Concrete class A3, VDOT 404SD20-0021
Low bidders on VDOT contracts carried a median of $3,078.50 per CY for this item, over the 24 months to 28 OCT 2026, across 2 low bids. Half of all 9 bids fell between $3,601.00 and $6,500.00.
- Owner
- Virginia DOT
- Item
- 404SD20-0021
- Unit
- CY
- Data through
- 28 OCT 2026
VDOT prints this item as “CONCRETE CLASS A3 SUBSTRUCT. MAINT.”.
VDOT has bid this work under more than one code: 69030 on lettings from 11 MAR 2002 to 27 OCT 2021 (358 bids); 404SD20-0021 on lettings from 22 APR 2026 to 22 APR 2026 (9 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 6 | 6 | $839.79 | 18 | $675.00 |
| 2003 | 4 | 4 | $538.75 | 12 | $700.00 |
| 2004 | 5 | 5 | $800.00 | 13 | $890.00 |
| 2005 | 6 | 6 | $950.00 | 18 | $1,200.00 |
| 2006 | 6 | 6 | $787.50 | 18 | $1,275.00 |
| 2007 | 14 | 14 | $875.00 | 42 | $1,235.00 |
| 2008 | 7 | 7 | $700.00 | 21 | $850.00 |
| 2009 | 3 | 3 | $1,500.00 | 9 | $1,500.00 |
| 2010 | 8 | 8 | $812.50 | 22 | $1,251.73 |
| 2011 | 5 | 5 | $1,225.00 | 15 | $1,200.00 |
| 2012 | 4 | 4 | $2,250.00 | 12 | $2,100.00 |
| 2013 | 9 | 9 | $1,500.00 | 26 | $2,000.00 |
| 2014 | 5 | 5 | $2,500.00 | 14 | $1,500.00 |
| 2015 | 7 | 7 | $1,000.00 | 18 | $1,350.00 |
| 2016 | 10 | 10 | $1,449.94 | 30 | $1,500.00 |
| 2017 | 3 | 3 | $1,000.00 | 9 | $1,326.84 |
| 2018 | 6 | 6 | $1,850.00 | 14 | $1,775.00 |
| 2019 | 7 | 7 | $2,000.00 | 21 | $2,000.00 |
| 2020 | 6 | 6 | $1,300.00 | 17 | $2,150.00 |
| 2021 | 3 | 3 | $1,100.00 | 9 | $2,000.00 |
| 2026 | 2 | 2 | $3,078.50 | 9 | $5,000.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Bristol | 49 | $1,225.00 | 146 | $1,474.94 |
| Salem | 26 | $1,150.00 | 77 | $1,200.00 |
| Culpeper | 13 | $1,200.00 | 38 | $1,500.00 |
| Richmond | 10 | $1,809.80 | 28 | $1,571.99 |
| Lynchburg | 8 | $2,000.00 | 23 | $1,650.00 |
| Northern Virginia | 7 | $1,600.00 | 18 | $1,266.00 |
| Staunton | 6 | $716.75 | 17 | $800.00 |
| Fredericksburg | 5 | $1,200.00 | 14 | $1,200.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 0.60 to 4.30 | 31 | $2,500.00 |
| 5 to 13 | 32 | $1,000.00 |
| 13.20 to 26.30 | 31 | $1,350.00 |
| 27 to 654.40 | 32 | $762.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| D. A. Brown, Inc. | 18 | 13 (72%) |
| Crossroads Bridge Inc | 22 | 12 (55%) |
| Ken Construction Co., Inc. | 25 | 11 (44%) |
| Patrick Construction, Inc. | 21 | 10 (48%) |
| Cleco Corporation | 11 | 6 (55%) |
| Corman Construction, Inc. | 11 | 5 (45%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 APR 2026 | C0000117081B10 | Bristol | 4 | $2,556.00 | $5,000.00 | 5 | Glass Machinery and Excavation, Inc. | VDOT |
| 22 APR 2026 | C0000120999D01 | Salem | 4.20 | $3,601.00 | $5,050.50 | 4 | Jones Road & Bridge, Inc. | VDOT |
| 27 OCT 2021 | C0000119068B29 | Hampton Roads | 6 | $3,536.50 | $3,536.50 | 3 | Curtis Contracting, Inc. | VDOT |
| 25 AUG 2021 | C0000110623D26 | Salem | 3.20 | $1,100.00 | $2,000.00 | 3 | Crossroads Bridge Inc | VDOT |
| 20 JAN 2021 | CM820BRA117425 | Staunton | 65.90 | $725.00 | $800.00 | 3 | Jones Road & Bridge, Inc. | VDOT |
| 16 DEC 2020 | C0000113878B08 | Bristol | 16.20 | $748.00 | $750.00 | 3 | Glass Machinery and Excavation, Inc. | VDOT |
| 21 OCT 2020 | C0000101043B60 | Lynchburg | 1.40 | $1,000.00 | $8,200.00 | 3 | Stonewall Bridge, Inc. | VDOT |
| 21 OCT 2020 | C0000105898B97 | Northern Virginia | 249.30 | $1,600.00 | $1,600.00 | 3 | Corman Kokosing Construction Company | VDOT |
| 24 JUN 2020 | C0000114769B01 | Staunton | 138.90 | $300.00 | $1,287.50 | 2 | Curtis Contracting, Inc. | VDOT |
| 24 JUN 2020 | C000101246M01B | Richmond | 4.30 | $9,500.00 | $9,500.00 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 22 APR 2020 | C0000111298B10 | Richmond | 45.60 | $4,900.00 | $4,000.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 13 NOV 2019 | C0000110952B50 | Bristol | 0.60 | $3,250.00 | $3,950.00 | 3 | Glass Machinery and Excavation, Inc. | VDOT |
| 21 AUG 2019 | C000110011B49 | Bristol | 1.60 | $7,838.25 | $2,500.00 | 3 | Estes Bros. Const., Inc. | VDOT |
| 24 JUL 2019 | C000081548B35B | Bristol | 16.10 | $2,000.00 | $2,000.00 | 3 | Patrick Construction, Inc. | VDOT |
| 26 JUN 2019 | C0000111264B61 | Bristol | 18.20 | $1,650.00 | $1,600.00 | 3 | Patrick Construction, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.