WSDOT contract XE3749 bid tabulation
Sr 240 Beloit Road To Hagen Rd Pavement Repairs. Let by Washington State DOT on July 1, 2026, Benton, SCR region. 3 bids received; low bid $400,000 by Central Washington Asphalt, Inc., -18% against the engineer's estimate of $485,121.
- Owner
- Washington State DOT
- Letting
- 01 JUL 2026
- Pay items
- 17
- Data through
- 07 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Central Washington Asphalt, Inc. | $400,000 | Low | -18% |
| 2 | Granite Construction Company | $581,784 | +45% | +20% |
| 3 | CPM Development Corporation | $640,000 | +60% | +32% |
Engineer's estimate: $485,121.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Central Washington Asphalt, Inc. | 2. Granite Construction Company | 3. CPM Development Corporation |
|---|---|---|---|---|---|---|---|
| 1 | Mobilization | LS | 1 | $44,102 | $22,000 | $58,000 | $75,000 |
| 2 | Pavement repair excavation including haul | SY | 884 | $35.00 | $50.00 | $115.00 | $130.00 |
| 3 | Crack sealing bit PVMT - CM | CM | 20 | $10,000 | $6,700.00 | $7,500.00 | $7,500.00 |
| 4 | Hot mix asphalt for pavement repair class 3/8 inch PG 64H-28 | TON | 91 | $475.00 | $800.00 | $1,050.00 | $1,200.00 |
| 5 | Job mix compliance price adjustment | CALC | 1 | $1,297.00 | $1,297.00 | $1,297.00 | $1,297.00 |
| 6 | Compaction price adjustment | CALC | 1 | $2,161.00 | $2,161.00 | $2,161.00 | $2,161.00 |
| 7 | Asphalt cost price adjustment | CALC | 1 | $2.00 | $2.00 | $2.00 | $2.00 |
| 8 | Portable changeable message sign | HR | 1,200 | $15.00 | $14.00 | $6.00 | $3.15 |
| 9 | Project temporary traffic control | LS | 1 | $127,540 | $88,234 | $147,000 | $165,000 |
| 10 | Work zone safety contingency | EST | 1 | $6,377.00 | $6,377.00 | $6,377.00 | $6,377.00 |
| 11 | Construction signs class A | SF | 212 | $40.00 | $36.00 | $45.00 | $40.00 |
| 12 | Project partnering | CALC | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 13 | Roadside cleanup | EST | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 14 | Reimbursement for third party damage | EST | 1 | $5.00 | $5.00 | $5.00 | $5.00 |
| 15 | Minor change | CALC | 1 | -$4.00 | -$4.00 | -$4.00 | -$4.00 |
| 16 | Aggregate compliance price adjustment | CALC | 1 | -$4.00 | -$4.00 | -$4.00 | -$4.00 |
| 17 | Spill prevention, control, and countermeasures plan | LS | 1 | $1,000.00 | $2,500.00 | $1,000.00 | $1,786.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WSDOT's tabulation for this contract. WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
Every contract let that day: WSDOT letting of July 1, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.