Salvaged rail, WisDOT 614.0920

Low bidders on WisDOT contracts carried a median of $3.50 per LF for this item, over the 24 months to 10 NOV 2026, across 26 low bids. Half of all 88 bids fell between $3.15 and $5.00.

Owner
Wisconsin DOT
Item
614.0920
Unit
LF
Data through
10 NOV 2026

WisDOT prints this item as “Salvaged Rail”.

$3.50Low bidder's median, per LF
$3.50Median of all bids, per LF
27Contracts in the window

By year of letting

Salvaged rail, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20222119$3.7058$3.77
20231312$2.6737$3.50
20241211$2.7542$3.00
20251212$3.3536$3.50
20261413$4.0048$4.00

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Dunn4$3.6213$4.00
Clark3$3.0010$3.21
Salvaged rail, WisDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
75 to 2926$4.00
294 to 4087$3.20
484 to 8036$3.75
962 to 2,0037$3.00
Salvaged rail, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Salvaged rail, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
10 NOV 202620261110009Iowa360$5.00$5.003Lunda Construction CompanyWisDOT
13 OCT 202620261013019Marathon395$2.98$2.985Sheet Piling Services LLCWisDOT
13 OCT 202620261013023Dunn408$4.00$4.003Sheet Piling Services LLCWisDOT
13 OCT 202620261013024Chippewa292$4.00$4.002Lunda Construction CompanyWisDOT
13 OCT 202620261013027Clark95$3.43$3.435Larson Construction Co., Inc.WisDOT
13 OCT 202620261013030Dunn321$3.15$3.156Haas Sons, Inc.WisDOT
15 SEP 202620260915019Oneida230$6.00$6.004Musson Bros., Inc.WisDOT
15 SEP 202620260915025Langlade686$3.50$3.504Pheifer Brothers Construction Co., Inc.WisDOT
15 SEP 202620260915031Douglas980$5.00$5.004Hoffman Construction CompanyWisDOT
10 MAR 202620260310026Marquette484$5.00$5.003D L Gasser ConstructionWisDOT
10 FEB 202620260210033Iron56n/a$10.003WisDOT
10 FEB 202620260210045Dunn170$4.00$4.003Zenith Tech., Inc. - WaukeshaWisDOT
13 JAN 202620260113001Dodge1,300$3.00$3.002Northeast Asphalt, IncWisDOT
13 JAN 202620260113048Dunn1,130$3.25$3.251Monarch Paving CompanyWisDOT
09 DEC 202520251209026Oconto536$4.00$4.003Northeast Asphalt, IncWisDOT
Latest WisDOT contracts carrying Salvaged rail

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy