8/3 conductor cable, VDOT 700SD20-0108
Low bidders on VDOT contracts carried a median of $11.68 per LF for this item, over the 24 months to 28 OCT 2026, across 6 low bids. Half of all 11 bids fell between $8.00 and $13.55.
- Owner
- Virginia DOT
- Item
- 700SD20-0108
- Unit
- LF
- Data through
- 28 OCT 2026
VDOT has bid this work under more than one code: 51598 on lettings from 23 APR 2002 to 25 AUG 2021 (151 bids); 700SD20-0108 on lettings from 17 DEC 2025 to 22 JUL 2026 (11 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 1 | 1 | $2.20 | 3 | $2.20 |
| 2003 | 2 | 2 | $2.00 | 5 | $1.10 |
| 2004 | 3 | 3 | $3.00 | 9 | $3.00 |
| 2005 | 2 | 2 | $3.33 | 4 | $2.66 |
| 2006 | 4 | 4 | $2.31 | 11 | $2.25 |
| 2007 | 1 | 1 | $5.30 | 2 | $5.20 |
| 2008 | 2 | 2 | $3.08 | 6 | $2.60 |
| 2009 | 2 | 2 | $2.50 | 6 | $2.50 |
| 2010 | 7 | 7 | $2.50 | 20 | $2.52 |
| 2011 | 2 | 2 | $2.54 | 6 | $2.51 |
| 2012 | 2 | 2 | $1.80 | 4 | $2.60 |
| 2013 | 2 | 2 | $3.62 | 5 | $2.50 |
| 2014 | 6 | 6 | $3.67 | 17 | $3.00 |
| 2015 | 2 | 2 | $2.30 | 4 | $2.38 |
| 2016 | 5 | 5 | $8.50 | 13 | $6.50 |
| 2017 | 3 | 3 | $4.33 | 9 | $1.95 |
| 2018 | 1 | 1 | $8.40 | 3 | $8.60 |
| 2019 | 4 | 4 | $3.13 | 9 | $2.72 |
| 2020 | 5 | 5 | $3.15 | 11 | $3.15 |
| 2021 | 2 | 2 | $4.04 | 4 | $4.05 |
| 2025 | 1 | 1 | $4.70 | 2 | $7.35 |
| 2026 | 5 | 5 | $12.10 | 9 | $11.25 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Richmond | 17 | $2.50 | 45 | $2.50 |
| Hampton Roads | 18 | $2.67 | 45 | $2.54 |
| Staunton | 9 | $6.00 | 20 | $4.33 |
| Salem | 8 | $7.55 | 19 | $5.30 |
| Bristol | 4 | $3.15 | 11 | $3.30 |
| Fredericksburg | 3 | $3.00 | 9 | $3.00 |
| Northern Virginia | 3 | $3.00 | 7 | $3.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 10 to 40 | 16 | $2.75 |
| 40 to 70 | 16 | $3.00 |
| 70 to 130 | 16 | $3.73 |
| 145 to 4,335 | 16 | $3.58 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Blakemore Construction Corporation | 7 | 5 (71%) |
| Howard Brothers Contractor, Inc. | 7 | 4 (57%) |
| W-L Construction & Paving, Inc. | 5 | 4 (80%) |
| Branscome Inc. | 9 | 3 (33%) |
| Curtis Contracting, Inc. | 5 | 3 (60%) |
| Allegheny Construction Company, Inc. | 5 | 3 (60%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | C0000120611C01 | Salem | 70 | $11.25 | $11.25 | 1 | Branch Civil, Inc. | VDOT |
| 24 JUN 2026 | C0000108810C01 | Staunton | 470 | $17.46 | $14.23 | 2 | A & J Development and Excavation, Inc. | VDOT |
| 24 JUN 2026 | C0000119655C01B | Staunton | 210 | $26.66 | $26.66 | 1 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 27 MAY 2026 | C0000119644C01 | Staunton | 195 | $6.00 | $5.00 | 2 | Arthur Construction Co., Inc. | VDOT |
| 04 FEB 2026 | C0000119451M01 | Salem | 10 | $12.10 | $12.10 | 3 | W. C. English, Incorporated | VDOT |
| 17 DEC 2025 | C0000119474C01 | Salem | 130 | $4.70 | $7.35 | 2 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 25 AUG 2021 | C0000111047T01 | Staunton | 300 | $6.20 | $6.20 | 1 | Ces Consulting, LLC | VDOT |
| 20 JAN 2021 | C0000109481C01 | Hampton Roads | 130 | $1.87 | $1.90 | 3 | Henry S. Branscome, L.L.C. | VDOT |
| 22 JUL 2020 | C0000109440C01 | Bristol | 1,525 | $1.75 | $1.69 | 2 | Jones Road & Bridge, Inc. | VDOT |
| 22 APR 2020 | C0000111707C01 | Hampton Roads | 55 | $5.15 | $14.11 | 2 | Curtis Contracting, Inc. | VDOT |
| 25 MAR 2020 | C0000018003C01 | Staunton | 275 | $3.15 | $4.58 | 2 | General Excavation, Inc. | VDOT |
| 25 MAR 2020 | C0000109466M01 | Fredericksburg | 25 | $3.00 | $3.00 | 3 | Howard Brothers Contractor, Inc. | VDOT |
| 22 JAN 2020 | C000111370C01B | Salem | 40 | $6.60 | $4.30 | 2 | Allegheny Construction Company, Inc. | VDOT |
| 23 OCT 2019 | C0000102944M01 | Hampton Roads | 40 | $3.74 | $3.74 | 3 | Henry S. Branscome, L.L.C. | VDOT |
| 24 JUL 2019 | C0000100921C01 | Hampton Roads | 60 | $2.52 | $2.52 | 3 | Branscome Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.