VDOT contract C0000122528N01 bid tabulation
Culvert replacement. Let by Virginia DOT on February 4, 2026, Southampton, Hampton Roads. 6 bids received; low bid $1,032,642 by Freyssinet, Inc..
- Owner
- Virginia DOT
- Letting
- 04 FEB 2026
- Pay items
- 58
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Freyssinet, Inc. | $1,032,642 | Low |
| 2 | Gray and Sons Construction, Inc. | $1,853,493 | +79% |
| 3 | Abernathy Construction Corporation | $1,977,315 | +91% |
| 4 | Howard Brothers Contractor, Inc. | $2,267,444 | +120% |
| 5 | Landwerks Contracting, LLC | $3,192,725 | +209% |
| 6 | Tidewater Utility Construction, Inc. | $4,493,288 | +335% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Freyssinet, Inc. | 2. Gray and Sons Construction, Inc. | 3. Abernathy Construction Corporation | 4. Howard Brothers Contractor, Inc. | 5. Landwerks Contracting, LLC | 6. Tidewater Utility Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001-0010 | Clearing and grubbing (301SD20-0001) | LS | 1 | $15,800 | $25,000 | $114,000 | $550,000 | $175,000 | $65,000 |
| 0001-0020 | Bedding matl.aggr.no. 25 or 26 (302SD20-0001) | TON | 172 | $65.00 | $58.00 | $103.00 | $45.00 | $45.00 | $200.00 |
| 0001-0030 | Bedding matl. aggr. no. 57 (302SD20-0002) | TON | 187 | $67.00 | $98.00 | $108.00 | $60.00 | $55.00 | $200.00 |
| 0001-0040 | Concrete class A4 box culvert (302SD20-0004) | CY | 39 | $1,840.00 | $3,600.00 | $3,800.00 | $4,000.00 | $6,000.00 | $8,750.00 |
| 0001-0050 | Reinf. steel (302SD20-0005) | LB | 4,429 | $4.00 | $10.00 | $3.30 | $8.00 | $10.00 | $17.00 |
| 0001-0060 | Endwall EW-12 (302SD20-0013) | EACH | 4 | $1,850.00 | $2,560.00 | $1,085.00 | $1,000.00 | $11,000 | $27,000 |
| 0001-0070 | Temp. dive. channel lining CL. A (302SD20-0670) | SY | 1,389 | $12.00 | $8.00 | $7.20 | $5.00 | $39.00 | $125.00 |
| 0001-0080 | NS precast box culvert 10X5 box culvert (302SX20-0005) | LF | 76 | $3,120.00 | $7,400.00 | $3,700.00 | $4,000.00 | $12,000 | $20,000 |
| 0001-0090 | Regular excavation (303SD20-0001) | CY | 752 | $17.00 | $58.00 | $57.00 | $25.00 | $60.00 | $95.00 |
| 0001-0100 | Minor STR. excav. box culvert (303SD20-0017) | CY | 533 | $17.00 | $48.00 | $74.00 | $40.00 | $45.00 | $75.00 |
| 0001-0110 | Erosion control mulch (303SD20-0019) | SY | 157 | $27.00 | $2.80 | $15.00 | $1.00 | $12.00 | $30.00 |
| 0001-0120 | Check dam rock TY. II (303SD20-0023) | EACH | 7 | $1,970.00 | $450.00 | $465.00 | $500.00 | $1,500.00 | $1,250.00 |
| 0001-0130 | Dewatering basin EC-8 (303SD20-0028) | EACH | 1 | $3,130.00 | $14,800 | $980.00 | $1,000.00 | $15,000 | $10,000 |
| 0001-0140 | Siltation control excavation (303SD20-0029) | CY | 69 | $17.00 | $24.00 | $35.00 | $0.01 | $120.00 | $35.00 |
| 0001-0150 | Geotextile fabric (303SD20-0032) | SY | 395 | $16.00 | $3.80 | $11.00 | $2.50 | $14.00 | $19.00 |
| 0001-0160 | Temp. silt fence type A (303SD20-0034) | LF | 388 | $4.50 | $12.00 | $7.45 | $5.00 | $10.00 | $15.00 |
| 0001-0170 | Turbidity curtain, pervious TY. I (303SD20-0037) | LF | 135 | $34.00 | $40.00 | $43.00 | $10.00 | $30.00 | $200.00 |
| 0001-0180 | NS excavation temp.dive.channel excavation (303SX20-0003) | CY | 702 | $17.00 | $58.00 | $55.00 | $70.00 | $84.00 | $150.00 |
| 0001-0190 | NS borrow excavation CBR 15 (303SX20-0006) | CY | 292 | $17.00 | $48.00 | $110.00 | $30.00 | $112.00 | $165.00 |
| 0001-0200 | Geotextile drainage fabric biaxial geosynthetic reinforcement geogrid (303SX20-0019) | SY | 425 | $12.00 | $3.00 | $9.00 | $5.00 | $50.00 | $45.00 |
| 0001-0210 | Aggr. matl. no. 25 or 26 (305SD20-0011) | TON | 674 | $59.00 | $59.00 | $94.00 | $45.00 | $45.00 | $200.00 |
| 0001-0220 | Machining shoulders (305SP20-0005) | LF | 325 | $7.00 | $8.00 | $24.00 | $6.00 | $11.00 | $10.00 |
| 0001-0230 | Manual shoulders restoration (305SP20-0006) | LF | 25 | $9.00 | $10.00 | $39.00 | $7.00 | $16.00 | $250.00 |
| 0001-0240 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 544 | $80.00 | $68.00 | $73.00 | $45.00 | $70.00 | $200.00 |
| 0001-0250 | Pipe underdrain 6" const. (401SD20-0005) | LF | 36 | $27.00 | $40.00 | $29.00 | $30.00 | $100.00 | $425.00 |
| 0001-0260 | Cofferdam (401SD20-0007) | EACH | 2 | $53,000 | $64,000 | $163,000 | $204,500 | $325,000 | $295,000 |
| 0001-0270 | NS temp support of excavation temporary sheet pile (402SX20-0001) | SF | 1,532 | $61.00 | $90.00 | $230.00 | $100.00 | $130.00 | $85.00 |
| 0001-0280 | Railing texas T-6 const. (410SD20-0004) | LF | 50 | $320.00 | $300.00 | $585.00 | $200.00 | $400.00 | $450.00 |
| 0001-0290 | Erosion CTRL. stone CL. A1, EC-1 (414SD20-0001) | TON | 210 | $54.00 | $150.00 | $117.00 | $70.00 | $200.00 | $350.00 |
| 0001-0300 | Dry riprap CL.I 26" (414SD20-0012) | TON | 130 | $54.00 | $150.00 | $116.00 | $70.00 | $210.00 | $475.00 |
| 0001-0310 | Remove EX. guardrail terminal (505SD20-0009) | EACH | 4 | $2,360.00 | $1,500.00 | $1,600.00 | $1,500.00 | $1,800.00 | $3,500.00 |
| 0001-0320 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 4 | $6,440.00 | $5,400.00 | $3,950.00 | $4,000.00 | $4,800.00 | $9,500.00 |
| 0001-0330 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 4 | $2,630.00 | $1,900.00 | $1,700.00 | $2,000.00 | $2,400.00 | $3,500.00 |
| 0001-0340 | Guardrail GR-2A (505SD20-0033) | LF | 112.50 | $140.00 | $160.00 | $88.00 | $100.00 | $110.00 | $150.00 |
| 0001-0350 | Remove existing guardrail (505SD20-0073) | LF | 325 | $11.00 | $12.00 | $8.00 | $8.00 | $14.00 | $27.00 |
| 0001-0360 | NS guardrail NS GR-MGS2 end terminal site preparation, 4’ moderate (505SX20-0058) | EACH | 4 | $2,450.00 | $1,400.00 | $1,600.00 | $1,750.00 | $2,500.00 | $3,500.00 |
| 0001-0370 | Traffic barrier service MB-11A (512SD20-0003) | LF | 40 | $155.00 | $100.00 | $94.00 | $50.00 | $200.00 | $750.00 |
| 0001-0380 | Type 3 barricade 4' (512SD20-0012) | EACH | 4 | $395.00 | $150.00 | $550.00 | $600.00 | $800.00 | $1,200.00 |
| 0001-0390 | Type 3 barricade 8' (512SD20-0013) | EACH | 4 | $480.00 | $150.00 | $650.00 | $400.00 | $1,200.00 | $1,450.00 |
| 0001-0400 | Temporary sign (512SD20-0014) | SF | 479 | $35.00 | $45.00 | $57.00 | $50.00 | $120.00 | $80.00 |
| 0001-0410 | Truck mounted attenuator (512SD20-0023) | HR | 40 | $180.00 | $180.00 | $74.00 | $0.01 | $85.00 | $35.00 |
| 0001-0420 | Port.changeable mess. sign (512SD20-0025) | HR | 1,008 | $5.00 | $25.00 | $9.50 | $10.00 | $15.00 | $25.00 |
| 0001-0430 | Flagger service (512SD20-0027) | HR | 80 | $105.00 | $60.00 | $60.00 | $0.01 | $100.00 | $150.00 |
| 0001-0440 | Warning light TY. B (512SD20-0029) | DAY | 3,800 | $2.00 | $10.00 | $1.40 | $1.00 | $1.25 | $10.00 |
| 0001-0450 | Mobilization (513SD20-0001) | LS | 1 | $33,600 | $190,000 | $155,000 | $190,000 | $175,000 | $250,000 |
| 0001-0460 | Field office TY.II (514SD20-0002) | MO | 8 | $3,070.00 | $9,500.00 | $3,200.00 | $2,500.00 | $4,500.00 | $4,200.00 |
| 0001-0470 | Construction surveying constr. (517SD20-0001) | LS | 1 | $43,800 | $25,000 | $17,200 | $122,022 | $60,000 | $32,500 |
| 0001-0480 | Topsoil class B 2" (602SD20-0003) | ACRE | 0.09 | $60,300 | $20,000 | $74,500 | $5,000.00 | $20,000 | $20,000 |
| 0001-0490 | Temporary seed (603SD20-0002) | LB | 9 | $31.00 | $25.00 | $86.00 | $5.00 | $100.00 | $120.00 |
| 0001-0500 | Regular seed (603SD20-0003) | LB | 16 | $24.00 | $25.00 | $74.00 | $5.00 | $125.00 | $125.00 |
| 0001-0510 | Overseeding (603SD20-0004) | LB | 13 | $26.00 | $50.00 | $73.00 | $5.00 | $150.00 | $100.00 |
| 0001-0520 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 424 | $5.00 | $2.00 | $9.60 | $1.00 | $12.00 | $30.00 |
| 0001-0530 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 557 | $3.50 | $2.00 | $9.90 | $1.50 | $20.00 | $35.00 |
| 0001-0540 | Fertilizer nitrogen - N (603SD20-0014) | LB | 9 | $20.00 | $25.00 | $80.00 | $3.00 | $100.00 | $1,000.00 |
| 0001-0550 | Fertilizer phosphorous - P (603SD20-0015) | LB | 6 | $22.00 | $25.00 | $80.00 | $3.00 | $150.00 | $850.00 |
| 0001-0560 | Fertilizer potassium - K (603SD20-0016) | LB | 6 | $22.00 | $25.00 | $80.00 | $3.00 | $150.00 | $875.00 |
| 0001-0570 | Lime (603SD20-0017) | TON | 0.49 | $340.00 | $90.00 | $1,300.00 | $300.00 | $1,000.00 | $3,500.00 |
| 0001-0580 | NS seed mixture wetland mixture (605SX20-0017) | LB | 5 | $90.00 | $150.00 | $452.00 | $40.00 | $180.00 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of February 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way