VDOT contract C0000122877C01 bid tabulation
Safety improvements. Let by Virginia DOT on March 25, 2026, Washington, Bristol. 3 bids received; low bid $1,485,086 by W-L Construction & Paving, Inc..
- Owner
- Virginia DOT
- Letting
- 25 MAR 2026
- Pay items
- 85
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | W-L Construction & Paving, Inc. | $1,485,086 | Low |
| 2 | Jones Road & Bridge, Inc. | $1,684,828 | +13% |
| 3 | Mountain Fuels, Inc. | $1,849,338 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. W-L Construction & Paving, Inc. | 2. Jones Road & Bridge, Inc. | 3. Mountain Fuels, Inc. |
|---|---|---|---|---|---|---|
| 0001-0010 | Clearing and grubbing (301SD20-0001) | LS | 1 | $22,542 | $145,300 | $72,000 |
| 0001-0020 | Endwall EW-12 (302SD20-0013) | EACH | 2 | $1,189.14 | $1,305.00 | $1,000.00 |
| 0001-0030 | 18" pipe (302SD20-0028) | LF | 82 | $219.50 | $208.00 | $250.00 |
| 0001-0040 | 18" conc. pipe (302SD20-0030) | LF | 210 | $281.00 | $248.00 | $350.00 |
| 0001-0050 | 18" storm sewer pipe (302SD20-0032) | LF | 204 | $257.12 | $200.00 | $250.00 |
| 0001-0060 | 24" pipe (302SD20-0037) | LF | 29 | $266.28 | $245.00 | $400.00 |
| 0001-0070 | 18" end section ES-1 or 2 (302SD20-0200) | EACH | 3 | $1,180.53 | $1,245.00 | $2,000.00 |
| 0001-0080 | 24" end section ES-1 or 2 (302SD20-0204) | EACH | 2 | $1,275.90 | $1,280.00 | $3,000.00 |
| 0001-0090 | Drop inlet DI-5 (302SD20-0446) | EACH | 2 | $6,080.93 | $7,220.00 | $10,000 |
| 0001-0100 | Drop inlet DI-10K TY. II,L=10' (302SD20-0502) | EACH | 1 | $20,961 | $20,000 | $18,500 |
| 0001-0110 | Manhole MH-1 or 2 (302SD20-0662) | LF | 8.40 | $952.30 | $1,000.00 | $1,200.00 |
| 0001-0120 | Frame & cover MH-1 (302SD20-0663) | EACH | 2 | $1,059.60 | $1,000.00 | $1,000.00 |
| 0001-0130 | Regular excavation (303SD20-0001) | CY | 805 | $65.53 | $60.00 | $60.00 |
| 0001-0140 | Borrow excavation (303SD20-0007) | CY | 729 | $72.36 | $51.00 | $100.00 |
| 0001-0150 | Check dam rock TY. II (303SD20-0023) | EACH | 14 | $533.54 | $590.00 | $600.00 |
| 0001-0160 | Siltation control excavation (303SD20-0029) | CY | 419 | $2.13 | $0.02 | $20.00 |
| 0001-0170 | Inlet protection type A (303SD20-0030) | EACH | 4 | $571.96 | $630.00 | $500.00 |
| 0001-0180 | Inlet protection type B (303SD20-0031) | EACH | 2 | $711.61 | $610.00 | $800.00 |
| 0001-0190 | Temp. silt fence type A (303SD20-0034) | LF | 2,129 | $7.23 | $6.50 | $8.00 |
| 0001-0200 | Aggr. matl. no. 1 (305SD20-0010) | TON | 150 | $58.77 | $65.00 | $50.00 |
| 0001-0210 | Aggr. matl. no. 21B (308SD20-0007) | TON | 882 | $58.02 | $62.00 | $50.00 |
| 0001-0220 | Crusher run aggr. no. 25 or 26 (308SX20-0003) | TON | 20 | $81.54 | $72.00 | $100.00 |
| 0001-0230 | Tack coat (310SD20-0001) | GAL | 421 | $4.94 | $6.50 | $5.00 |
| 0001-0240 | Asphalt concrete TY. SM- 12.5E const (315SD20-0003) | TON | 826 | $180.38 | $235.00 | $181.00 |
| 0001-0250 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 499 | $161.63 | $210.00 | $165.00 |
| 0001-0260 | Rumble strip cylindrical asphalt (315SD20-0015) | LF | 1,929 | $3.74 | $5.00 | $1.25 |
| 0001-0270 | Liquid asphalt coating (rumble strip) (315SD20-0019) | SY | 358 | $8.34 | $8.00 | $10.00 |
| 0001-0280 | Saw-cut asphalt concrete full depth (315SD20-0104) | LF | 2,547 | $5.73 | $6.00 | $1.00 |
| 0001-0290 | Erosion CTRL. stone CL. A1, EC-1 (414SD20-0001) | TON | 6.20 | $150.47 | $80.00 | $100.00 |
| 0001-0300 | Erosion CTRL. stone CL. I, EC-1 (414SD20-0003) | TON | 2.30 | $299.37 | $124.00 | $100.00 |
| 0001-0310 | Dry riprap CL.I 26" (414SD20-0012) | TON | 59 | $124.56 | $90.00 | $100.00 |
| 0001-0320 | Underdrain UD-4 (501SD20-0004) | LF | 528 | $28.55 | $42.00 | $30.00 |
| 0001-0330 | Outlet pipe (501SD20-0009) | LF | 44 | $43.06 | $49.00 | $30.00 |
| 0001-0340 | Median barrier MB-8A type III (502SD20-0046) | LF | 226 | $559.34 | $700.00 | $500.00 |
| 0001-0350 | Median strip MS-1A (502SD20-0056) | SY | 119 | $353.18 | $220.00 | $270.00 |
| 0001-0360 | Remove EX. guardrail terminal (505SD20-0009) | EACH | 1 | $1,298.40 | $1,453.00 | $2,000.00 |
| 0001-0370 | Guardrail GR-2 (505SD20-0030) | LF | 144 | $30.30 | $34.00 | $100.00 |
| 0001-0380 | Fixed object attach. GR- foa-2 TY. I (505SD20-0053) | EACH | 1 | $5,410.00 | $13,100 | $10,800 |
| 0001-0390 | Remove existing guardrail (505SD20-0073) | LF | 247 | $6.49 | $8.00 | $6.00 |
| 0001-0400 | Obscuring roadway (508SD20-0001) | UNIT | 3.80 | $1,246.84 | $5,800.00 | $1,000.00 |
| 0001-0410 | Demo. of pavement flexible (508SD20-0004) | SY | 1,337 | $20.54 | $37.00 | $12.00 |
| 0001-0420 | Flowable backfill (509SD20-0001) | CY | 9 | $545.88 | $462.00 | $600.00 |
| 0001-0430 | Allaying dust (511SD20-0001) | HR | 70 | $48.88 | $26.00 | $40.00 |
| 0001-0440 | Traffic barrier service MB-11A (512SD20-0003) | LF | 1,175 | $68.92 | $66.00 | $90.00 |
| 0001-0450 | Impact atten.ser. TY. 1 TL- 3, >=40 MPH (512SD20-0007) | EACH | 1 | $15,148 | $15,150 | $33,500 |
| 0001-0460 | Type 3 barricade 8' (512SD20-0013) | EACH | 4 | $697.43 | $680.00 | $600.00 |
| 0001-0470 | Temporary sign (512SD20-0014) | SF | 1,537 | $24.00 | $30.00 | $22.00 |
| 0001-0480 | Truck mounted attenuator (512SD20-0023) | HR | 660 | $36.57 | $18.00 | $55.00 |
| 0001-0490 | Group 2 channelizing devices (512SD20-0024) | DAY | 12,450 | $1.53 | $1.00 | $1.50 |
| 0001-0500 | Port.changeable mess. sign (512SD20-0025) | HR | 1,512 | $10.61 | $5.00 | $9.00 |
| 0001-0510 | Electronic arrow board (512SD20-0026) | HR | 360 | $9.00 | $5.00 | $10.00 |
| 0001-0520 | Temp. PVMT MRKG TY. E, 6" (512SD20-0054) | LF | 1,230 | $3.47 | $4.00 | $3.75 |
| 0001-0530 | Temp. PVMT MRKG TY. D, CL. III, 4" (512SD20-0061) | LF | 389 | $2.13 | $2.40 | $3.75 |
| 0001-0540 | Temp. PVMT MRKG TY. D, CL. III, 6" (512SD20-0062) | LF | 4,482 | $2.83 | $3.20 | $3.50 |
| 0001-0550 | Temp. PVMT MRKG TY. D, CL. III, 8" (512SD20-0063) | LF | 1,394 | $3.70 | $4.20 | $5.75 |
| 0001-0560 | Impact attenuator IA-1 (512SD20-0069) | EACH | 1 | $30,296 | $36,500 | $15,000 |
| 0001-0570 | Mobilization (513SD20-0001) | LS | 1 | $75,173 | $77,700 | $353,000 |
| 0001-0580 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 5,613 | $6.83 | $8.50 | $6.83 |
| 0001-0590 | Construction surveying constr. (517SD20-0001) | LS | 1 | $65,230 | $28,860 | $50,000 |
| 0001-0600 | Topsoil class A (602SD20-0002) | CY | 202 | $70.08 | $79.00 | $100.00 |
| 0001-0610 | Topsoil class B (602SD20-0004) | CY | 202 | $158.43 | $185.00 | $100.00 |
| 0001-0620 | Temporary seed (603SD20-0002) | LB | 300 | $16.23 | $15.00 | $15.00 |
| 0001-0630 | Regular seed (603SD20-0003) | LB | 425 | $17.31 | $16.00 | $16.00 |
| 0001-0640 | Overseeding (603SD20-0004) | LB | 340 | $17.31 | $16.00 | $16.00 |
| 0001-0650 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 12,100 | $0.92 | $1.00 | $1.00 |
| 0001-0660 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 9,680 | $1.08 | $1.00 | $1.00 |
| 0001-0670 | Fertilizer nitrogen - N (603SD20-0014) | LB | 200 | $2.16 | $2.00 | $2.00 |
| 0001-0680 | Fertilizer phosphorous - P (603SD20-0015) | LB | 140 | $2.16 | $2.00 | $2.00 |
| 0001-0690 | Fertilizer potassium - K (603SD20-0016) | LB | 140 | $2.16 | $2.00 | $2.00 |
| 0001-0700 | Lime (603SD20-0017) | TON | 11 | $162.30 | $150.00 | $150.00 |
| 0001-0710 | Rolled erosion CTRL product EC-2 type 1 (606SD20-0001) | SY | 956 | $5.41 | $5.00 | $5.00 |
| 0001-0720 | Rolled erosion CTRL product EC-2 type 3 (606SD20-0003) | SY | 253 | $7.57 | $7.00 | $9.00 |
| 0001-0730 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 15 | $405.75 | $455.00 | $400.00 |
| 0001-0740 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 4 | $189.35 | $212.00 | $400.00 |
| 0001-0750 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 140 | $17.31 | $19.00 | $30.00 |
| 0001-0760 | Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036) | LF | 15 | $21.64 | $25.00 | $50.00 |
| 0001-0770 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 82 | $19.48 | $22.00 | $50.00 |
| 0001-0780 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 17 | $640.54 | $715.00 | $600.00 |
| 0001-0790 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 1 | $970.55 | $1,100.00 | $1,000.00 |
| 0001-0800 | NS traffic sign barrier attachment (700SX20-0021) | EACH | 2 | $1,018.16 | $1,250.00 | $500.00 |
| 0001-0810 | Sign panel (701SD20-0001) | SF | 148 | $29.92 | $35.00 | $65.00 |
| 0001-0820 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 4,971 | $2.20 | $2.50 | $1.50 |
| 0001-0830 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 28 | $251.18 | $280.00 | $100.00 |
| 0001-0840 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 2 | $510.15 | $570.00 | $400.00 |
| 0001-0850 | PVMT symb MRKG yield 1' X 1.5' TY B CL II (704SD20-0084) | EACH | 9 | $48.18 | $55.00 | $425.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of March 25, 2026. Compiled by Mirage Metrics.