NS BR. substr. wid./repair concrete slab slope, VDOT 412SX20-0024
Low bidders on VDOT contracts carried a median of $3,090.00 per SY for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 7 bids fell between $937.44 and $2,795.00.
- Owner
- Virginia DOT
- Item
- 412SX20-0024
- Unit
- SY
- Data through
- 28 OCT 2026
VDOT prints this item as “NS BR. SUBSTR. WID./REPAIR CONCRETE SLAB SLOPE”.
VDOT has bid this work under more than one code: 69908 on lettings from 23 APR 2002 to 27 OCT 2021 (260 bids); 412SX20-0024 on lettings from 25 MAR 2026 to 25 MAR 2026 (7 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 1 | 1 | $41.00 | 3 | $41.00 |
| 2003 | 3 | 7 | $145.00 | 18 | $347.50 |
| 2004 | 1 | 0 | n/a | 2 | $10.00 |
| 2005 | 2 | 2 | $25.00 | 6 | $47.50 |
| 2006 | 1 | 1 | $40.00 | 3 | $40.00 |
| 2007 | 2 | 2 | $13.50 | 6 | $17.00 |
| 2008 | 3 | 3 | $500.00 | 9 | $300.00 |
| 2009 | 1 | 1 | $32.00 | 3 | $32.00 |
| 2010 | 4 | 5 | $465.39 | 10 | $500.00 |
| 2011 | 6 | 6 | $67.50 | 18 | $80.65 |
| 2012 | 4 | 4 | $612.50 | 12 | $700.00 |
| 2013 | 7 | 9 | $350.00 | 23 | $75.00 |
| 2014 | 3 | 3 | $2,500.00 | 9 | $2,500.00 |
| 2015 | 7 | 10 | $420.00 | 25 | $553.79 |
| 2016 | 13 | 18 | $796.00 | 53 | $752.00 |
| 2017 | 4 | 4 | $37.50 | 11 | $50.00 |
| 2018 | 5 | 6 | $75.00 | 14 | $75.00 |
| 2019 | 1 | 1 | $40.00 | 3 | $40.00 |
| 2020 | 3 | 3 | $70.00 | 9 | $75.00 |
| 2021 | 6 | 5 | $34.78 | 16 | $34.89 |
| 2026 | 1 | 1 | $3,090.00 | 7 | $1,350.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Northern Virginia | 21 | $45.00 | 59 | $50.00 |
| Bristol | 18 | $350.00 | 56 | $317.50 |
| Richmond | 13 | $145.00 | 36 | $570.00 |
| Salem | 10 | $179.50 | 29 | $200.00 |
| Fredericksburg | 11 | $50.00 | 29 | $67.00 |
| Hampton Roads | 8 | $880.50 | 19 | $885.00 |
| Lynchburg | 4 | $975.00 | 15 | $1,007.79 |
| Culpeper | 6 | $752.00 | 14 | $796.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 23 | 23 | $752.00 |
| 23 to 100 | 23 | $723.00 |
| 100 to 500 | 23 | $45.00 |
| 775 to 15,347 | 23 | $40.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Lanford Brothers Company, Incorporated | 28 | 9 (32%) |
| M. D. Miller Co., Inc. | 18 | 9 (50%) |
| Martins Construction Corp. | 20 | 8 (40%) |
| Corman Construction, Inc. | 14 | 8 (57%) |
| Burleigh Construction Co., Inc. | 15 | 5 (33%) |
| McClain & Co., Inc. | 6 | 5 (83%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 25 MAR 2026 | C0000121244B67 | Bristol | 28 | $3,090.00 | $1,350.00 | 7 | Freyssinet, Inc. | VDOT |
| 27 OCT 2021 | C0000118978N01 | Northern Virginia | 100 | $35.00 | $50.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 28 APR 2021 | C0000115172B01 | Bristol | 25 | $45.00 | $200.00 | 3 | Crossroads Bridge Inc | VDOT |
| 24 MAR 2021 | C0000117564B40 | Salem | 7,516 | $17.75 | $17.75 | 3 | Eti Environmental, Inc. | VDOT |
| 24 MAR 2021 | C0000117565B21 | Salem | 5,684 | $7.00 | $16.00 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 24 FEB 2021 | C0000115007B02 | Salem | 1,725 | $34.78 | $60.00 | 3 | Structural Engineering Group, Incorporated | VDOT |
| 20 JAN 2021 | C0000116748N01 | Lynchburg | 15,323 | n/a | $12.00 | 1 | Eti Environmental, Inc. | VDOT |
| 21 OCT 2020 | C0000111688B69 | Northern Virginia | 131 | $50.00 | $65.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 23 SEP 2020 | C0000114676B17 | Richmond | 100.40 | $1,000.00 | $2,100.00 | 3 | Coastal Gunite Construction Company | VDOT |
| 22 JUL 2020 | C0000111678B43 | Northern Virginia | 416 | $70.00 | $70.00 | 3 | Shirley Contracting Company, LLC | VDOT |
| 23 JAN 2019 | C0000111320B47 | Northern Virginia | 180 | $40.00 | $40.00 | 3 | Martins Construction Corp. | VDOT |
| 19 DEC 2018 | C0000000113640 | Fredericksburg | 39 | $50.00 | $62.50 | 2 | Curtis Contracting, Inc. | VDOT |
| 19 DEC 2018 | C0000000113640 | Fredericksburg | 39 | $50.00 | $62.50 | 2 | Curtis Contracting, Inc. | VDOT |
| 19 DEC 2018 | C0000110578B79 | Bristol | 94 | $500.00 | $375.03 | 2 | Lanford Brothers Company, Incorporated | VDOT |
| 28 MAR 2018 | C0000110922N01 | Bristol | 20 | $2,200.00 | $2,100.00 | 2 | Elk Knob, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.