Connect to exist. A/C pipe, VDOT 510SX20-0009

Low bidders on VDOT contracts carried a median of $6,503.27 per EACH for this item, over the 24 months to 28 OCT 2026, across 6 low bids. Half of all 17 bids fell between $3,500.00 and $6,334.55.

Owner
Virginia DOT
Item
510SX20-0009
Unit
EACH
Data through
28 OCT 2026

VDOT prints this item as “CONNECT TO EXIST. A/C PIPE”.

VDOT has bid this work under more than one code: 45505 on lettings from 26 AUG 2003 to 26 MAY 2021 (110 bids); 510SX20-0009 on lettings from 17 DEC 2025 to 22 JUL 2026 (17 bids). They are combined here into one trend.

$6,503.27Low bidder's median, per EACH
$5,000.00Median of all bids, per EACH
6Contracts in the window

By year of letting

Connect to exist. A/C pipe, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200322$1,200.006$920.00
200444$3,097.5410$4,200.00
200544$3,625.0011$2,300.00
200633$1,150.007$1,200.00
200822$5,658.636$830.00
201011$2,334.353$2,500.00
201121$1,400.005$1,400.00
201222$1,213.406$1,400.00
201366$1,650.0017$2,100.00
201411$1,230.073$1,230.07
201566$1,900.0016$2,000.00
201711$3,750.003$3,750.00
201822$1,050.006$1,111.50
201922$2,472.474$3,975.97
202022$2,771.575$2,900.00
202111$1,500.001$1,500.00
202511$5,000.004$5,500.00
202655$6,672.0013$5,000.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Richmond15$2,334.3539$3,000.00
Bristol8$1,750.0024$1,750.00
Fredericksburg6$1,350.0018$1,675.00
Salem5$2,643.1315$2,643.13
Staunton6$1,450.0012$1,500.00
Northern Virginia3$2,100.009$2,000.00
Connect to exist. A/C pipe, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 211$1,400.00
2 to 212$2,081.00
2 to 311$2,643.13
4 to 1412$2,300.00
Connect to exist. A/C pipe, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Fielder'S Choice Enterprises, Inc.98 (89%)
DLB, Inc.63 (50%)
Jones Road & Bridge, Inc.53 (60%)
Blakemore Construction Corporation50 (0%)
Connect to exist. A/C pipe, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
22 JUL 2026C0000119436C01Bristol2$6,334.55$5,325.004E. C. Pace Company, Inc.VDOT
25 FEB 2026C0000119431C01BBristol2$9,669.00$6,834.502King General Contractors, Inc.VDOT
04 FEB 2026C0000119457C01Salem2$3,225.00$3,225.003MCC ACQUISITION, LC dba VIRGINIA-CAROLINAVDOT
04 FEB 2026C0000119451M01Salem2$6,672.00$3,500.003W. C. English, IncorporatedVDOT
04 FEB 2026C000115407C01BRichmond13$27,496$27,4961J. R. Caskey, Inc.VDOT
17 DEC 2025C0000119429C01Bristol3$5,000.00$5,500.004Ramirez Contracting, L.L.C.VDOT
26 MAY 2021C0000109370M01Staunton2$1,500.00$1,500.001A & J Development and Excavation, Inc.VDOT
22 APR 2020C0000107061C01Salem2$2,643.13$3,500.003Kanawha Stone Company, Inc.VDOT
25 MAR 2020C0000018003C01Staunton2$2,900.00$2,750.002General Excavation, Inc.VDOT
05 SEP 20190000116195C01Northern Virginia2$1,355.00$1,355.001Martins Construction Corp.VDOT
24 JUL 2019C0000100921C01Hampton Roads2$3,589.95$4,362.003Branscome Inc.VDOT
22 AUG 2018C0000090018C01Richmond13$1,100.00$4,119.393J. L. Kent & Sons, Inc.VDOT
28 MAR 2018C0000008753C01Salem1$1,000.00$1,000.003Kanawha Stone Company, Inc.VDOT
25 OCT 2017C0000017179C01Richmond3$3,750.00$3,750.003Shoosmith Construction, Inc.VDOT
18 NOV 2015C0000101021C01Richmond2$2,300.00$3,360.003Fielder'S Choice Enterprises, Inc.VDOT
Latest VDOT contracts carrying Connect to exist. A/C pipe

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.