Low bidders on VDOT contracts carried a median of $1,250.00 per EACH for this item, over the 24 months to 28 OCT 2026, across 6 low bids. Half of all 23 bids fell between $1,000.00 and $2,750.00.
- Owner
- Virginia DOT
- Item
- 412SD20-0010
- Unit
- EACH
- Data through
- 28 OCT 2026
VDOT has bid this work under more than one code: 68166 on lettings from 22 APR 2003 to 15 DEC 2021 (156 bids); 412SD20-0010 on lettings from 04 FEB 2026 to 23 SEP 2026 (23 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2003 | 2 | 2 | $450.00 | 5 | $500.00 |
| 2005 | 3 | 3 | $550.00 | 9 | $750.00 |
| 2006 | 1 | 1 | $1,200.00 | 3 | $1,000.00 |
| 2007 | 5 | 5 | $500.00 | 15 | $750.00 |
| 2008 | 2 | 2 | $1,850.00 | 6 | $1,850.00 |
| 2010 | 4 | 4 | $650.00 | 12 | $650.00 |
| 2011 | 3 | 3 | $580.00 | 9 | $670.00 |
| 2012 | 1 | 1 | $950.00 | 3 | $950.00 |
| 2013 | 5 | 5 | $660.00 | 13 | $843.82 |
| 2014 | 4 | 4 | $1,125.00 | 11 | $1,000.00 |
| 2015 | 4 | 4 | $975.00 | 11 | $500.00 |
| 2016 | 5 | 5 | $1,000.00 | 14 | $1,182.00 |
| 2017 | 4 | 4 | $1,000.00 | 11 | $1,000.00 |
| 2018 | 3 | 3 | $750.00 | 6 | $699.50 |
| 2019 | 2 | 2 | $2,297.84 | 5 | $1,000.00 |
| 2020 | 4 | 4 | $685.00 | 11 | $750.75 |
| 2021 | 4 | 4 | $962.50 | 12 | $937.50 |
| 2026 | 6 | 6 | $1,250.00 | 23 | $1,500.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Bristol | 24 | $750.00 | 76 | $1,000.00 |
| Fredericksburg | 10 | $850.00 | 28 | $725.00 |
| Hampton Roads | 9 | $1,000.00 | 25 | $1,000.00 |
| Richmond | 7 | $1,000.00 | 20 | $1,166.00 |
| Culpeper | 4 | $575.00 | 9 | $575.00 |
| Staunton | 3 | $700.00 | 8 | $750.00 |
| Northern Virginia | 3 | $320.00 | 7 | $320.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 4 | 15 | $1,000.00 |
| 4 to 11 | 16 | $975.00 |
| 11 to 28 | 15 | $750.00 |
| 30 to 312 | 16 | $725.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Lanford Brothers Company, Incorporated | 27 | 15 (56%) |
| M. D. Miller Co., Inc. | 19 | 9 (47%) |
| Crossroads Bridge Inc | 8 | 5 (63%) |
| Elk Knob, Inc. | 19 | 4 (21%) |
| Cleco Corporation | 12 | 2 (17%) |
| Ken Construction Co., Inc. | 7 | 2 (29%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 23 SEP 2026 | C0000128606B15 | Bristol | 10 | $1,500.00 | $1,388.63 | 5 | M. D. Miller Co., Inc. | VDOT |
| 26 AUG 2026 | C0000128603B82 | Bristol | 17 | $1,500.00 | $1,587.16 | 6 | M. D. Miller Co., Inc. | VDOT |
| 24 JUN 2026 | C0000128696N01 | Staunton | 48 | $900.00 | $900.00 | 3 | Lanford Brothers Company, Incorporated | VDOT |
| 25 FEB 2026 | C0000117418B28 | Hampton Roads | 2 | $4,500.00 | $6,628.95 | 4 | OTB ASSOCIATES, LLC dba OTB CONTRACTING | VDOT |
| 04 FEB 2026 | C0000126720N01 | Fredericksburg | 6 | $1,000.00 | $1,600.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 04 FEB 2026 | C0000127189N01 | Hampton Roads | 35 | $1,000.00 | $1,250.00 | 2 | M. D. Miller Co., Inc. | VDOT |
| 15 DEC 2021 | C0000113885N01 | Bristol | 16 | $500.00 | $550.00 | 3 | Crossroads Bridge Inc | VDOT |
| 22 SEP 2021 | C0000118463B20 | Bristol | 10 | $1,000.00 | $950.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 28 APR 2021 | C0000115172B01 | Bristol | 5 | $1,000.00 | $1,400.00 | 3 | Crossroads Bridge Inc | VDOT |
| 24 FEB 2021 | C0000117348B63 | Bristol | 40 | $925.00 | $920.00 | 3 | Elk Knob, Inc. | VDOT |
| 22 JUL 2020 | C0000116333N01 | Culpeper | 4 | $575.00 | $750.00 | 3 | Lanford Brothers Company, Incorporated | VDOT |
| 24 JUN 2020 | C0000112505N01 | Northern Virginia | 42 | $620.00 | $685.38 | 2 | Martins Construction Corp. | VDOT |
| 24 JUN 2020 | C0000114954N01 | Hampton Roads | 10 | $2,500.00 | $2,500.00 | 3 | Curtis Contracting, Inc. | VDOT |
| 27 MAY 2020 | C000115006B61 | Salem | 31 | $750.00 | $2,000.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 22 MAY 2019 | C000114328N01B | Hampton Roads | 20 | $1,000.00 | $1,000.00 | 2 | Coastal Gunite Construction Company | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way