Temp. dive. channel excavation, VDOT 302SD20-0672

Low bidders on VDOT contracts carried a median of $54.00 per CY for this item, over the 24 months to 28 OCT 2026, across 5 low bids. Half of all 16 bids fell between $50.69 and $145.49.

Owner
Virginia DOT
Item
302SD20-0672
Unit
CY
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 27340 on lettings from 29 JAN 2002 to 27 OCT 2021 (324 bids); 302SD20-0672 on lettings from 04 FEB 2026 to 27 MAY 2026 (16 bids). They are combined here into one trend.

$54.00Low bidder's median, per CY
$82.50Median of all bids, per CY
5Contracts in the window

By year of letting

Temp. dive. channel excavation, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20021210$7.0032$7.53
20031211$10.0033$11.70
20041616$14.5043$15.00
200565$16.6016$17.30
200655$13.0013$16.00
200711$25.003$25.00
200888$15.0024$14.50
200933$10.509$10.50
201055$9.5015$11.19
201177$25.0021$19.00
201244$15.3012$17.80
201399$18.0027$20.00
201477$39.0021$34.00
201566$16.0017$18.00
201655$30.0015$35.00
201711$3.073$18.00
201911$51.583$28.46
202022$18.406$23.50
202122$24.155$31.00
202655$54.0016$82.50

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Salem44$15.80132$19.50
Lynchburg20$10.0061$11.60
Staunton10$11.1634$13.50
Fredericksburg11$10.0032$18.00
Northern Virginia8$21.1924$25.75
Hampton Roads8$20.0021$19.00
Richmond7$42.0017$25.00
Culpeper5$15.2313$25.00
Temp. dive. channel excavation, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (CY)Low bidsLow-bid median
6 to 8928$25.70
94 to 28028$12.50
300 to 60028$14.00
600 to 16,30029$15.00
Temp. dive. channel excavation, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Branch Highways, Inc.98 (89%)
D. A. Brown, Inc.127 (58%)
Carnell Construction Corporation96 (67%)
Sowers Construction Co., Inc.165 (31%)
Haymes Brothers, Inc.135 (38%)
W. C. English, Incorporated95 (56%)
Temp. dive. channel excavation, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
27 MAY 2026C0000119458C01Salem145$40.75$125.466Branch Civil, Inc.VDOT
22 APR 2026C0000101435C01Staunton525$54.00$54.005General Excavation, Inc.VDOT
22 APR 2026C0000118863C01Culpeper6$145.00$145.001Caton Construction Group, Inc.VDOT
04 FEB 2026C0000119451M01Salem218$33.45$85.003W. C. English, IncorporatedVDOT
04 FEB 2026C000115407C01BRichmond28$256.00$256.001J. R. Caskey, Inc.VDOT
27 OCT 2021C000109550C01BLynchburg478$31.00$31.002Caton Construction Group, Inc.VDOT
22 SEP 2021C0000118341D38Salem667$17.30$20.003Kanawha Stone Company, Inc.VDOT
23 SEP 2020C0000109520C01Culpeper225$6.30$25.003Chemung Contracting CorporationVDOT
26 FEB 2020C0000108907C01Salem3,635$30.50$22.003W. C. English, IncorporatedVDOT
18 DEC 2019C000109286M501Salem35$51.58$28.463James R. Vannoy & Sons Construction Company, Inc.VDOT
21 JUN 2017C0000008216C01Richmond775$3.07$18.003Phillips Construction, LLCVDOT
27 JUL 2016C0000004544N02Salem39$100.00$100.003Sowers Construction Co., Inc.VDOT
27 APR 2016C0000105346D38Salem245$12.00$25.003Boring Contractors, Inc.VDOT
27 APR 2016C0000105347D47Salem1,294$101.00$35.003Boring Contractors, Inc.VDOT
24 FEB 2016C000051047C01BCulpeper218$30.00$30.003Kickin Asphalt Paving and Excavating, LLCVDOT
Latest VDOT contracts carrying Temp. dive. channel excavation

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy