WSDOT letting results, January 20, 2022

3 contracts let by Washington State DOT on January 20, 2022, $6,644,751 in low bids, a median of 3 bidders per contract. On the 3 with an engineer's estimate, the low bid came in under it 2 times; median low bid -1.0% against the estimate.

Owner
Washington State DOT
Contracts
3
Low bids, total
$6,644,751
Data through
07 OCT 2026

Contracts let that day

ContractProjectRegionBidsLow bidderLow bidSecond bidGapAgainst estimateSource
009754Sr 546 pepin creek and duffner ditch fish passageNWR region3Granite Construction Company$3,343,054$3,730,309+12%+45%WSDOT
009759Us 2 davenport to reardan pavingER region3CPM Development Corporation$2,907,207$2,989,203+3.0%-1.0%WSDOT
009761Sr160 southworth ferry terminal painting preservationRegion 95Mericka Group LLC$394,490$416,504+6.0%-15%WSDOT
WSDOT contracts let on January 20, 2022, largest low bid first

Gap is the second bid over the low bid. Where a contract shows fewer bids than WSDOT received, the others did not match their published totals and are left out.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy