Reinforcing steel substruct. maint., VDOT 406SD20-0019

Low bidders on VDOT contracts carried a median of $17.50 per LB for this item, over the 24 months to 28 OCT 2026, across 2 low bids. Half of all 5 bids fell between $10.00 and $25.00.

Owner
Virginia DOT
Item
406SD20-0019
Unit
LB
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 69100 on lettings from 23 APR 2002 to 25 AUG 2021 (133 bids); 406SD20-0019 on lettings from 17 DEC 2025 to 04 FEB 2026 (5 bids). They are combined here into one trend.

$17.50Low bidder's median, per LB
$15.00Median of all bids, per LB
2Contracts in the window

By year of letting

Reinforcing steel substruct. maint., VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200233$0.859$1.00
200355$2.1015$2.10
200433$0.908$1.00
200522$1.736$2.00
200633$1.609$1.60
200777$1.1421$1.25
200822$1.236$1.15
201022$3.505$3.00
201333$2.009$2.00
201411$1.973$1.97
201566$1.5712$2.25
201611$6.383$2.00
201722$1.626$2.12
201822$1.606$1.65
201911$3.003$5.00
202022$1.856$1.70
202122$3.106$3.17
202511$25.002$83.82
202611$10.003$10.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Bristol15$1.7045$1.74
Salem9$2.0026$2.00
Fredericksburg7$2.5719$4.00
Northern Virginia7$1.5018$1.67
Culpeper3$1.259$2.00
Lynchburg3$2.008$2.00
Reinforcing steel substruct. maint., VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (LB)Low bidsLow-bid median
34 to 38012$3.29
380 to 70212$2.05
800 to 2,78012$1.62
2,800 to 59,37013$1.14
Reinforcing steel substruct. maint., VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Elk Knob, Inc.126 (50%)
Ken Construction Co., Inc.74 (57%)
Patrick Construction, Inc.64 (67%)
Crossroads Bridge Inc54 (80%)
DLB, Inc.73 (43%)
Burleigh Construction Co., Inc.62 (33%)
Reinforcing steel substruct. maint., VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
04 FEB 2026C0000126720N01Fredericksburg500$10.00$10.003M. D. Miller Co., Inc.VDOT
17 DEC 2025C0000121000D04Salem34$25.00$83.822Crossroads Bridge IncVDOT
25 AUG 2021C0000110623D26Salem290$4.00$4.003Crossroads Bridge IncVDOT
20 JAN 2021CM820BRA117425Staunton5,760$2.20$2.203Jones Road & Bridge, Inc.VDOT
21 OCT 2020C0000101043B60Lynchburg160$2.00$2.003Stonewall Bridge, Inc.VDOT
21 OCT 2020C0000105898B97Northern Virginia28,530$1.70$1.703Corman Kokosing Construction CompanyVDOT
24 JUL 2019C000081548B35BBristol440$3.00$5.003Patrick Construction, Inc.VDOT
25 APR 2018C0000104837B07Bristol2,768$1.70$1.703Orders Construction Company, Inc.VDOT
24 JAN 2018C000109813C01BNorthern Virginia59,370$1.50$1.603Ardent Company, LLCVDOT
16 MAR 2017C0000110467B85Northern Virginia2,048$2.15$3.003Fort Myer Construction CorporationVDOT
25 JAN 2017C0000103500B46Bristol2,800$1.10$1.303Patrick Construction, Inc.VDOT
03 FEB 2016C0000103558B63Bristol380$6.38$2.003Estes Bros. Const., Inc.VDOT
18 NOV 2015CM0000107633C01Fredericksburg200$5.00$4.502M. D. Miller Co., Inc.VDOT
24 JUN 2015C0000106829B40Fredericksburg1,920$1.65$4.003Burleigh Construction Co., Inc.VDOT
25 MAR 2015C00106511N01Bristol500$2.00$2.003Elk Knob, Inc.VDOT
Latest VDOT contracts carrying Reinforcing steel substruct. maint.

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.