VDOT contract CM326PMB127076 bid tabulation
Sgr*-2026 plant mix - primary/secondary. Let by Virginia DOT on January 14, 2026, Appomattox, Campbell, Lynchburg, Lynchburg. 2 bids received; low bid $6,912,042 by Superior Paving Corporation.
- Owner
- Virginia DOT
- Letting
- 14 JAN 2026
- Pay items
- 32
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Superior Paving Corporation | $6,912,042 | Low |
| 2 | Adams Construction Company | $7,199,530 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Superior Paving Corporation | 2. Adams Construction Company |
|---|---|---|---|---|---|
| 0001-0010 | Aggr. matl. no. 25 or 26 (308SD20-0008) | TON | 4,770.29 | $55.00 | $63.32 |
| 0001-0020 | Tack coat (310SD20-0001) | GAL | 40,501 | $2.70 | $3.66 |
| 0001-0030 | Rumble strip cylindrical asphalt (315SD20-0015) | LF | 33,565 | $0.30 | $0.29 |
| 0001-0040 | Liquid asphalt coating (rumble strip) (315SD20-0019) | SY | 3,302 | $1.50 | $1.51 |
| 0001-0050 | Asph. conc TY. SM-9.5E maint (315SD20-0031) | TON | 5,048.03 | $118.85 | $126.31 |
| 0001-0060 | Pavement shoulder wedge prep. const (315SP20-0006) | LF | 26,825 | $0.10 | $0.14 |
| 0001-0070 | Asph. conc. BMD P+VO SM- 9.5D (315SP20-0049) | TON | 9,460.38 | $110.25 | $121.23 |
| 0001-0080 | Asph. conc. BMD P+VO SM- 12.5D (315SP20-0051) | TON | 27,424.95 | $108.00 | $113.50 |
| 0001-0090 | NS pavement liquid asphalt coating (pavement marker grooves) (316SX20-0004) | SY | 428 | $12.00 | $11.40 |
| 0001-0100 | Flagger service (512SD20-0027) | HR | 1,100 | $35.00 | $38.32 |
| 0001-0110 | Temp. PVMT MRKG TY. A, 4" (512SD20-0046) | LF | 367,355 | $0.13 | $0.15 |
| 0001-0120 | Temp. PVMT MRKG TY. A, 24" (512SD20-0050) | LF | 2,152 | $2.50 | $2.67 |
| 0001-0130 | Temp. PVMT. symb. MRKG thru arrow TY. A (512SD20-0051) | EACH | 8 | $40.00 | $39.92 |
| 0001-0140 | Temp. PVMT. symb. MRKG SNGL turn arrow TY. A (512SD20-0052) | EACH | 112 | $40.00 | $39.92 |
| 0001-0150 | NS maintenance of traffic plant mix (512SP20-0002) | LS | 1 | $199,500 | $138,121 |
| 0001-0160 | NS temp. PVMT MRKG dble turn arr. thru/LT, type A (512SX20-0006) | EACH | 5 | $65.00 | $68.43 |
| 0001-0170 | NS temp. PVMT MRKG dble turn arr. thru/RT, type A (512SX20-0006) | EACH | 3 | $65.00 | $68.43 |
| 0001-0180 | Flex. pave. tie-in planing 0"-2" (515SD20-0011) | SY | 844.80 | $10.60 | $9.38 |
| 0001-0190 | Flexible pave.planing 0"-2" (515SD20-0013) | SY | 380,640.93 | $2.45 | $2.30 |
| 0001-0200 | Type A PVMT line MRKG 4" (704SD20-0001) | LF | 7,484 | $0.80 | $0.83 |
| 0001-0210 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 112,539 | $1.00 | $1.01 |
| 0001-0220 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 213,905 | $1.10 | $1.14 |
| 0001-0230 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 2,231 | $20.10 | $21.34 |
| 0001-0240 | Type B class VI PVMT line MRKG 6" (704SD20-0027) | LF | 34,452 | $5.00 | $5.31 |
| 0001-0250 | Type B class VI PVMT line MRKG 12" (704SD20-0029) | LF | 2,006 | $9.00 | $9.55 |
| 0001-0260 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 1,258 | $33.15 | $35.19 |
| 0001-0270 | PVMT symb MRKG thru arrow TY B, CL II (704SD20-0045) | EACH | 4 | $400.00 | $411.87 |
| 0001-0280 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 82 | $400.00 | $359.71 |
| 0001-0290 | DBL turn arr.thru/LT or RT TY B, CL II (704SD20-0051) | EACH | 10 | $650.00 | $690.15 |
| 0001-0300 | PVMT MSG. mark. “school” TY A, 8’ (704SD20-0109) | EACH | 4 | $150.00 | $154.36 |
| 0001-0310 | PVMT MSG. mark. “school” TY B, CL II, 8’ (704SD20-0111) | EACH | 2 | $1,200.00 | $1,184.32 |
| 0002-0320 | NS select material alternate shoulder material (305SX20-0006) | TON | 1 | $60.00 | $63.32 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of January 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.