VDOT contract C0000119451M01 bid tabulation

Smart scale - intersection improvements. Let by Virginia DOT on February 4, 2026, Patrick, Salem. 3 bids received; low bid $4,512,140 by W. C. English, Incorporated.

Owner
Virginia DOT
Letting
04 FEB 2026
Pay items
120
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1W. C. English, Incorporated$4,512,140Low
2Haymes Brothers, Inc.$4,825,320+7.0%
3Jones Road & Bridge, Inc.$5,950,816+32%
VDOT contract C0000119451M01: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. W. C. English, Incorporated2. Haymes Brothers, Inc.3. Jones Road & Bridge, Inc.
0001-0010Clearing and grubbing (301SD20-0001)LS1$665,301$300,000$500,000
0001-0020Bedding matl.aggr.no. 25 or 26 (302SD20-0001)TON45.50$70.85$75.00$120.00
0001-0030Concrete class A4 box culvert (302SD20-0004)CY18$8,000.00$12,500$7,000.00
0001-0040Reinf. steel (302SD20-0005)LB1,560$0.01$3.00$10.00
0001-005024" pipe (302SD20-0037)LF105$197.45$325.00$350.00
0001-006048" pipe (302SD20-0067)LF136$294.05$400.00$550.00
0001-007078" pipe (302SD20-0097)LF155$659.65$2,000.00$2,000.00
0001-008024" end section ES-1 or 2 (302SD20-0204)EACH1$2,958.00$750.00$2,500.00
0001-0090Pipe spillout PS-3 (302SD20-0669)EACH2$1,250.00$25,000$5,000.00
0001-0100Temp. dive. channel lining CL. A (302SD20-0670)SY66$24.70$25.00$45.00
0001-0110Temp. dive. channel lining CL. B (302SD20-0671)SY553$19.65$125.00$55.00
0001-0120Temp. dive. channel excavation (302SD20-0672)CY218$33.45$85.00$90.00
0001-0130Regular excavation (303SD20-0001)CY1,938$40.40$60.00$100.00
0001-0140Borrow excavation (303SD20-0007)CY5,919$34.40$30.00$98.00
0001-0150Geotextile embankment stab. (303SD20-0013)SY1,100$8.90$3.00$15.00
0001-0160Minor STR. excav. pipe culvert (303SD20-0016)CY1,651$33.00$100.00$100.00
0001-0170Minor STR. excav. box culvert (303SD20-0017)CY24$235.00$700.00$120.00
0001-0180Slope drain (303SD20-0018)EACH1$793.55$2,800.00$10,000
0001-0190Erosion control mulch (303SD20-0019)SY442$12.50$1.40$5.00
0001-0200Temporary diversion dike (303SD20-0021)LF186$6.15$24.00$10.00
0001-0210Check dam rock TY. I (303SD20-0022)EACH2$598.00$1,000.00$1,000.00
0001-0220Dewatering basin EC-8 (303SD20-0028)EACH7$989.00$500.00$10,000
0001-0230Siltation control excavation (303SD20-0029)CY458$0.01$15.00$0.01
0001-0240Temp. silt fence type B (303SD20-0033)LF239$8.30$7.00$15.00
0001-0250Temp. silt fence type A (303SD20-0034)LF1,880$4.65$6.00$10.00
0001-0260Rock excavation (303SX20-0005)CY300$360.75$125.00$300.00
0001-0270Utility test pit unpaved (303SX20-0012)EACH5$1,521.75$1,850.00$1,000.00
0001-0280NS rockfill NS rockfill no. 1 aggregate (303SX20-0015)TON141.30$85.15$140.00$120.00
0001-0290Temp.veh.watercourse crossing (303SX20-0024)EACH3$14,896$7,500.00$30,000
0001-0300Aggr. matl. no. 3 (305SD20-0013)TON489$90.50$75.00$99.00
0001-0310Aggr. matl. no. 21B (308SD20-0007)TON55$116.15$75.00$95.00
0001-0320Aggr. base matl. TY. I no. 21B (308SD20-0012)TON1,521$74.60$75.00$95.00
0001-0330Crusher run aggr. no. 25 or 26 (308SX20-0003)TON242$68.95$75.00$85.00
0001-0340Tack coat (310SD20-0001)GAL161$6.25$10.00$10.00
0001-0350Prime coat (311SD20-0001)GAL32$18.75$10.00$10.00
0001-0360Asphalt concrete TY. IM- 19.0D const (315SD20-0005)TON144$750.00$330.00$450.00
0001-0370Asphalt concrete TY. SM- 9.5D const (315SD20-0008)TON358$481.25$315.00$375.00
0001-0380Asphalt concrete BM-25.0 (315SD20-0010)TON384$437.50$300.00$350.00
0001-0390NS saw-cut asph conc full depth saw-cut (315SX20-0011)LF568$9.50$15.00$20.00
0001-0400Cofferdam (401SD20-0007)EACH7$22,000$25,000$30,000
0001-0410NS temp support of excavation (for 78" culvert) (402SX20-0002)LS1$896,000$725,000$400,000
0001-0420Erosion CTRL. stone CL. A1, EC-1 (414SD20-0001)TON3$412.40$145.00$100.00
0001-0430Erosion CTRL. stone CL. I, EC-1 (414SD20-0003)TON170$101.00$125.00$100.00
0001-0440Dry riprap CL. AI (414SD20-0008)TON840$91.00$125.00$125.00
0001-0450Energy dissipator EG-1 (502SD20-0001)EACH2$3,431.50$10,000$10,000
0001-0460Paved ditch PG-2A (502SD20-0003)SY15$302.65$330.00$300.00
0001-0470Paved ditch PG-5 (502SD20-0004)SY22$410.10$330.00$400.00
0001-0480Paved flume PG-4 (502SD20-0005)SY16.10$752.50$330.00$425.00
0001-0490NS paved ditch (modified PG-2A) (502SX20-0006)SY34$258.90$330.00$325.00
0001-0500Concrete class A3 misc. (504SD20-0001)CY17.73$1,102.30$1,000.00$3,000.00
0001-0510Guardrail GR-MGS1 (505SD20-0011)LF325$43.75$30.00$50.00
0001-0520Radial guardrail GR-MGS1 (505SD20-0014)LF100$50.00$33.00$55.00
0001-0530Guardrail terminal GR- MGS2 (505SD20-0017)EACH3$6,250.00$3,850.00$7,500.00
0001-0540Guardrail height transition GR-MGS4 (505SD20-0019)EACH3$2,500.00$2,750.00$3,000.00
0001-0550Impact attenuator IA-2 (505SD20-0068)EACH1$42,493$30,000$35,000
0001-0560Remove existing guardrail (505SD20-0073)LF387$12.50$3.30$15.00
0001-0570NS hand dig guardrail post holes (505SX20-0001)EACH10$1,250.00$330.00$750.00
0001-0580High visibility fence, 4 feet (507SD20-0027)LF308$4.55$8.50$20.00
0001-0590Demo. of pavement flexible (508SD20-0004)SY822$25.60$18.00$50.00
0001-0600Flowable backfill (509SD20-0001)CY70$388.45$550.00$500.00
0001-0610Adjust exist. valve & box (510SD20-0038)EACH1$3,098.00$2,500.00$1,500.00
0001-0620Connect to exist. A/C pipe (510SX20-0009)EACH2$6,672.00$2,500.00$3,500.00
0001-0630Remove exist. A/C pipe (510SX20-0010)LF136$29.15$70.00$250.00
0001-0640NS rem. exist. paved ditch (temporary) (510SX20-0015)SY8.10$67.40$250.00$120.00
0001-0650NS remove exist. endwall (temporary) (510SX20-0028)EACH2$273.00$2,500.00$2,000.00
0001-0660NS remove exist. pipe culvert (42" and 48") (510SX20-0039)LF152$20.30$150.00$1,000.00
0001-0670Allaying dust (511SD20-0001)HR150$0.01$100.00$30.00
0001-0680Type 3 barricade 8' (512SD20-0013)EACH6$343.75$550.00$1,000.00
0001-0690Temporary sign (512SD20-0014)SF181$20.00$28.00$40.00
0001-0700Group 2 channelizing devices (512SD20-0024)DAY5,000$1.20$1.00$3.00
0001-0710Port.changeable mess. sign (512SD20-0025)HR700$3.85$10.00$10.00
0001-0720Flagger service (512SD20-0027)HR400$47.90$100.00$50.00
0001-0730Warning light TY. B (512SD20-0029)DAY500$2.50$5.00$2.00
0001-0740Eradicate linear PVMT MRKG (512SD20-0042)LF100$7.10$61.00$75.00
0001-0750Temp. PVMT MRKG TY. D, CL. III, 6" (512SD20-0062)LF100$8.80$46.00$65.00
0001-0760Temp. PVMT MRKG TY. D, CL. III, 24" (512SD20-0065)LF30$39.00$54.00$65.00
0001-0770Traffic barrier service conc. (512SD20-0066)LF645$95.00$115.00$75.00
0001-0780Portable temporary rumble strip array (512SP20-0001)DAY100$103.30$50.00$200.00
0001-0790Mobilization (513SD20-0001)LS1$255,000$218,000$287,000
0001-0800Field office TY.I (514SD20-0001)MO10$4,250.00$4,800.00$5,000.00
0001-0810Flexible pave.planing 0"-2" (515SD20-0004)SY1,609$31.25$14.00$20.00
0001-0820Construction surveying constr. (517SD20-0001)LS1$59,544$120,000$400,000
0001-08306" DI water main (520SD20-0014)LF153$244.70$400.00$250.00
0001-08406" gate valve & box (520SD20-0089)EACH1$7,315.00$3,250.00$5,000.00
0001-0850Mailbox post, double (521SD20-0002)EACH1$1,090.00$350.00$800.00
0001-0860NS storm water management temporary pump around (at 4 locations) (523SP20-0005)LS1$68,525$500,000$400,000
0001-0870NS soil NS soil clay plug (523SX20-0002)CY9.60$1,007.00$500.00$400.00
0001-0880Topsoil class B 3" (602SD20-0004)CY375$195.00$200.00$400.00
0001-0890Temporary seed (603SD20-0002)LB206$20.00$18.00$20.00
0001-0900Regular seed (603SD20-0003)LB320$21.25$19.00$22.00
0001-0910Overseeding (603SD20-0004)LB255$21.25$19.00$22.00
0001-0920Hydraulic erosion control product type 2 (603SD20-0008)SY1,510$1.20$1.10$4.00
0001-0930Hydraulic erosion control product type 3 (603SD20-0009)SY8,230$1.40$1.20$4.00
0001-0940Sediment retention roll 18" min (603SD20-0011)LF392$21.80$25.00$30.00
0001-0950Fertilizer nitrogen - N (603SD20-0014)LB90$2.50$2.20$4.00
0001-0960Fertilizer phosphorous - P (603SD20-0015)LB63$2.50$2.20$4.00
0001-0970Fertilizer potassium - K (603SD20-0016)LB63$2.50$2.20$4.00
0001-0980Lime (603SD20-0017)TON4.92$187.50$165.00$200.00
0001-0990Rolled erosion CTRL product EC-2 type 4 (606SD20-0004)SY2,478$6.60$5.85$10.00
0001-1000Rolled erosion CTRL product EC-3 type 1 (606SD20-0005)SY160$10.00$8.80$12.00
0001-1010Mowing (608SD20-0001)HR20$125.00$50.00$30.00
0001-1020Remove existing 1 post sign structure (700SD20-0003)EACH9$576.00$520.00$500.00
0001-1030Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036)LF120$57.30$50.00$30.00
0001-1040Conc. found. STP-1, TY. A (700SD20-0038)EACH9$1,532.95$1,400.00$800.00
0001-10508/3 conductor cable (700SD20-0108)LF10$12.10$11.00$15.00
0001-106014/4 conductor cable (700SD20-0112)LF50$6.35$6.00$9.00
0001-1070Electrical service SE-4, TY. A (700SD20-0134)EACH1$4,864.00$4,400.00$5,200.00
0001-1080Junction box JB-S2 (700SD20-0178)EACH1$3,059.80$2,850.00$3,500.00
0001-1090Conduit PVC 3" (700SD20-0195)LF60$11.20$11.00$15.00
0001-1100Trench excavation eci-1 (700SD20-0197)LF60$10.90$11.00$15.00
0001-1110NS traffic signalization solar powered flashing beacon warning system assembly (700SX20-0010)EACH1$29,684$40,000$35,000
0001-1120Sign panel (701SD20-0001)SF100$75.30$68.00$40.00
0001-1130Flashing beacon FB-2 (703SD20-0005)EACH1$16,945$21,000$20,000
0001-1140Flasher (703SD20-0006)EACH1$4,365.00$4,400.00$5,000.00
0001-1150Type B class I PVMT line MRKG 4" (704SD20-0006)LF1,480$13.20$5.50$7.00
0001-1160Type B class I PVMT line MRKG 6" (704SD20-0007)LF1,250$15.20$5.60$8.00
0001-1170Type B class II PVMT line MRKG 24" (704SD20-0015)LF150$36.45$38.00$45.00
0001-1180PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048)EACH2$1,202.75$550.00$625.00
0001-1190ITS controller cabinet pole mounted (801SD20-0002)EACH1$15,439$15,000$20,000
0001-1200Uninterruptible power supply ITS-CC (802SD20-0001)EACH1$9,667.00$12,000$15,000
VDOT contract C0000119451M01: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

Every contract let that day: VDOT letting of February 4, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy