Erosion CTRL. stone CL. II, EC-1, VDOT 414SD20-0005

Low bidders on VDOT contracts carried a median of $110.00 per TON for this item, over the 24 months to 28 OCT 2026, across 5 low bids. Half of all 9 bids fell between $110.00 and $199.69.

Owner
Virginia DOT
Item
414SD20-0005
Unit
TON
Data through
28 OCT 2026

VDOT prints this item as “EROSION CTRL. STONE CL. II, EC-1”.

VDOT has bid this work under more than one code: 9152 on lettings from 29 JAN 2002 to 17 NOV 2021 (247 bids); 414SD20-0005 on lettings from 22 OCT 2025 to 22 JUL 2026 (9 bids). They are combined here into one trend.

$110.00Low bidder's median, per TON
$164.00Median of all bids, per TON
5Contracts in the window

By year of letting

Erosion CTRL. stone CL. II, EC-1, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200266$31.0018$30.00
200311$30.003$30.00
200455$50.008$50.00
200566$55.0012$57.50
200644$30.0012$35.50
200722$64.755$82.50
200844$43.3012$41.00
200955$60.0015$60.00
201033$39.349$39.34
201244$51.5011$50.00
201399$73.0021$86.50
201455$70.0014$60.50
20151111$74.0032$74.50
201687$68.0020$80.00
201755$70.0015$105.00
201822$127.505$140.09
201933$53.058$62.02
202088$76.0020$76.00
202122$93.006$93.00
202522$165.003$230.00
202633$110.006$144.50

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Salem29$50.2180$52.25
Staunton14$60.0034$55.00
Northern Virginia10$75.0026$82.50
Culpeper9$74.0023$80.00
Lynchburg9$80.0022$64.50
Bristol7$30.0021$35.00
Hampton Roads7$155.0018$161.50
Fredericksburg7$90.2916$92.65
Richmond5$82.5015$97.60
Erosion CTRL. stone CL. II, EC-1, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (TON)Low bidsLow-bid median
3 to 2424$61.00
28 to 63.7024$60.60
66 to 20024$70.00
206 to 1,22525$47.00
Erosion CTRL. stone CL. II, EC-1, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
DLB, Inc.199 (47%)
Burleigh Construction Co., Inc.85 (63%)
W. C. English, Incorporated84 (50%)
Arthur Construction Co., Inc.54 (80%)
Sowers Construction Co., Inc.83 (38%)
Boring Contractors, Inc.63 (50%)
Erosion CTRL. stone CL. II, EC-1, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
22 JUL 2026C0000115403C01CRichmond131.80$110.00$125.003MCC ACQUISITION, LC dba VIRGINIA-CAROLINAVDOT
24 JUN 2026C0000108810C01Staunton63.70$91.00$127.502A & J Development and Excavation, Inc.VDOT
22 APR 2026C0000118863C01Culpeper99$187.24$187.241Caton Construction Group, Inc.VDOT
17 DEC 2025C0000121000D04Salem428.90$100.00$297.632Crossroads Bridge IncVDOT
22 OCT 2025C000117033M01DHampton Roads11$230.00$230.001Joseph B. Fay Co.VDOT
17 NOV 2021CM521000118502Hampton Roads50$101.00$101.003Tri-State Utilities Co.VDOT
22 SEP 2021C0000117020D36Salem329$85.00$85.003Burleigh Construction Co., Inc.VDOT
18 NOV 2020C0000109419C01Bristol275$46.49$49.003Phillips Construction, LLC of Ky(Use In Va By:Phillips ConstVDOT
23 SEP 2020C0000116960N01Fredericksburg150$72.00$91.002Caton Construction Group, Inc.VDOT
23 SEP 2020C000115806N01BHampton Roads50$175.00$175.003Henry S. Branscome, L.L.C.VDOT
26 AUG 2020C0000116959N01Fredericksburg150$100.00$91.002Curtis Contracting, Inc.VDOT
27 MAY 202000116067N01Culpeper288$80.00$127.502Caton Construction Group, Inc.VDOT
25 MAR 2020C0000094726C01Salem40$55.00$60.003Jones Road & Bridge, Inc.VDOT
26 FEB 2020C0000108907C01Salem775$52.50$52.863W. C. English, IncorporatedVDOT
22 JAN 2020C0000115748N01Hampton Roads50$215.00$263.752Ipr Northeast LLCVDOT
Latest VDOT contracts carrying Erosion CTRL. stone CL. II, EC-1

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy