton Roads | 4 | $95.00 | 12 | $75.00 |
| Northern Virginia | 3 | $76.00 | 10 | $78.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 16 to 186 | 35 | $43.14 |
| 187 to 388 | 36 | $49.50 |
| 392 to 690 | 35 | $58.75 |
| 690 to 11,170 | 36 | $60.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Patrick Construction, Inc. | 15 | 14 (93%) |
| Burleigh Construction Co., Inc. | 29 | 13 (45%) |
| Fairfield-Echols, LLC | 29 | 13 (45%) |
| Elk Knob, Inc. | 19 | 10 (53%) |
| Crossroads Bridge Inc | 18 | 7 (39%) |
| A. R. Coffey and Sons, Inc. | 11 | 6 (55%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | C0000118431B20 | Culpeper | 494 | $135.00 | $169.70 | 6 | Freyssinet, Inc. | VDOT |
| 22 JUL 2026 | C0000121138B52 | Bristol | 456 | $58.75 | $62.98 | 5 | Elk Knob, Inc. | VDOT |
| 27 MAY 2026 | C0000118430B39 | Culpeper | 562 | $146.05 | $192.50 | 8 | Burleigh Construction Co., Inc. | VDOT |
| 27 MAY 2026 | C0000107309M01 | Salem | 141 | $110.00 | $176.64 | 4 | Burleigh Construction Co., Inc. | VDOT |
| 25 FEB 2026 | C0000117021B19 | Staunton | 276 | $140.00 | $140.00 | 5 | Freyssinet, Inc. | VDOT |
| 25 FEB 2026 | C0000115132M01 | Staunton | 16 | $110.00 | $200.00 | 5 | A & J Development and Excavation, Inc. | VDOT |
| 19 NOV 2025 | C0000116160B01 | Bristol | 249 | $85.00 | $92.00 | 3 | Caton Construction Group, Inc. | VDOT |
| 25 AUG 2021 | C0000111282B24 | Lynchburg | 770 | $76.00 | $80.00 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 24 MAR 2021 | C0000110433B43 | Northern Virginia | 360 | $61.26 | $125.00 | 3 | Clearwater Construction, Inc. | VDOT |
| 24 FEB 2021 | C0000104828B73 | Bristol | 572 | $51.00 | $62.00 | 3 | Jones Road & Bridge, Inc. | VDOT |
| 20 JAN 2021 | CM820BRA117425 | Staunton | 233 | $50.00 | $80.00 | 3 | Jones Road & Bridge, Inc. | VDOT |
| 16 DEC 2020 | C0000090178B02 | Staunton | 75 | $64.54 | $65.00 | 3 | Kanawha Stone Company, Inc. | VDOT |
| 18 NOV 2020 | C00110097B609 | Fredericksburg | 318 | $98.00 | $98.00 | 3 | Bryant Structures, Inc. | VDOT |
| 21 OCT 2020 | C0000101238B22 | Richmond | 409 | $67.25 | $90.64 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 22 APR 2020 | C0000094725B58 | Salem | 187 | $56.50 | $56.50 | 3 | Crossroads Bridge Inc | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.