NS BR. substr. wid./repair bridge substr. cleaning and washing - substructure, VDOT 412SX20-0017
Low bidders on VDOT contracts carried a median of $11.68 per LF for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 2 bids fell between $12.51 and $14.17.
- Owner
- Virginia DOT
- Item
- 412SX20-0017
- Unit
- LF
- Data through
- 28 OCT 2026
VDOT prints this item as “NS BR. SUBSTR. WID./REPAIR BRIDGE SUBSTR. CLEANING AND WASHING - SUBSTRUCTURE”.
VDOT has bid this work under more than one code: 69901 on lettings from 27 AUG 2002 to 25 AUG 2021 (261 bids); 412SX20-0017 on lettings from 17 DEC 2025 to 17 DEC 2025 (2 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 1 | 1 | $450.00 | 3 | $450.00 |
| 2003 | 3 | 6 | $56.09 | 18 | $49.00 |
| 2005 | 6 | 8 | $61.50 | 24 | $85.00 |
| 2006 | 2 | 3 | $8.00 | 6 | $62.50 |
| 2007 | 3 | 4 | $71.00 | 12 | $56.00 |
| 2008 | 4 | 7 | $8.00 | 21 | $100.00 |
| 2010 | 3 | 6 | $543.00 | 10 | $145.50 |
| 2011 | 4 | 6 | $42.50 | 18 | $70.00 |
| 2012 | 4 | 6 | $100.00 | 18 | $100.00 |
| 2013 | 3 | 5 | $12.00 | 9 | $40.00 |
| 2014 | 6 | 6 | $85.00 | 17 | $108.00 |
| 2015 | 6 | 8 | $64.00 | 16 | $71.50 |
| 2016 | 7 | 13 | $35.00 | 39 | $57.00 |
| 2017 | 1 | 2 | $82.00 | 4 | $77.00 |
| 2018 | 3 | 4 | $41.75 | 10 | $37.50 |
| 2019 | 4 | 4 | $502.50 | 10 | $425.00 |
| 2020 | 2 | 5 | $925.00 | 14 | $937.50 |
| 2021 | 3 | 4 | $61.12 | 12 | $63.12 |
| 2025 | 1 | 1 | $11.68 | 2 | $13.34 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Northern Virginia | 30 | $82.00 | 80 | $94.25 |
| Richmond | 19 | $45.00 | 54 | $83.75 |
| Hampton Roads | 15 | $100.00 | 36 | $100.00 |
| Fredericksburg | 11 | $105.00 | 31 | $120.00 |
| Culpeper | 12 | $8.00 | 28 | $33.25 |
| Bristol | 9 | $12.00 | 26 | $66.00 |
| Salem | 3 | $34.00 | 8 | $30.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 2 to 50 | 24 | $105.00 |
| 52.40 to 100 | 25 | $72.00 |
| 100 to 390 | 25 | $60.00 |
| 480 to 24,665 | 25 | $35.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Lanford Brothers Company, Incorporated | 24 | 18 (75%) |
| Martins Construction Corp. | 24 | 9 (38%) |
| Fort Myer Construction Corporation | 24 | 7 (29%) |
| M. D. Miller Co., Inc. | 11 | 7 (64%) |
| Freyssinet, Inc. | 10 | 6 (60%) |
| Corman Construction, Inc. | 14 | 4 (29%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 17 DEC 2025 | C0000126353N01C | Hampton Roads | 24,665 | $11.68 | $13.34 | 2 | Deangelo Contracting Services, LLC | VDOT |
| 25 AUG 2021 | C0000110623D26 | Salem | 1,000 | $17.00 | $19.00 | 3 | Crossroads Bridge Inc | VDOT |
| 25 AUG 2021 | C0000110623D26 | Salem | 500 | $34.00 | $34.00 | 3 | Crossroads Bridge Inc | VDOT |
| 28 JUL 2021 | C0000111303B28 | Richmond | 32 | $100.00 | $241.17 | 3 | M. D. Miller Co., Inc. | VDOT |
| 28 APR 2021 | C0000071874B03 | Bristol | 20 | $88.25 | $100.00 | 3 | Estes Bros. Const., Inc. | VDOT |
| 21 OCT 2020 | C0000105898B97 | Northern Virginia | 52.40 | $925.00 | $1,500.00 | 3 | Corman Kokosing Construction Company | VDOT |
| 21 OCT 2020 | C0000105898B97 | Northern Virginia | 110.50 | $105.00 | $200.00 | 3 | Corman Kokosing Construction Company | VDOT |
| 21 OCT 2020 | C0000105898B97 | Northern Virginia | 25 | $1,000.00 | $1,350.00 | 3 | Corman Kokosing Construction Company | VDOT |
| 21 OCT 2020 | C0000105898B97 | Northern Virginia | 53.10 | $950.00 | $950.00 | 3 | Corman Kokosing Construction Company | VDOT |
| 24 JUN 2020 | C0000112505N01 | Northern Virginia | 2 | $400.00 | $249.25 | 2 | Martins Construction Corp. | VDOT |
| 24 JUL 2019 | C000081548B35B | Bristol | 80 | $100.00 | $100.00 | 3 | Patrick Construction, Inc. | VDOT |
| 22 MAY 2019 | C000110784B20 | Richmond | 79 | $275.00 | $387.50 | 2 | Burleigh Construction Co., Inc. | VDOT |
| 22 MAY 2019 | C000110997B04 | Richmond | 56 | $730.00 | $540.00 | 2 | Allan Myers Va, Inc. | VDOT |
| 23 JAN 2019 | C0000111320B47 | Northern Virginia | 36 | $1,108.00 | $2,000.00 | 3 | Martins Construction Corp. | VDOT |
| 19 DEC 2018 | C000110614B78 | Salem | 160 | $60.00 | $45.00 | 2 | D. A. Brown, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.