VDOT contract CM226PMT126925 bid tabulation
2026 plant mix - secondary. Let by Virginia DOT on December 17, 2025, Carroll, Salem. 1 bid received; low bid $2,225,461 by Adams Construction Company.
- Owner
- Virginia DOT
- Letting
- 17 DEC 2025
- Pay items
- 14
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Adams Construction Company | $2,225,461 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Adams Construction Company |
|---|---|---|---|---|
| 0001-0010 | Agr. base mat. TY.I or II no. 21A or 21B (305SP20-0003) | TON | 2,196.27 | $95.00 |
| 0001-0020 | Tack coat (310SD20-0001) | GAL | 14,414 | $3.50 |
| 0001-0030 | Pavement shoulder wedge prep. const (315SP20-0006) | LF | 97,839 | $0.10 |
| 0001-0040 | Asph. conc. BMD P+VO SM- 9.5A (315SP20-0048) | TON | 8,914.07 | $130.00 |
| 0001-0050 | Asph. conc. BMD P+VO SM- 9.5D (315SP20-0049) | TON | 3,626.99 | $125.00 |
| 0001-0060 | Flagger service (512SD20-0027) | HR | 1,085 | $40.00 |
| 0001-0070 | Eradicate nonlinear PVMT MRKG (512SD20-0043) | SF | 800 | $10.00 |
| 0001-0080 | Temp. PVMT MRKG TY. A, 4" (512SD20-0046) | LF | 129,200 | $0.20 |
| 0001-0090 | NS maintenance of traffic plant mix (512SP20-0002) | LS | 1 | $140,000 |
| 0001-0100 | Flex. pave. tie-in planing 0"-2" (515SD20-0011) | SY | 5,976.96 | $10.00 |
| 0001-0110 | Flexible pave.planing 0"-2" (515SD20-0013) | SY | 1,853.86 | $6.50 |
| 0001-0120 | Type A PVMT line MRKG 4" (704SD20-0001) | LF | 129,300 | $0.40 |
| 0001-0130 | Type B class II PVMT line MRKG 6" (704SD20-0012) | LF | 160 | $22.50 |
| 0002-0140 | NS select material alternate shoulder material (305SX20-0006) | TON | 1 | $0.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of December 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.