VDOT contract C0000128603B82 bid tabulation
Bridge rehabilitation. Let by Virginia DOT on August 26, 2026, Smyth, Bristol. 6 bids received; low bid $8,479,194 by M. D. Miller Co., Inc..
- Owner
- Virginia DOT
- Letting
- 26 AUG 2026
- Pay items
- 41
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | M. D. Miller Co., Inc. | $8,479,194 | Low |
| 2 | Freyssinet, Inc. | $9,974,792 | +18% |
| 3 | Crossroads Bridge Inc | $11,467,571 | +35% |
| 4 | Lanford Brothers Company, Incorporated | $11,844,370 | +40% |
| 5 | King General Contractors, Inc. | $12,713,217 | +50% |
| 6 | Southern Road & Bridge, LLC | $14,607,248 | +72% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. M. D. Miller Co., Inc. | 2. Freyssinet, Inc. | 3. Crossroads Bridge Inc | 4. Lanford Brothers Company, Incorporated | 5. King General Contractors, Inc. | 6. Southern Road & Bridge, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0001-0010 | Asphalt concrete TY. SM- 12.5E const (315SD20-0003) | TON | 1,679 | $322.00 | $625.00 | $360.00 | $400.00 | $488.00 | $385.00 |
| 0001-0020 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 2,880 | $177.00 | $340.00 | $200.00 | $235.00 | $267.81 | $285.00 |
| 0001-0030 | Rumble strip cylindrical asphalt (315SD20-0015) | LF | 9,200 | $5.00 | $8.00 | $5.25 | $5.00 | $6.22 | $9.00 |
| 0001-0040 | Saw-cut asphalt concrete (full depth) (315SD20-0104) | LF | 7,500 | $0.01 | $21.00 | $5.00 | $30.00 | $15.42 | $22.00 |
| 0001-0050 | Bridge deck grooving maint. (404SD20-0020) | SY | 5,519 | $18.00 | $35.00 | $12.00 | $25.00 | $6.09 | $15.00 |
| 0001-0060 | Anchor bolt replacement (412SD20-0010) | EACH | 17 | $1,500.00 | $240.00 | $1,200.00 | $3,000.00 | $1,674.32 | $2,500.00 |
| 0001-0070 | Embedded galvanic anodes (412SD20-0017) | EACH | 1,072 | $32.00 | $55.00 | $55.00 | $60.00 | $83.28 | $95.00 |
| 0001-0080 | Parapet closure type A (412SD20-0026) | EACH | 16 | $2,500.00 | $645.00 | $3,700.00 | $3,000.00 | $10,487 | $15,000 |
| 0001-0090 | Deck slab closure (412SD20-0037) | SY | 154 | $3,000.00 | $1,540.00 | $1,900.00 | $3,000.00 | $2,297.94 | $2,950.00 |
| 0001-0100 | Expansion joint preparation (412SD20-0043) | LF | 993 | $0.01 | $29.00 | $60.00 | $40.00 | $57.06 | $125.00 |
| 0001-0110 | Jacking and blocking beam (412SD20-0048) | EACH | 77 | $7,900.00 | $5,610.00 | $8,000.00 | $5,000.00 | $11,368 | $13,950 |
| 0001-0120 | Conc. superstr. surface repair (412SD20-0049) | SY | 192 | $2,750.00 | $2,930.00 | $3,125.00 | $4,200.00 | $4,110.07 | $3,500.00 |
| 0001-0130 | Concrete substruct. surface repair (412SD20-0061) | SY | 210 | $1,400.00 | $2,940.00 | $2,900.00 | $2,500.00 | $3,817.04 | $3,500.00 |
| 0001-0140 | NS BR.superstr. wid./repair shim existing bearing (412SX20-0009) | EACH | 32 | $5,000.00 | $630.00 | $1,650.00 | $1,500.00 | $1,580.80 | $12,500 |
| 0001-0150 | NS BR.superstr. wid./repair structural steel (412SX20-0012) | LB | 102 | $1,000.00 | $95.00 | $200.00 | $850.00 | $495.38 | $150.00 |
| 0001-0160 | NS BR.superstr. wid./repair type C patching (ves) (412SX20-0015) | SY | 128 | $1,000.00 | $1,520.00 | $2,500.00 | $3,000.00 | $5,050.84 | $6,850.00 |
| 0001-0170 | NS BR. substr. wid./repair concrete slab slope protection repair (412SX20-0024) | SY | 116 | $1,100.00 | $3,260.00 | $1,400.00 | $3,500.00 | $347.00 | $6,500.00 |
| 0001-0180 | Waterproofing – epoxy resin type EP-3B/EP-3T (416SD20-0003) | SY | 3,059 | $75.00 | $87.00 | $95.00 | $100.00 | $133.97 | $98.00 |
| 0001-0190 | Adhesive based JT. sealer CL. I, 1" maint. (420SD20-0018) | LF | 639 | $95.00 | $96.00 | $110.00 | $200.00 | $186.47 | $285.00 |
| 0001-0200 | Adhesive based JT. sealer CL. I, 1-1/2" maint. (420SD20-0019) | LF | 354 | $95.00 | $105.00 | $120.00 | $225.00 | $251.65 | $385.00 |
| 0001-0210 | Type A milling 1-1/2" (425SD20-0004) | SY | 5,439 | $65.00 | $30.00 | $60.00 | $90.00 | $77.51 | $68.00 |
| 0001-0220 | Place very early mod.conc.overlay (425SD20-0015) | SY | 5,439 | $120.00 | $94.50 | $135.00 | $140.00 | $223.62 | $355.00 |
| 0001-0230 | Type A hydro-demolition 1/2" (425SD20-0022) | SY | 5,439 | $115.00 | $165.00 | $125.00 | $105.00 | $143.57 | $129.00 |
| 0001-0240 | NS furn very early latex mod conc. (1 3/4" - 2 1/4") (425SX20-0004) | CY | 381 | $1,900.00 | $2,750.00 | $2,200.00 | $2,500.00 | $1,657.91 | $2,450.00 |
| 0001-0250 | Modify exist. fixed bearing (426SD20-0004) | EACH | 24 | $2,500.00 | $6,880.00 | $2,200.00 | $5,000.00 | $4,433.94 | $9,800.00 |
| 0001-0260 | Demo. of pavement flexible (508SD20-0004) | SY | 10,005 | $45.00 | $37.00 | $25.00 | $40.00 | $28.64 | $22.00 |
| 0001-0270 | Maintenance of traffic (STR no. 2011) (512SP20-0002) | LS | 1 | $93,000 | $91,100 | $300,000 | $240,000 | $235,837 | $85,000 |
| 0001-0280 | Maintenance of traffic (STR. no. 2010 ) (512SP20-0002) | LS | 1 | $93,000 | $76,300 | $300,000 | $260,000 | $240,445 | $85,000 |
| 0001-0290 | Maintenance of traffic (STR. no. 2012 ) (512SP20-0002) | LS | 1 | $93,000 | $90,300 | $375,000 | $180,000 | $235,837 | $85,000 |
| 0001-0300 | Maintenance of traffic (STR. no. 2013) (512SP20-0002) | LS | 1 | $93,000 | $91,100 | $350,000 | $240,000 | $240,445 | $85,000 |
| 0001-0310 | Maintenance of traffic (STR. no. 2016) (512SP20-0002) | LS | 1 | $93,000 | $66,900 | $250,000 | $180,000 | $217,936 | $85,000 |
| 0001-0320 | Maintenance of traffic (STR. no. 2017) (512SP20-0002) | LS | 1 | $93,000 | $66,900 | $350,000 | $225,000 | $222,255 | $85,000 |
| 0001-0330 | Maintenance of traffic (STR. no. 2032) (512SP20-0002) | LS | 1 | $93,000 | $65,700 | $275,000 | $190,000 | $206,918 | $85,000 |
| 0001-0340 | Maintenance of traffic (STR. no. 2033) (512SP20-0002) | LS | 1 | $93,000 | $64,800 | $325,000 | $235,000 | $231,335 | $85,000 |
| 0001-0350 | NS mobilization (rte. 683) (513SX20-0001) | EACH | 1 | $93,000 | $75,300 | $250,000 | $250,000 | $157,308 | $300,000 |
| 0001-0360 | NS mobilization (rte. 689) (513SX20-0001) | EACH | 1 | $93,000 | $75,300 | $325,000 | $160,000 | $157,308 | $300,000 |
| 0001-0370 | NS mobilization (rte. 690) (513SX20-0001) | EACH | 1 | $93,000 | $75,300 | $325,000 | $160,000 | $157,308 | $300,000 |
| 0001-0380 | NS mobilization (rte. 691) (513SX20-0001) | EACH | 1 | $119,000 | $75,300 | $250,000 | $250,000 | $157,308 | $300,000 |
| 0001-0390 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 6,990 | $46.00 | $47.00 | $32.00 | $45.00 | $36.32 | $35.00 |
| 0001-0400 | Type B class VI PVMT line MRKG 6" (704SD20-0027) | LF | 3,235 | $20.00 | $36.00 | $7.50 | $10.00 | $27.73 | $28.00 |
| 0001-0410 | Type B class VI contrast PVMT line MRKG 6" (704SD20-0031) | LF | 2,792 | $20.00 | $31.00 | $20.00 | $20.00 | $36.13 | $34.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of August 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.