Concrete substruct. surface repair, VDOT 412SD20-0061
Low bidders on VDOT contracts carried a median of $1,550.00 per SY for this item, over the 24 months to 28 OCT 2026, across 16 low bids. Half of all 75 bids fell between $1,746.10 and $3,500.00.
- Owner
- Virginia DOT
- Item
- 412SD20-0061
- Unit
- SY
- Data through
- 28 OCT 2026
VDOT has bid this work under more than one code: 69500 on lettings from 26 MAR 2002 to 15 DEC 2021 (932 bids); 412SD20-0061 on lettings from 22 OCT 2025 to 28 OCT 2026 (75 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 12 | 12 | $700.00 | 35 | $750.00 |
| 2003 | 13 | 12 | $700.00 | 34 | $775.00 |
| 2004 | 15 | 15 | $800.00 | 41 | $880.64 |
| 2005 | 23 | 22 | $750.00 | 63 | $900.00 |
| 2006 | 12 | 12 | $950.00 | 34 | $900.00 |
| 2007 | 36 | 36 | $945.00 | 99 | $1,000.00 |
| 2008 | 19 | 19 | $850.00 | 56 | $895.00 |
| 2009 | 13 | 12 | $1,050.00 | 38 | $1,000.00 |
| 2010 | 22 | 22 | $925.00 | 62 | $1,000.00 |
| 2011 | 19 | 19 | $900.00 | 57 | $964.77 |
| 2012 | 16 | 16 | $962.50 | 48 | $1,000.00 |
| 2013 | 18 | 18 | $807.00 | 53 | $900.00 |
| 2014 | 15 | 15 | $900.00 | 44 | $1,000.00 |
| 2015 | 13 | 13 | $1,045.00 | 34 | $1,022.50 |
| 2016 | 23 | 22 | $984.15 | 63 | $990.00 |
| 2017 | 7 | 7 | $1,100.00 | 20 | $1,620.00 |
| 2018 | 13 | 13 | $1,045.00 | 30 | $1,225.00 |
| 2019 | 11 | 11 | $1,125.00 | 29 | $1,300.00 |
| 2020 | 14 | 14 | $1,225.00 | 40 | $1,450.00 |
| 2021 | 15 | 15 | $1,500.00 | 44 | $1,800.00 |
| 2025 | 3 | 3 | $1,850.00 | 9 | $2,000.00 |
| 2026 | 13 | 13 | $1,400.00 | 66 | $2,542.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Bristol | 5 | $1,280.00 | 29 | $2,500.00 |
| Fredericksburg | 3 | $1,400.00 | 13 | $2,500.00 |
| Salem | 3 | $1,850.00 | 11 | $3,000.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 4 to 34 | 4 | $2,043.04 |
| 44 to 100 | 4 | $1,455.00 |
| 115 to 150 | 4 | $1,650.00 |
| 150 to 573.20 | 4 | $1,625.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Lanford Brothers Company, Incorporated | 136 | 59 (43%) |
| Cleco Corporation | 96 | 32 (33%) |
| Ken Construction Co., Inc. | 40 | 27 (68%) |
| M. D. Miller Co., Inc. | 42 | 25 (60%) |
| Burleigh Construction Co., Inc. | 65 | 24 (37%) |
| Elk Knob, Inc. | 79 | 21 (27%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | C0000127207B70 | Salem | 16 | $3,292.20 | $3,146.10 | 4 | King General Contractors, Inc. | VDOT |
| 23 SEP 2026 | C0000128606B15 | Bristol | 150 | $1,200.00 | $1,825.00 | 5 | M. D. Miller Co., Inc. | VDOT |
| 26 AUG 2026 | C0000128603B82 | Bristol | 210 | $1,400.00 | $2,920.00 | 6 | M. D. Miller Co., Inc. | VDOT |
| 22 JUL 2026 | C0000126560B40 | Northern Virginia | 56 | $1,700.00 | $1,700.00 | 7 | Martins Construction Corp. | VDOT |
| 22 JUL 2026 | C0000122360M01 | Fredericksburg | 137 | $1,900.00 | $2,287.50 | 6 | Martins Construction Corp. | VDOT |
| 24 JUN 2026 | C0000121544B01 | Richmond | 4 | $2,686.08 | $2,686.08 | 5 | Freyssinet, Inc. | VDOT |
| 25 MAR 2026 | C0000121244B67 | Bristol | 201 | $2,430.00 | $2,200.00 | 7 | Freyssinet, Inc. | VDOT |
| 25 FEB 2026 | C0000117418B28 | Hampton Roads | 44 | $2,000.00 | $4,391.64 | 4 | OTB ASSOCIATES, LLC dba OTB CONTRACTING | VDOT |
| 25 FEB 2026 | C0000120996B89 | Salem | 86 | $1,210.00 | $2,450.00 | 5 | Structural Technologies, LLC of Maryland | VDOT |
| 04 FEB 2026 | C0000126720N01 | Fredericksburg | 150 | $1,400.00 | $2,100.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 04 FEB 2026 | C0000126721N01 | Fredericksburg | 10 | $1,400.00 | $2,575.00 | 4 | M. D. Miller Co., Inc. | VDOT |
| 04 FEB 2026 | C0000127189N01 | Hampton Roads | 100 | $1,200.00 | $2,350.00 | 2 | M. D. Miller Co., Inc. | VDOT |
| 04 FEB 2026 | C0000123319B54 | Bristol | 34 | $1,150.00 | $2,900.00 | 8 | Freyssinet, Inc. | VDOT |
| 17 DEC 2025 | C0000121000D04 | Salem | 573.20 | $1,850.00 | $3,390.61 | 2 | Crossroads Bridge Inc | VDOT |
| 19 NOV 2025 | C0000124819B65 | Bristol | 115 | $1,280.00 | $2,000.00 | 3 | Freyssinet, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.