Bridge deck grooving const., VDOT 404SD20-0009
Low bidders on VDOT contracts carried a median of $24.00 per SY for this item, over the 24 months to 28 OCT 2026, across 8 low bids. Half of all 40 bids fell between $15.00 and $48.20.
- Owner
- Virginia DOT
- Item
- 404SD20-0009
- Unit
- SY
- Data through
- 28 OCT 2026
VDOT has bid this work under more than one code: 60490 on lettings from 26 FEB 2002 to 17 NOV 2021 (575 bids); 404SD20-0009 on lettings from 22 OCT 2025 to 22 JUL 2026 (40 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 12 | 12 | $8.00 | 36 | $9.00 |
| 2003 | 5 | 5 | $8.00 | 15 | $14.00 |
| 2004 | 8 | 8 | $5.00 | 22 | $6.67 |
| 2005 | 9 | 9 | $9.00 | 23 | $10.00 |
| 2006 | 12 | 12 | $11.00 | 35 | $12.00 |
| 2007 | 10 | 10 | $10.00 | 28 | $8.88 |
| 2008 | 4 | 4 | $20.88 | 12 | $12.00 |
| 2009 | 8 | 8 | $7.83 | 24 | $8.00 |
| 2010 | 6 | 6 | $6.88 | 18 | $6.88 |
| 2011 | 9 | 9 | $9.19 | 27 | $9.19 |
| 2012 | 8 | 8 | $16.00 | 24 | $15.50 |
| 2013 | 12 | 12 | $6.05 | 35 | $9.50 |
| 2014 | 16 | 16 | $12.36 | 41 | $13.00 |
| 2015 | 16 | 16 | $15.50 | 42 | $11.82 |
| 2016 | 20 | 19 | $15.75 | 54 | $17.00 |
| 2017 | 6 | 6 | $18.75 | 18 | $19.50 |
| 2018 | 10 | 10 | $10.12 | 30 | $13.50 |
| 2019 | 14 | 14 | $13.20 | 39 | $15.00 |
| 2020 | 7 | 7 | $15.00 | 21 | $15.00 |
| 2021 | 10 | 10 | $17.75 | 30 | $17.75 |
| 2025 | 2 | 2 | $7.88 | 7 | $11.00 |
| 2026 | 6 | 6 | $40.10 | 33 | $25.79 |
Bid prices as published, not adjusted for inflation.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Elk Knob, Inc. | 31 | 15 (48%) |
| Ken Construction Co., Inc. | 31 | 13 (42%) |
| Abernathy Construction Corporation | 26 | 13 (50%) |
| Corman Construction, Inc. | 17 | 12 (71%) |
| Crossroads Bridge Inc | 22 | 9 (41%) |
| Estes Bros. Const., Inc. | 17 | 9 (53%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | C0000121138B52 | Bristol | 125 | $55.20 | $61.57 | 5 | Elk Knob, Inc. | VDOT |
| 24 JUN 2026 | C0000112964B03 | Staunton | 118 | $74.00 | $65.00 | 5 | Hammond-Mitchell, Inc. | VDOT |
| 22 APR 2026 | C0000124564B64 | Culpeper | 518 | $15.00 | $17.09 | 6 | WG Construction Co., Inc. | VDOT |
| 25 MAR 2026 | C0000121531B68 | Hampton Roads | 522 | $72.00 | $20.00 | 7 | Crofton Construction Services, | VDOT |
| 04 FEB 2026 | C0000127189N01 | Hampton Roads | 1,750 | $25.00 | $22.50 | 2 | M. D. Miller Co., Inc. | VDOT |
| 04 FEB 2026 | C0000113851B01 | Fredericksburg | 416 | $23.00 | $19.62 | 8 | WG Construction Co., Inc. | VDOT |
| 19 NOV 2025 | C0000116160B01 | Bristol | 1,176 | $6.75 | $6.75 | 3 | Caton Construction Group, Inc. | VDOT |
| 22 OCT 2025 | C0000118396B57 | Northern Virginia | 1,046 | $9.00 | $15.50 | 4 | Martins Construction Corp. | VDOT |
| 17 NOV 2021 | CM119LMA115175 | Bristol | 446 | $17.50 | $16.50 | 3 | Patrick Construction, Inc. | VDOT |
| 27 OCT 2021 | C0000112877B10 | Salem | 194 | $34.50 | $38.00 | 3 | A. R. Coffey and Sons, Inc. | VDOT |
| 27 OCT 2021 | C0000119068B29 | Hampton Roads | 1,475 | $4.09 | $4.09 | 3 | Curtis Contracting, Inc. | VDOT |
| 25 AUG 2021 | C0000110620B36 | Salem | 583 | $8.00 | $8.65 | 3 | Archer Western Construction, LLC | VDOT |
| 25 AUG 2021 | C0000111282B24 | Lynchburg | 410 | $18.00 | $18.00 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 28 JUL 2021 | C0000110001B54 | Culpeper | 182 | $56.40 | $55.00 | 3 | Clearwater Construction, Inc. | VDOT |
| 24 MAR 2021 | C0000105490B43 | Richmond | 239 | $28.00 | $23.50 | 3 | Clearwater Construction, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.