VDOT contract C0000120996B89 bid tabulation
Bridge rehabilitation. Let by Virginia DOT on February 25, 2026, Botetourt, Salem. 5 bids received; low bid $1,440,517 by Structural Technologies, LLC of Maryland.
- Owner
- Virginia DOT
- Letting
- 25 FEB 2026
- Pay items
- 26
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Structural Technologies, LLC of Maryland | $1,440,517 | Low |
| 2 | M. D. Miller Co., Inc. | $1,478,235 | +3.0% |
| 3 | Lanford Brothers Company, Incorporated | $1,734,424 | +20% |
| 4 | Gemstone, LLC | $2,395,762 | +66% |
| 5 | Structural Engineering Group, Incorporated | $2,873,947 | +100% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Structural Technologies, LLC of Maryland | 2. M. D. Miller Co., Inc. | 3. Lanford Brothers Company, Incorporated | 4. Gemstone, LLC | 5. Structural Engineering Group, Incorporated |
|---|---|---|---|---|---|---|---|---|
| 0001-0010 | NS cem. stab. approach slab repair (307SX20-0002) | CY | 14 | $5,800.00 | $2,000.00 | $5,500.00 | $3,000.00 | $2,419.62 |
| 0001-0020 | CR reinf. steel CL. III SPR. struct. maint. (406SD20-0013) | LB | 1,600 | $3.40 | $10.00 | $7.00 | $6.50 | $7.33 |
| 0001-0030 | NS bridge superstructure metal rail repair (410SX20-0008) | LF | 110 | $620.00 | $1,000.00 | $500.00 | $650.00 | $821.21 |
| 0001-0040 | Crack repair type C (412SD20-0015) | SY | 14 | $1,100.00 | $250.00 | $500.00 | $880.00 | $1,173.15 |
| 0001-0050 | Embedded galvanic anodes (412SD20-0017) | EACH | 820 | $75.00 | $24.00 | $45.00 | $63.00 | $73.32 |
| 0001-0060 | NS conc. surface color coating maint. (412SD20-0018) | SY | 360 | $54.00 | $75.00 | $100.00 | $95.00 | $124.65 |
| 0001-0070 | H.E.S. patching type B (412SD20-0034) | SY | 68 | $1,200.00 | $1,000.00 | $1,200.00 | $1,300.00 | $1,613.08 |
| 0001-0080 | H.E.S. patching type C (412SD20-0036) | SY | 12 | $3,400.00 | $1,200.00 | $2,500.00 | $3,250.00 | $3,812.74 |
| 0001-0090 | Expansion joint reconstruction hes (412SD20-0042) | LF | 448 | $470.00 | $600.00 | $600.00 | $1,000.00 | $1,173.15 |
| 0001-0100 | Beam end repair (412SD20-0047) | EACH | 12 | $5,000.00 | $3,500.00 | $6,000.00 | $6,000.00 | $7,332.19 |
| 0001-0110 | Conc. superstr. surface repair (412SD20-0049) | SY | 37 | $1,200.00 | $2,200.00 | $3,500.00 | $3,200.00 | $4,362.65 |
| 0001-0120 | Concrete substruct. surface repair (412SD20-0061) | SY | 86 | $1,210.00 | $2,000.00 | $3,500.00 | $2,450.00 | $3,299.49 |
| 0001-0130 | Adhesive based JT. sealer CL. I, 1" maint. (420SD20-0018) | LF | 448 | $48.75 | $120.00 | $185.00 | $300.00 | $322.62 |
| 0001-0140 | NS nbis access, under bridge bridge inspection (430SX20-0001) | DAY | 1 | $2,800.00 | $5,000.00 | $5,000.00 | $5,000.00 | $3,821.42 |
| 0001-0150 | Epoxy overlay maint (431SD20-0002) | SY | 1,068 | $120.00 | $150.00 | $105.00 | $115.00 | $234.63 |
| 0001-0160 | Temporary sign (512SD20-0014) | SF | 156 | $27.75 | $0.01 | $40.00 | $16.44 | $471.02 |
| 0001-0170 | Truck mounted attenuator (512SD20-0023) | HR | 2,112 | $34.50 | $0.01 | $12.00 | $120.00 | $57.43 |
| 0001-0180 | Group 2 channelizing devices (512SD20-0024) | DAY | 6,900 | $0.24 | $0.01 | $1.00 | $12.00 | $11.36 |
| 0001-0190 | Port.changeable mess. sign (512SD20-0025) | HR | 3,200 | $6.50 | $0.01 | $7.00 | $21.00 | $20.74 |
| 0001-0200 | Electronic arrow board (512SD20-0026) | HR | 2,112 | $4.50 | $0.01 | $12.00 | $16.00 | $19.78 |
| 0001-0210 | Flagger service (512SD20-0027) | HR | 2,880 | $83.00 | $0.01 | $60.00 | $72.00 | $90.10 |
| 0001-0220 | Portable temporary rumble strip array (512SP20-0001) | DAY | 180 | $92.00 | $0.01 | $400.00 | $288.00 | $159.43 |
| 0001-0230 | Mobilization (513SD20-0001) | LS | 1 | $102,000 | $372,800 | $70,000 | $150,000 | $234,630 |
| 0001-0240 | NS asbestos removal bridge structures: 011- 2040(03252) & 011-2041(03254) (522SX20-0004) | LS | 1 | $7,800.00 | $20,000 | $9,000.00 | $45,000 | $87,986 |
| 0001-0250 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 450 | $26.50 | $20.00 | $22.00 | $52.79 | $14.66 |
| 0001-0260 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 326 | $26.50 | $20.00 | $26.00 | $52.79 | $14.66 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of February 25, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way