Abernathy Construction Corporation submitted 85 bids on Virginia DOT contracts in the data, from 26 MAR 2002 to 24 JUN 2026, and was the low bidder on 24 of them (28%). When it was not low, its total sat a median +14% above the low bid.
- Owner
- Virginia DOT
- Low bid volume
- $42,917,919
- Latest bid
- 24 JUN 2026
- Data through
- 28 OCT 2026
VDOT's 2002 to 2021 workbooks list only the three lowest bids on each contract, so a firm's bids that ranked fourth or lower in those years are missing: bid counts are understated and win rates overstated for those years.
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2002 | 4 | 2 | 50% |
| 2003 | 12 | 2 | 17% |
| 2004 | 6 | 1 | 17% |
| 2005 | 4 | 1 | 25% |
| 2006 | 6 | 0 | 0% |
| 2007 | 5 | 2 | 40% |
| 2008 | 1 | 0 | 0% |
| 2009 | 2 | 1 | 50% |
| 2010 | 4 | 3 | 75% |
| 2011 | 5 | 2 | 40% |
| 2012 | 5 | 3 | 60% |
| 2013 | 5 | 1 | 20% |
| 2015 | 5 | 1 | 20% |
| 2016 | 6 | 2 | 33% |
| 2017 | 1 | 0 | 0% |
| 2018 | 3 | 0 | 0% |
| 2019 | 5 | 2 | 40% |
| 2020 | 2 | 0 | 0% |
| 2021 | 1 | 1 | 100% |
| 2026 | 3 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Fredericksburg | 43 | 11 | 26% |
| Richmond | 20 | 8 | 40% |
| Hampton Roads | 14 | 2 | 14% |
| Culpeper | 5 | 2 | 40% |
| Northern Virginia | 3 | 1 | 33% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Dewatering basin EC-8 | 303SD20-0028 | EACH | 51 | 31 (61%) | $650.00 | $1,000.00 |
| Alt.breakaway cable term. GR-9 | 505SD20-0038 | EACH | 43 | 26 (60%) | $2,290.00 | $2,425.00 |
| Check dam rock TY. II | 303SD20-0023 | EACH | 41 | 23 (56%) | $205.00 | $250.00 |
| Temp. silt fence type A | 303SD20-0034 | LF | 54 | 22 (41%) | $4.00 | $3.00 |
| Regular seed | 603SD20-0003 | LB | 51 | 22 (43%) | $20.00 | $13.50 |
| Flagger service | 512SD20-0027 | HR | 41 | 21 (51%) | $18.00 | $20.00 |
| Demo. of pavement flexible | 508SD20-0004 | SY | 32 | 20 (63%) | $6.50 | $9.00 |
| Guardrail GR-2 | 505SD20-0030 | LF | 38 | 18 (47%) | $18.50 | $18.00 |
| Siltation control excavation | 303SD20-0029 | CY | 51 | 16 (31%) | $10.00 | $3.50 |
| Regular excavation | 303SD20-0001 | CY | 38 | 15 (39%) | $30.00 | $31.00 |
| Borrow excavation | 305SD20-0001 | CY | 34 | 15 (44%) | $17.50 | $20.00 |
| Group 2 channelizing devices | 512SD20-0024 | DAY | 51 | 13 (25%) | $1.00 | $1.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Bryant Contracting, Inc. | 15 | 8 of 15 |
| Corman Construction, Inc. | 14 | 6 of 14 |
| J. L. Kent & Sons, Inc. | 12 | 9 of 12 |
| D. W. Lyle Corporation | 8 | 4 of 8 |
| Howard Brothers Contractor, Inc. | 6 | 2 of 6 |
| Curtis Contracting, Inc. | 6 | 4 of 6 |
| Burleigh Construction Co., Inc. | 6 | 5 of 6 |
| J. Sanders Construction Co. | 5 | 4 of 5 |
| Infrastructure and Industrial Constructors Southeast, Inc. | 5 | 2 of 5 |
| English Construction Company, Incorporated | 4 | 2 of 4 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 24 JUN 2026 | C0000121544B01 | Richmond | Superstructure replacement | 2 of 5 | $968,111 | +5.0% |
| 25 MAR 2026 | C0000121531B68 | Hampton Roads | Bridge replacement over seacock swamp | 4 of 7 | $4,946,794 | +24% |
| 04 FEB 2026 | C0000122528N01 | Hampton Roads | Culvert replacement | 3 of 6 | $1,977,315 | +91% |
| 20 JAN 2021 | C0000109988C01 | Richmond | Sgr - bridge replacement over newfound river | 1 of 3 | $986,476 | Low, 2.0% under the second |
| 16 DEC 2020 | C0000101034C01 | Richmond | Smart scale - intersection improvement | 3 of 3 | $7,903,057 | +20% |
| 21 OCT 2020 | C0000111392B46 | Fredericksburg | Sgr - legacy bridge replacement over south river | 2 of 3 | $1,074,780 | +9.0% |
| 25 SEP 2019 | C0000110111B21 | Fredericksburg | Sgr - sbl bridge replacement over mattaponi river | 3 of 3 | $5,906,892 | +3.0% |
| 25 SEP 2019 | C0000110901B11 | Fredericksburg | Sgr - bridge replacement over exol swamp | 2 of 3 | $1,475,159 | +9.0% |
| 25 SEP 2019 | C000110088B13 | Fredericksburg | Sgr - bridge replacement over piscataway creek | 2 of 2 | $1,232,606 | +13% |
| 21 AUG 2019 | C0000110112B17 | Fredericksburg | Sgr - bridge replacement over harrison's creek | 1 of 2 | $1,067,062 | Low, 12% under the second |
| 15 JAN 2019 | C000114662B10 | Northern Virginia | Rte. 634 over clarks millpond, northumberland county | 1 of 2 | $1,258,633 | Low, 18% under the second |
| 28 MAR 2018 | C0000104965B63 | Hampton Roads | Sgr - bridge on rte. 308 over three creek | 3 of 3 | $2,737,042 | +26% |
| 01 MAR 2018 | CM618BEB39549 | Fredericksburg | Culvert replacement - rte. 608 over massaponax creek | 2 of 2 | $783,991 | +1.0% |
| 26 JAN 2018 | 0M618BEA39521 | Northern Virginia | Culvert rehabilitation- rte 3 over laten's swamp | 3 of 3 | $655,089 | +33% |
| 23 AUG 2017 | C0000104009M01 | Hampton Roads | Bridge replacements over blackwater river | 3 of 3 | $3,971,024 | +21% |
| 21 DEC 2016 | C0000081502B15 | Fredericksburg | Bridge route 1003 (chelsea road) over sandy creek | 2 of 3 | $1,240,725 | +1.0% |
| 24 AUG 2016 | C00101493B39 | Hampton Roads | Prop bridge rte 35 (main st/meherrin rd) over tarrara creek | 1 of 3 | $1,797,486 | Low, 3.0% under the second |
| 22 JUN 2016 | C0000100828B01 | Fredericksburg | Bridge replacement on rte 721 over beverly creek | 2 of 3 | $1,643,455 | +10% |
| 27 APR 2016 | C000106606D643 | Richmond | Rte 729 - replace pipe | 3 of 3 | $645,381 | +79% |
| 24 FEB 2016 | C0000100951B32 | Hampton Roads | Replacement brdg. over mill swamp & over stalling creek | 1 of 3 | $1,775,519 | Low, 14% under the second |
| 24 FEB 2016 | C0000104689M01 | Fredericksburg | Route 360 / route 3 business pedestrian accommodations | 2 of 2 | $417,439 | +37% |
| 16 DEC 2015 | C0000101243C01 | Richmond | Rte 604 - replace bridge over tomahawk creek | 3 of 3 | $2,047,230 | +26% |
| 18 NOV 2015 | C0000093079B65 | Hampton Roads | Rte. 659 bridge over flat swamp | 2 of 3 | $1,451,988 | +13% |
| 28 OCT 2015 | C000002103C03B | Northern Virginia | Intersection reconstruction with route 205 | 3 of 3 | $1,430,388 | +19% |
| 20 MAY 2015 | C00097521B08B | Fredericksburg | Route 198 (dutton road) over harper creek | 2 of 2 | $1,761,224 | +28% |
How this record was read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Every bid counted here matched its published total to within one dollar; VDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.