WisDOT contract 20250114002 bid tabulation

1370-00-73. Let by Wisconsin DOT on January 14, 2025, Jefferson. 6 bids received; low bid $15,803,890 by Hoffman Construction Company.

Owner
Wisconsin DOT
Letting
14 JAN 2025
Pay items
221
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Hoffman Construction Company$15,803,890Low
2Mashuda Contractors, Inc.$16,146,874+2.0%
3Michels Road & Stone, Inc.$17,074,259+8.0%
4James Peterson Sons, Inc.$17,942,329+14%
5Musson Bros., Inc.$17,949,960+14%
6Edgerton Contractors, Inc.$19,512,564+23%
WisDOT contract 20250114002: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Hoffman Construction Company2. Mashuda Contractors, Inc.3. Michels Road & Stone, Inc.4. James Peterson Sons, Inc.5. Musson Bros., Inc.6. Edgerton Contractors, Inc.
1Clearing (201.0105)STA3$767.60$767.60$767.60$767.60$767.60$767.60
2Grubbing (201.0205)STA3$517.14$517.14$517.14$517.14$517.14$517.14
3Removing small pipe culverts (203.0100)EACH4$1,500.00$600.00$578.00$750.00$891.80$580.00
4Removing structure over waterway minimal debris (structure) 01. B-28- 12 (203.0260)EACH1$270,000$260,000$260,000$260,000$260,000$260,000
5Removing concrete pavement (204.0100)SY125,179$2.00$0.70$0.60$1.04$5.82$2.00
6Removing asphaltic surface butt joints (204.0115)SY57$18.00$18.00$18.00$18.00$18.00$18.00
7Removing asphaltic surface milling (204.0120)SY10,331$2.50$2.50$2.50$2.50$2.50$2.50
8Removing curb & gutter (204.0150)LF4,012$3.00$2.00$3.00$2.00$3.70$3.00
9Removing concrete sidewalk (204.0155)SY117$10.00$4.00$6.00$5.00$2.29$14.00
10Removing delineators and markers (204.0180)EACH11$50.00$50.00$25.00$50.00$50.00$50.00
11Removing inlets (204.0220)EACH7$250.00$400.00$535.00$500.00$874.52$539.00
12Removing storm sewer (size) 01. 12-inch (204.0245)LF119$15.00$15.00$26.00$28.00$24.69$26.00
13Removing storm sewer (size) 02. 24-inch (204.0245)LF26$15.00$25.00$28.00$30.00$48.95$29.00
14Excavation common (205.0100)CY244,029$0.01$6.69$9.10$10.33$12.20$13.00
15Excavation for structures bridges (structure) 01. B-28-12 (206.1001)EACH1$3,000.00$3,000.00$3,000.00$3,000.00$307,441$3,000.00
16Backfill structure type A (210.1500)TON120$40.00$30.00$30.00$30.00$37.10$42.00
17Prepare foundation for asphaltic paving (project) 01. 1370-00-73 (211.0101)EACH1$1.00$1,450.00$1,450.00$1,450.00$1,450.00$1,450.00
18Finishing roadway (project) 01. 1370-00-73 (213.0100)EACH1$500.00$875.00$6,500.00$3,500.00$500.00$2,500.00
19Finishing roadway (project) 02. 1370-00-76 (213.0100)EACH1$500.00$400.00$6,500.00$3,500.00$500.00$2,500.00
20Base aggregate dense 3/4-inch (305.0110)TON27,952$0.01$18.62$16.50$19.79$18.93$26.00
21Base aggregate dense 1 1/4-inch (305.0120)TON209,310$0.01$12.74$11.00$12.22$13.39$11.00
22Base aggregate open-graded (310.0110)TON253$30.00$45.00$26.00$22.00$39.85$27.00
23Select crushed material (312.0110)TON176,223$0.01$15.00$12.50$17.24$11.32$18.00
24QMP base aggregate dense 1 1/4- inch compaction (371.2000.S)EACH132$700.00$760.00$600.00$612.90$718.22$592.00
25Coloring concrete wisdot red (405.0100)CY180$97.95$97.95$130.00$130.00$130.00$130.00
26Concrete pavement 9-inch (415.0090)SY7,968$71.23$71.23$79.79$62.00$62.00$62.00
27Concrete pavement 12-inch (415.0120)SY171$111.15$111.15$100.58$84.00$84.00$84.00
28Concrete pavement approach slab (415.0410)SY293$160.84$160.84$255.33$240.00$240.00$240.00
29Concrete truck apron 12-inch (415.2010)SY540$108.93$108.93$84.00$84.00$84.00$84.00
30Concrete pavement joint filling (415.4100)SY9,293$1.00$1.00$4.15$1.00$1.00$1.00
31HMA cold weather paving (450.4000)TON2,760$0.75$0.75$0.75$0.75$0.75$0.75
32Tack coat (455.0605)GAL9,654$2.25$2.25$2.25$2.25$2.25$2.25
33HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH2$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00
34HMA percent within limits (PWL) test strip density (460.0110.S)EACH2$7,250.00$7,250.00$7,250.00$7,250.00$7,250.00$7,250.00
35Incentive density PWL HMA pavement (460.2005)DOL35,330$1.00$1.00$1.00$1.00$1.00$1.00
36Incentive density HMA pavement longitudinal joints (460.2007)DOL6,790$1.00$1.00$1.00$1.00$1.00$1.00
37Incentive air voids HMA pavement (460.2010)DOL58,370$1.00$1.00$1.00$1.00$1.00$1.00
38HMA pavement 3 MT 58-28 S (460.6223)TON34,360$57.10$57.10$57.10$57.10$57.10$57.10
39HMA pavement 4 MT 58-28 S (460.6224)TON24,770$66.50$66.50$66.50$66.50$66.50$66.50
40HMA pavement 4 MT 58-28 H (460.6424)TON1,420$79.50$79.50$79.50$79.50$79.50$79.50
41Asphaltic surface driveways and field entrances (465.0120)TON67$78.00$78.00$78.00$78.00$78.00$78.00
42Asphaltic flumes (465.0315)SY109$49.00$49.00$49.00$49.00$49.00$49.00
43Asphaltic rumble strips, shoulder divided roadway (465.0510)LF12,236$0.32$0.32$0.23$0.46$0.32$0.32
44Asphaltic rumble strips, shoulder (465.0520)LF58,408$0.21$0.21$0.23$0.19$0.21$0.21
45Asphaltic rumble strips, centerline (465.0560)LF28,387$0.32$0.32$0.23$0.24$0.32$0.32
46Concrete masonry bridges (502.0100)CY496$1,000.00$980.00$980.00$980.00$980.00$980.00
47Expansion device (502.3101)LF115$200.00$235.00$235.00$235.00$235.00$235.00
48Protective surface treatment (502.3200)SY1,288$3.25$5.00$5.00$5.00$5.00$5.00
49Pigmented surface sealer (502.3210)SY293$4.00$8.00$8.00$8.00$8.00$8.00
50Adhesive anchors no. 5 bar (502.4205)EACH110$30.00$18.00$18.00$18.00$18.00$18.00
51Bar steel reinforcement HS coated structures (505.0600)LB103,960$1.45$1.20$1.20$1.20$1.20$1.20
52Steel diaphragms (structure) 01. B- 28-12 (506.4000)EACH36$1,200.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00
53Concrete surface repair (509.1500)SF72$155.00$150.00$150.00$150.00$150.00$150.00
54Rubberized membrane waterproofing (516.0500)SY32$20.00$35.00$35.00$35.00$35.00$35.00
55Apron endwalls for culvert pipe 12- inch (520.1012)EACH2$420.00$383.00$1,068.00$286.55$562.58$1,073.00
56Culvert pipe class III-A 12-inch (520.3312)LF27$42.00$50.00$70.00$54.10$77.41$71.00
57Concrete collars for pipe (520.8000)EACH2$1,100.00$900.00$892.00$1,126.25$951.54$895.00
58Apron endwalls for culvert pipe steel 12-inch (521.1012)EACH1$450.00$383.00$2,124.00$268.26$330.71$2,165.00
59Apron endwalls for culvert pipe steel 18-inch (521.1018)EACH8$480.00$398.00$246.00$379.07$360.11$247.00
60Apron endwalls for culvert pipe steel 24-inch (521.1024)EACH5$550.00$462.00$336.00$504.10$500.92$338.00
61Culvert pipe corrugated steel 12- inch (521.3112)LF8$50.00$65.00$83.00$120.10$83.22$83.00
62Culvert pipe corrugated steel 18- inch (521.3118)LF192$57.00$67.75$55.00$74.94$102.86$56.00
63Culvert pipe corrugated steel 24- inch (521.3124)LF37$65.00$163.00$65.00$136.80$111.79$66.00
64Culvert pipe corrugated steel aluminum coated 18-inch (521.6118)LF298$102.00$122.50$59.00$165.56$149.07$59.00
65Culvert pipe reinforced concrete class III 24-inch (522.0124)LF16$89.00$110.50$160.00$152.64$138.81$161.00
66Culvert pipe reinforced concrete class III 36-inch (522.0136)LF88$165.00$162.00$178.00$189.13$202.86$179.00
67Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH6$1,520.00$822.00$1,126.00$1,135.87$1,248.34$1,130.00
68Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH2$1,810.00$1,078.00$1,578.00$1,468.61$1,601.78$1,584.00
69Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036)EACH2$2,640.00$1,782.00$2,382.00$2,210.62$2,413.64$2,391.00
70Culvert pipe reinforced concrete horizontal elliptical class HE-III 43X68-inch (522.2343)LF38$380.00$375.25$392.00$342.21$83.73$394.00
71Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 43X68-inch (522.2643)EACH1$4,170.00$3,054.00$3,853.00$4,182.30$769.13$3,868.00
72Culvert pipe corrugated polyethylene 12-inch (530.0112)LF50$42.00$56.00$40.00$54.43$71.77$41.00
73Concrete curb & gutter 18-inch type A (601.0405)LF245$19.44$19.44$26.00$26.00$26.00$26.00
74Concrete curb & gutter 30-inch type A (601.0409)LF2,885$19.87$19.87$28.00$28.00$28.00$28.00
75Concrete curb & gutter 6-inch sloped 36-inch type A (601.0555)LF822$24.81$24.81$28.00$28.00$28.00$28.00
76Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF4,641$22.52$22.52$28.00$28.00$28.00$28.00
77Concrete curb & gutter 4-inch sloped 36-inch type R (601.0580)LF609$31.11$31.11$27.00$27.00$27.00$27.00
78Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588)LF158$28.22$28.22$27.00$27.00$27.00$27.00
79Concrete sidewalk 4-inch (602.0405)SF14,526$4.42$4.42$7.50$7.50$7.50$7.50
80Curb ramp detectable warning field yellow (602.0505)SF148$52.75$52.75$45.00$45.00$45.00$45.00
81Concrete surface drains (602.3010)CY32$749.36$749.36$1,100.00$1,100.00$1,100.00$1,100.00
82Concrete rumble strips, shoulder (602.3220)LF1,920$1.26$1.26$0.95$3.81$1.26$1.26
83Reseal crushed aggregate slope paving (604.9015.S)SY617$13.00$13.00$16.00$20.00$13.00$13.00
84Riprap medium (606.0200)CY14$140.00$150.00$74.00$105.00$232.46$75.00
85Riprap heavy (606.0300)CY216$155.00$115.00$115.00$115.00$115.00$115.00
86Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF616$56.00$76.75$80.00$98.06$101.27$80.00
87Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF30$69.00$85.25$83.00$101.22$115.24$83.00
88Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF81$89.00$112.75$99.00$123.31$131.01$100.00
89Reconstructing manholes (611.0420)EACH1$2,000.00$2,500.00$1,970.00$1,330.29$1,271.37$1,977.00
90Manhole covers type J (611.0530)EACH2$780.00$1,190.00$1,027.00$1,326.15$922.10$1,031.00
91Inlet covers type A (611.0600)EACH2$1,050.00$860.00$1,329.00$1,411.20$1,167.01$1,333.00
92Inlet covers type H (611.0624)EACH19$1,080.00$880.00$1,433.00$1,436.40$1,302.09$1,438.00
93Inlet covers type T (611.0652)EACH2$1,400.00$1,150.00$1,801.00$1,789.20$1,732.42$1,807.00
94Inlet covers type V (611.0654)EACH1$1,000.00$820.00$1,392.00$1,359.40$1,236.80$1,397.00
95Manholes 4-FT diameter (611.2004)EACH2$2,850.00$3,297.00$3,086.00$2,894.53$2,975.56$3,099.00
96Inlets 4-FT diameter (611.3004)EACH4$2,530.00$2,850.00$2,658.00$2,525.02$2,868.97$2,669.00
97Inlets 2X2-FT (611.3220)EACH3$2,050.00$3,414.00$2,618.00$2,426.42$2,309.82$2,636.00
98Inlets 2X2.5-FT (611.3225)EACH1$1,630.00$2,188.00$1,685.00$1,632.13$2,058.34$1,692.00
99Inlets 2X3-FT (611.3230)EACH16$2,080.00$2,494.00$2,006.00$1,818.99$1,949.94$2,014.00
100Pipe underdrain 6-inch (612.0106)LF1,861$12.00$12.05$6.00$8.00$4.86$6.00
101Pipe underdrain wrapped 6-inch (612.0406)LF200$5.00$6.00$6.00$6.00$4.49$5.00
102Anchor assemblies for steel plate beam guard (614.0150)EACH4$250.00$300.00$300.00$300.00$300.00$300.00
103Steel plate beam guard class A (614.0305)LF150$29.00$29.00$25.25$29.00$29.00$29.00
104Steel plate beam guard energy absorbing terminal (614.0370)EACH1$4,000.00$4,000.00$4,000.00$4,000.00$4,000.00$4,000.00
105Salvaged rail (614.0920)LF2,003$2.00$2.00$2.35$2.00$2.00$2.00
106MGS guardrail 3 (614.2300)LF1,413$29.00$29.00$25.50$29.00$29.00$29.00
107MGS thrie beam transition (614.2500)LF276$90.00$90.00$84.00$90.00$90.00$90.00
108MGS guardrail terminal eat (614.2610)EACH10$4,000.00$4,000.00$3,475.00$4,000.00$4,000.00$4,000.00
109MGS guardrail terminal type 2 (614.2620)EACH3$3,800.00$3,800.00$2,600.00$3,800.00$3,800.00$3,800.00
110Maintenance and repair of haul roads (project) 01. 1370-00-73 (618.0100)EACH1$1.00$1.00$1.00$1,500.00$1,000.00$1.00
111Maintenance and repair of haul roads (project) 02. 1370-00-76 (618.0100)EACH1$1.00$1.00$1.00$1,500.00$1,000.00$1.00
112Mobilization (619.1000)EACH1$7,491,500$573,080$1,180,810$753,045$628,000$1,369,000
113Concrete median sloped nose (620.0300)SF358$12.31$12.31$18.00$18.00$18.00$18.00
114Water (624.0100)MGAL3,350$0.01$30.00$58.00$5.50$0.01$46.00
115Salvaged topsoil (625.0500)SY30,614$5.00$1.20$2.10$1.49$1.86$1.00
116Mulching (627.0200)SY10,240$1.40$1.40$0.40$1.40$1.40$1.40
117Silt fence (628.1504)LF6,662$2.00$2.00$1.90$2.00$2.00$2.00
118Silt fence maintenance (628.1520)LF13,324$0.01$0.01$0.01$0.01$0.01$0.01
119Mobilizations erosion control (628.1905)EACH15$1.00$1.00$100.00$1.00$1.00$1.00
120Mobilizations emergency erosion control (628.1910)EACH8$1.00$1.00$100.00$1.00$1.00$1.00
121Erosion mat class I type A (628.2002)SY14,050$2.10$2.10$1.05$2.10$2.10$2.10
122Erosion mat urban class I type A (628.2006)SY4,625$2.85$2.85$1.60$2.85$2.85$2.85
123Erosion mat class II type B (628.2023)SY1,700$2.85$2.85$1.70$2.85$2.85$2.85
124Inlet protection type A (628.7005)EACH25$1.00$1.00$75.00$1.00$1.00$1.00
125Inlet protection type C (628.7015)EACH25$150.00$150.00$63.00$150.00$150.00$150.00
126Temporary ditch checks (628.7504)LF9$20.00$20.00$18.00$20.00$20.00$20.00
127Culvert pipe checks (628.7555)EACH144$12.00$12.00$18.00$12.00$12.00$12.00
128Rock bags (628.7570)EACH85$12.00$12.00$18.00$12.00$12.00$12.00
129Fertilizer type A (629.0205)CWT72.50$0.01$0.01$82.00$0.01$0.01$0.01
130Seeding mixture no. 20 (630.0120)LB3,135$0.01$0.01$8.95$0.01$0.01$0.01
131Seed water (630.0500)MGAL2,615$0.01$0.01$1.00$0.01$0.01$0.01
132Markers culvert end (633.5200)EACH24$85.00$85.00$60.00$85.00$85.00$85.00
133Posts wood 4X6-inch X 14-FT (634.0614)EACH21$120.00$120.00$85.00$120.00$120.00$120.00
134Posts wood 4X6-inch X 16-FT (634.0616)EACH177$120.00$120.00$90.00$120.00$120.00$120.00
135Posts wood 4X6-inch X 18-FT (634.0618)EACH8$130.00$130.00$100.00$130.00$130.00$130.00
136Posts wood 4X6-inch X 20-FT (634.0620)EACH2$160.00$160.00$125.00$160.00$160.00$160.00
137Posts wood 4X6-inch X 22-FT (634.0622)EACH2$200.00$200.00$150.00$200.00$200.00$200.00
138Posts wood 4X6-inch X 24-FT (634.0624)EACH2$300.00$300.00$175.00$300.00$300.00$300.00
139Posts tubular steel 2X2-inch X 14- FT (634.0814)EACH2$220.00$220.00$200.00$220.00$220.00$220.00
140Posts tubular steel 2X2-inch X 16- FT (634.0816)EACH6$225.00$225.00$210.00$225.00$225.00$225.00
141Signs type II reflective H (637.2210)SF283$26.00$26.00$20.00$26.00$26.00$26.00
142Signs type II reflective F (637.2230)SF43$28.00$28.00$22.00$28.00$28.00$28.00
143Moving signs type II (638.2102)EACH117$60.00$60.00$137.50$60.00$60.00$60.00
144Removing signs type II (638.2602)EACH12$40.00$40.00$30.00$40.00$40.00$40.00
145Removing small sign supports (638.3000)EACH129$30.00$30.00$30.00$30.00$30.00$30.00
146Field office type C (642.5201)EACH1$25,000$12,500$23,500$30,000$22,258$32,732
147Traffic control drums (643.0300)DAY70$5.00$1.00$1.00$1.00$1.00$1.00
148Traffic control barricades type III (643.0420)DAY19,007$0.25$0.25$0.25$0.25$0.25$0.25
149Traffic control warning lights type A (643.0705)DAY27,366$0.05$0.07$0.07$0.07$0.07$0.05
150Traffic control signs (643.0900)DAY171,319$0.10$0.10$0.10$0.10$0.10$0.10
151Traffic control covering signs type I (643.0910)EACH4$150.00$300.00$300.00$300.00$300.00$300.00
152Traffic control covering signs type II (643.0920)EACH19$50.00$50.00$50.00$50.00$50.00$50.00
153Traffic control signs PCMS (643.1050)DAY14$35.00$40.00$40.00$40.00$40.00$35.00
154Traffic control (643.5000)EACH1$60,500$29,000$29,000$29,000$29,000$29,000
155Geotextile type DF schedule A (645.0111)SY760$2.00$5.00$6.00$5.00$3.78$3.00
156Geotextile type HR (645.0120)SY54$5.00$20.00$6.00$18.52$4.62$3.00
157Geogrid type SR (645.0220)SY237,727$1.50$1.00$1.65$0.75$0.63$0.90
158Marking line epoxy 6-inch (646.2020)LF4,392$0.70$0.80$0.70$0.70$0.71$0.70
159Marking line grooved wet ref epoxy 6-inch (646.2040)LF129,566$1.29$1.30$1.29$1.29$1.30$1.29
160Marking line epoxy 10-inch (646.4020)LF558$1.75$1.80$1.75$1.75$1.77$1.75
161Marking line grooved wet ref epoxy 10-inch (646.4040)LF5,636$2.25$2.10$2.25$2.25$2.27$2.25
162Marking stop line epoxy 18-inch (646.6120)LF715$11.00$13.00$11.00$11.00$11.11$11.00
163Marking dotted extension epoxy 18-inch (646.6320)LF157$17.00$11.00$17.00$17.00$17.17$17.00
164Marking diagonal epoxy 12-inch (646.7120)LF1,512$8.00$7.00$8.00$8.00$8.08$8.00
165Marking crosswalk epoxy transverse line 6-inch (646.7420)LF236$12.50$11.00$12.50$12.50$12.62$12.50
166Marking curb epoxy (646.8120)LF187$8.50$7.50$8.50$8.50$8.58$8.50
167Marking island nose epoxy (646.8220)EACH2$275.00$310.00$275.00$275.00$277.75$275.00
168Locating no-passing zones (648.0100)MI6.61$350.00$400.00$350.00$350.00$353.50$350.00
169Construction staking storm sewer (650.4000)EACH26$150.00$150.00$150.00$200.00$150.00$150.00
170Construction staking subgrade (650.4500)LF50,697$0.01$0.01$0.01$0.01$0.01$0.01
171Construction staking base (650.5000)LF50,587$0.01$1.35$1.35$1.50$1.35$1.35
172Construction staking curb gutter and curb & gutter (650.5500)LF5,167$1.80$1.80$1.80$2.00$1.80$1.80
173Construction staking pipe culverts (650.6000)EACH10$350.00$350.00$350.00$200.00$350.00$350.00
174Construction staking structure layout (structure) 01. B-28-12 (650.6501)EACH1$4,000.00$4,000.00$4,000.00$5,000.00$4,000.00$4,000.00
175Construction staking concrete pavement (650.7000)LF3,768$2.25$2.25$2.25$3.00$2.25$2.25
176Construction staking electrical installations (project) 02. 1370-00- 76 (650.8501)EACH1$4,000.00$4,000.00$4,000.00$3,000.00$4,000.00$4,000.00
177Construction staking curb ramps (650.9000)EACH8$300.00$300.00$300.00$300.00$300.00$300.00
178Construction staking sidewalk (project) 02. 1370-00-76 (650.9500)EACH1$3,500.00$3,500.00$3,500.00$2,000.00$3,500.00$3,500.00
179Construction staking supplemental control (project) 01. 1370-00-73 (650.9911)EACH1$5,600.00$5,600.00$5,600.00$50,000$5,600.00$5,600.00
180Construction staking supplemental control (project) 02. 1370-00-76 (650.9911)EACH1$2,000.00$2,000.00$2,000.00$50,000$2,000.00$2,000.00
181Construction staking slope stakes (650.9920)LF50,697$0.01$1.35$1.35$1.50$1.35$1.35
182Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF1,624$10.00$10.00$10.00$10.00$10.00$10.00
183Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF403$12.00$12.00$12.00$12.00$12.00$12.00
184Pull boxes steel 24X42-inch (653.0140)EACH21$850.00$850.00$850.00$850.00$850.00$850.00
185Concrete bases type 5 (654.0105)EACH17$1,100.00$1,100.00$1,100.00$1,100.00$1,100.00$1,100.00
186Concrete control cabinet bases type L30 (654.0230)EACH1$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00
187Electrical wire lighting 12 AWG (655.0610)LF2,397$1.00$1.00$1.00$1.00$1.00$1.00
188Electrical wire lighting 8 AWG (655.0620)LF9,612$1.55$1.55$1.55$1.55$1.55$1.55
189Electrical service meter breaker pedestal (location) 01. STH 16 & main street (656.0201)EACH1$2,000.00$2,000.00$2,000.00$2,000.00$2,000.00$2,000.00
190Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH17$600.00$600.00$600.00$600.00$600.00$600.00
191Poles type 5-aluminum (657.0322)EACH17$2,250.00$2,250.00$2,250.00$2,250.00$2,250.00$2,250.00
192Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710)EACH17$650.00$650.00$650.00$650.00$650.00$650.00
193Luminaires utility LED B (659.1120)EACH17$250.00$250.00$250.00$250.00$250.00$250.00
194Lighting control cabinets 120/240 30-inch (659.2130)EACH1$7,800.00$7,800.00$7,800.00$7,800.00$7,800.00$7,800.00
195Sawing asphalt (690.0150)LF646$1.39$1.25$1.69$1.25$5.00$1.75
196Sawing concrete (690.0250)LF175$2.25$2.25$2.25$2.25$10.00$2.35
197Incentive strength concrete structures (715.0502)DOL2,928$1.00$1.00$1.00$1.00$1.00$1.00
198Incentive compressive strength concrete pavement (715.0720)DOL3,052.40$1.00$1.00$1.00$1.00$1.00$1.00
199Incentive iri ride (740.0440)DOL16,640$1.00$1.00$1.00$1.00$1.00$1.00
200Installing and maintaining bird deterrent system (station) 01. station 465+89 (999.2000.S)EACH1$0.01$0.01$0.01$0.01$0.01$0.01
201On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,100$5.00$5.00$5.00$5.00$5.00$5.00
202On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS6,480$5.00$5.00$5.00$5.00$5.00$5.00
203Special 01. culvert pipe liner grout (SPV.0035)CY38$450.00$450.00$400.00$450.00$450.00$450.00
204Special 01. 8" watermain tie in, station 10+00 (SPV.0060)EACH1$1,000.00$3,400.00$5,820.00$2,184.27$9,004.06$5,843.00
205Special 02. 12" watermain tie in, station 23+22 (SPV.0060)EACH1$1,000.00$3,800.00$5,820.00$2,572.12$6,606.36$5,843.00
206Special 03. 6" gate valve & box (SPV.0060)EACH3$3,200.00$2,400.00$2,771.00$2,394.00$3,168.59$2,782.00
207Special 04. 8" butterfly valve & box (SPV.0060)EACH1$8,700.00$4,700.00$5,961.00$7,848.40$6,385.14$5,984.00
208Special 05. 12" butterfly valve & box (SPV.0060)EACH4$10,900$6,600.00$8,375.00$10,245$6,824.85$8,408.00
209Special 06. water main fire hydrant (SPV.0060)EACH3$10,500$6,250.00$9,334.00$6,562.68$9,782.70$9,371.00
210Special 07. parapet cover plates (SPV.0060)EACH1$500.00$900.00$900.00$900.00$900.00$900.00
211Special 08. mowing mobilization (SPV.0060)EACH10$450.00$450.00$250.00$450.00$450.00$450.00
212Special 09. verify landmark reference monument (SPV.0060)EACH1$2,350.00$2,350.00$2,350.00$1,000.00$2,350.00$2,350.00
213Special 01. construction site maintenance - mowing (SPV.0075)HRS90$125.00$125.00$125.00$125.00$125.00$125.00
214Special 01. abandoning watermain in place by grouting (SPV.0090)LF640$20.00$7.00$24.00$18.54$13.28$24.00
215Special 02. water main pipe, PVC C-900, 12-inch (SPV.0090)LF660$135.00$123.50$133.00$229.32$164.25$134.00
216Special 03. water main pipe, PVC C-900, 8-inch (SPV.0090)LF4$95.00$118.00$324.00$241.40$266.11$328.00
217Special 04. water hydrant lead, PVC C-900, 6-inch (SPV.0090)LF33$88.00$100.00$89.00$205.43$160.41$90.00
218Special 05. steel casing pipe, 20- inch (SPV.0090)LF250$172.00$300.00$470.00$306.54$279.25$478.00
219Special 01. partial parapet removal (SPV.0165)SF11$75.00$2,500.00$2,500.00$2,500.00$2,500.00$2,500.00
220Special 01. abutment seat cleaning and sealing (SPV.0180)SY34$155.00$110.00$110.00$110.00$110.00$110.00
221Special 01. traffic control base course (SPV.0195)TON13,500$0.01$0.01$4.75$15.72$0.01$27.00
WisDOT contract 20250114002: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy