Low bidders on VDOT contracts carried a median of $300.00 per LF for this item, over the 24 months to 28 OCT 2026, across 7 low bids. Half of all 27 bids fell between $300.00 and $980.00.
- Owner
- Virginia DOT
- Item
- 412SD20-0046
- Unit
- LF
- Data through
- 28 OCT 2026
VDOT has bid this work under more than one code: 68579 on lettings from 17 DEC 2002 to 27 OCT 2021 (169 bids); 412SD20-0046 on lettings from 19 NOV 2025 to 23 SEP 2026 (27 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 4 | 4 | $103.13 | 12 | $121.56 |
| 2003 | 1 | 1 | $200.00 | 3 | $200.00 |
| 2004 | 1 | 1 | $300.00 | 3 | $300.00 |
| 2007 | 1 | 1 | $450.00 | 2 | $375.00 |
| 2010 | 6 | 6 | $141.00 | 16 | $237.50 |
| 2011 | 3 | 3 | $306.73 | 9 | $349.00 |
| 2012 | 3 | 3 | $325.00 | 9 | $307.00 |
| 2013 | 6 | 6 | $155.00 | 15 | $213.00 |
| 2014 | 3 | 3 | $160.00 | 9 | $180.00 |
| 2015 | 4 | 4 | $312.50 | 11 | $325.00 |
| 2016 | 6 | 6 | $250.00 | 18 | $325.00 |
| 2017 | 5 | 5 | $225.00 | 15 | $280.00 |
| 2018 | 5 | 5 | $300.00 | 12 | $325.00 |
| 2019 | 4 | 4 | $544.60 | 10 | $642.60 |
| 2020 | 4 | 4 | $450.00 | 12 | $550.00 |
| 2021 | 4 | 4 | $425.00 | 11 | $350.00 |
| 2025 | 1 | 1 | $105.00 | 2 | $202.50 |
| 2026 | 6 | 6 | $300.00 | 25 | $520.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Fredericksburg | 12 | $225.00 | 35 | $300.00 |
| Hampton Roads | 13 | $150.00 | 35 | $200.00 |
| Northern Virginia | 8 | $317.50 | 26 | $396.00 |
| Lynchburg | 9 | $350.00 | 25 | $280.00 |
| Salem | 7 | $137.00 | 21 | $300.00 |
| Culpeper | 7 | $213.00 | 18 | $300.00 |
| Bristol | 5 | $225.00 | 16 | $375.00 |
| Richmond | 5 | $250.00 | 15 | $450.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 2 to 39 | 16 | $300.00 |
| 39 to 78 | 17 | $225.00 |
| 80 to 145 | 17 | $250.00 |
| 160 to 660 | 17 | $180.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Lanford Brothers Company, Incorporated | 25 | 14 (56%) |
| M. D. Miller Co., Inc. | 24 | 10 (42%) |
| Crossroads Bridge Inc | 9 | 7 (78%) |
| McClain & Co., Inc. | 11 | 5 (45%) |
| Burleigh Construction Co., Inc. | 14 | 3 (21%) |
| Elk Knob, Inc. | 6 | 3 (50%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 23 SEP 2026 | C0000128606B15 | Bristol | 25 | $250.00 | $450.00 | 5 | M. D. Miller Co., Inc. | VDOT |
| 22 JUL 2026 | C0000126560B40 | Northern Virginia | 133 | $300.00 | $630.00 | 7 | Martins Construction Corp. | VDOT |
| 24 JUN 2026 | C0000127213B53 | Culpeper | 15 | $500.00 | $510.00 | 4 | M. D. Miller Co., Inc. | VDOT |
| 04 FEB 2026 | C0000126720N01 | Fredericksburg | 35 | $300.00 | $800.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 04 FEB 2026 | C0000126721N01 | Fredericksburg | 25 | $400.00 | $725.00 | 4 | M. D. Miller Co., Inc. | VDOT |
| 04 FEB 2026 | C0000127189N01 | Hampton Roads | 100 | $300.00 | $650.00 | 2 | M. D. Miller Co., Inc. | VDOT |
| 19 NOV 2025 | C0000127206B17 | Culpeper | 246 | $105.00 | $202.50 | 2 | Freyssinet, Inc. | VDOT |
| 27 OCT 2021 | C0000118978N01 | Northern Virginia | 50 | $500.00 | $500.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 22 SEP 2021 | C0000118463B20 | Bristol | 25 | $500.00 | $350.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 24 MAR 2021 | C0000116749N01 | Lynchburg | 50 | $350.00 | $350.00 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 20 JAN 2021 | C000117194B612 | Hampton Roads | 565 | $36.61 | $266.88 | 2 | Elite Contracting Group, Inc. | VDOT |
| 16 DEC 2020 | C0000117420N01 | Hampton Roads | 300 | $400.00 | $400.00 | 3 | Curtis Contracting, Inc. | VDOT |
| 22 JUL 2020 | C0000116333N01 | Culpeper | 236 | $213.00 | $300.00 | 3 | Lanford Brothers Company, Incorporated | VDOT |
| 24 JUN 2020 | C0000114954N01 | Hampton Roads | 200 | $700.00 | $700.00 | 3 | Curtis Contracting, Inc. | VDOT |
| 27 MAY 2020 | C000115006B61 | Salem | 2 | $500.00 | $625.00 | 3 | M. D. Miller Co., Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.