Erosion CTRL. stone CL. II, EC-1, VDOT 414SD20-0005
Low bidders on VDOT contracts carried a median of $110.00 per TON for this item, over the 24 months to 28 OCT 2026, across 5 low bids. Half of all 9 bids fell between $110.00 and $199.69.
- Owner
- Virginia DOT
- Item
- 414SD20-0005
- Unit
- TON
- Data through
- 28 OCT 2026
VDOT prints this item as “EROSION CTRL. STONE CL. II, EC-1”.
VDOT has bid this work under more than one code: 9152 on lettings from 29 JAN 2002 to 17 NOV 2021 (247 bids); 414SD20-0005 on lettings from 22 OCT 2025 to 22 JUL 2026 (9 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 6 | 6 | $31.00 | 18 | $30.00 |
| 2003 | 1 | 1 | $30.00 | 3 | $30.00 |
| 2004 | 5 | 5 | $50.00 | 8 | $50.00 |
| 2005 | 6 | 6 | $55.00 | 12 | $57.50 |
| 2006 | 4 | 4 | $30.00 | 12 | $35.50 |
| 2007 | 2 | 2 | $64.75 | 5 | $82.50 |
| 2008 | 4 | 4 | $43.30 | 12 | $41.00 |
| 2009 | 5 | 5 | $60.00 | 15 | $60.00 |
| 2010 | 3 | 3 | $39.34 | 9 | $39.34 |
| 2012 | 4 | 4 | $51.50 | 11 | $50.00 |
| 2013 | 9 | 9 | $73.00 | 21 | $86.50 |
| 2014 | 5 | 5 | $70.00 | 14 | $60.50 |
| 2015 | 11 | 11 | $74.00 | 32 | $74.50 |
| 2016 | 8 | 7 | $68.00 | 20 | $80.00 |
| 2017 | 5 | 5 | $70.00 | 15 | $105.00 |
| 2018 | 2 | 2 | $127.50 | 5 | $140.09 |
| 2019 | 3 | 3 | $53.05 | 8 | $62.02 |
| 2020 | 8 | 8 | $76.00 | 20 | $76.00 |
| 2021 | 2 | 2 | $93.00 | 6 | $93.00 |
| 2025 | 2 | 2 | $165.00 | 3 | $230.00 |
| 2026 | 3 | 3 | $110.00 | 6 | $144.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Salem | 29 | $50.21 | 80 | $52.25 |
| Staunton | 14 | $60.00 | 34 | $55.00 |
| Northern Virginia | 10 | $75.00 | 26 | $82.50 |
| Culpeper | 9 | $74.00 | 23 | $80.00 |
| Lynchburg | 9 | $80.00 | 22 | $64.50 |
| Bristol | 7 | $30.00 | 21 | $35.00 |
| Hampton Roads | 7 | $155.00 | 18 | $161.50 |
| Fredericksburg | 7 | $90.29 | 16 | $92.65 |
| Richmond | 5 | $82.50 | 15 | $97.60 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 3 to 24 | 24 | $61.00 |
| 28 to 63.70 | 24 | $60.60 |
| 66 to 200 | 24 | $70.00 |
| 206 to 1,225 | 25 | $47.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| DLB, Inc. | 19 | 9 (47%) |
| Burleigh Construction Co., Inc. | 8 | 5 (63%) |
| W. C. English, Incorporated | 8 | 4 (50%) |
| Arthur Construction Co., Inc. | 5 | 4 (80%) |
| Sowers Construction Co., Inc. | 8 | 3 (38%) |
| Boring Contractors, Inc. | 6 | 3 (50%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | C0000115403C01C | Richmond | 131.80 | $110.00 | $125.00 | 3 | MCC ACQUISITION, LC dba VIRGINIA-CAROLINA | VDOT |
| 24 JUN 2026 | C0000108810C01 | Staunton | 63.70 | $91.00 | $127.50 | 2 | A & J Development and Excavation, Inc. | VDOT |
| 22 APR 2026 | C0000118863C01 | Culpeper | 99 | $187.24 | $187.24 | 1 | Caton Construction Group, Inc. | VDOT |
| 17 DEC 2025 | C0000121000D04 | Salem | 428.90 | $100.00 | $297.63 | 2 | Crossroads Bridge Inc | VDOT |
| 22 OCT 2025 | C000117033M01D | Hampton Roads | 11 | $230.00 | $230.00 | 1 | Joseph B. Fay Co. | VDOT |
| 17 NOV 2021 | CM521000118502 | Hampton Roads | 50 | $101.00 | $101.00 | 3 | Tri-State Utilities Co. | VDOT |
| 22 SEP 2021 | C0000117020D36 | Salem | 329 | $85.00 | $85.00 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 18 NOV 2020 | C0000109419C01 | Bristol | 275 | $46.49 | $49.00 | 3 | Phillips Construction, LLC of Ky(Use In Va By:Phillips Const | VDOT |
| 23 SEP 2020 | C0000116960N01 | Fredericksburg | 150 | $72.00 | $91.00 | 2 | Caton Construction Group, Inc. | VDOT |
| 23 SEP 2020 | C000115806N01B | Hampton Roads | 50 | $175.00 | $175.00 | 3 | Henry S. Branscome, L.L.C. | VDOT |
| 26 AUG 2020 | C0000116959N01 | Fredericksburg | 150 | $100.00 | $91.00 | 2 | Curtis Contracting, Inc. | VDOT |
| 27 MAY 2020 | 00116067N01 | Culpeper | 288 | $80.00 | $127.50 | 2 | Caton Construction Group, Inc. | VDOT |
| 25 MAR 2020 | C0000094726C01 | Salem | 40 | $55.00 | $60.00 | 3 | Jones Road & Bridge, Inc. | VDOT |
| 26 FEB 2020 | C0000108907C01 | Salem | 775 | $52.50 | $52.86 | 3 | W. C. English, Incorporated | VDOT |
| 22 JAN 2020 | C0000115748N01 | Hampton Roads | 50 | $215.00 | $263.75 | 2 | Ipr Northeast LLC | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way