WisDOT contract 20260210033 bid tabulation
T Kimball, Town Park Drive; W Br Montreal River Bridge B260047 (LOC STR, Iron County T Kimball, Town Park Drive). Let by Wisconsin DOT on February 10, 2026, Iron. 4 bids received.
- Owner
- Wisconsin DOT
- Letting
- 10 FEB 2026
- Pay items
- 64
- Data through
- 10 NOV 2026
3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 2 | Larson Construction Co., Inc. | $542,045 | +1.0% |
| 3 | Janke General Contractors, Inc. | $654,765 | +23% |
| 4 | Lunda Construction Company | $812,605 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Larson Construction Co., Inc. | 2. Janke General Contractors, Inc. | 3. Lunda Construction Company |
|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0205) | STA | 1 | $500.00 | $900.00 | $500.00 |
| 2 | Removing small pipe culverts (203.0100) | EACH | 1 | $500.00 | $900.00 | $500.00 |
| 3 | Removing structure over waterway debris capture (structure) 01. P-26- 0903 (203.0270) | EACH | 1 | $29,300 | $40,500 | $140,000 |
| 4 | Excavation common (205.0100) | CY | 199 | $17.32 | $42.00 | $20.00 |
| 5 | Excavation rock (205.0200) | CY | 5 | $1,200.00 | $500.00 | $500.00 |
| 6 | Excavation for structures bridges (structure) 01. B-26-0047 (206.1001) | EACH | 1 | $34,000 | $48,000 | $35,000 |
| 7 | Cofferdams (structure) 01. B-26- 0047 (206.5001) | EACH | 1 | $18,000 | $65,000 | $20,000 |
| 8 | Backfill structure type A (210.1500) | TON | 230 | $36.58 | $27.00 | $35.00 |
| 9 | Finishing roadway (project) 01. 9826-00-70 (213.0100) | EACH | 1 | $500.00 | $250.00 | $500.00 |
| 10 | Base aggregate dense 3/4-inch (305.0110) | TON | 115 | $33.69 | $42.00 | $60.00 |
| 11 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 345 | $26.56 | $23.00 | $38.00 |
| 12 | Tack coat (455.0605) | GAL | 43 | $10.81 | $10.81 | $10.81 |
| 13 | Asphaltic surface (465.0105) | TON | 140 | $154.32 | $154.32 | $154.32 |
| 14 | Concrete masonry bridges (502.0100) | CY | 153 | $858.00 | $912.00 | $850.00 |
| 15 | Protective surface treatment (502.3200) | SY | 195 | $4.00 | $5.50 | $5.00 |
| 16 | Bar steel reinforcement HS structures (505.0400) | LB | 2,580 | $2.00 | $2.30 | $1.30 |
| 17 | Bar steel reinforcement HS coated structures (505.0600) | LB | 23,470 | $2.00 | $2.30 | $1.35 |
| 18 | Railing tubular type M (513.4061) | LF | 106 | $450.00 | $448.00 | $298.00 |
| 19 | Rubberized membrane waterproofing (516.0500) | SY | 12 | $71.00 | $44.00 | $25.00 |
| 20 | Concrete staining multi-color (structure) 01. B-26-0047 (517.1015.S) | SF | 345 | $22.60 | $22.60 | $16.00 |
| 21 | Architectural surface treatment (structure) 01. B-26-0047 (517.1050.S) | SF | 345 | $15.00 | $22.00 | $7.40 |
| 22 | Culvert pipe class III-A 12-inch (520.3312) | LF | 36 | $120.00 | $140.00 | $150.00 |
| 23 | Riprap extra-heavy (606.0400) | CY | 40 | $125.00 | $140.00 | $70.00 |
| 24 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 110 | $9.10 | $18.00 | $40.00 |
| 25 | Salvaged rail (614.0920) | LF | 56 | $6.00 | $11.00 | $10.00 |
| 26 | Maintenance and repair of haul roads (project) 01. 9826-00-70 (618.0100) | EACH | 1 | $1,500.00 | $250.00 | $0.01 |
| 27 | Mobilization (619.1000) | EACH | 1 | $74,500 | $80,000 | $300,644 |
| 28 | Water (624.0100) | MGAL | 13 | $30.00 | $30.00 | $40.00 |
| 29 | Topsoil (625.0100) | SY | 160 | $8.90 | $12.00 | $10.00 |
| 30 | Mulching (627.0200) | SY | 200 | $1.10 | $4.00 | $5.00 |
| 31 | Silt fence (628.1504) | LF | 525 | $3.89 | $3.00 | $3.00 |
| 32 | Silt fence maintenance (628.1520) | LF | 1,050 | $0.10 | $0.01 | $0.03 |
| 33 | Mobilizations erosion control (628.1905) | EACH | 4 | $300.00 | $50.00 | $293.00 |
| 34 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $300.00 | $50.00 | $393.00 |
| 35 | Erosion mat class II type C (628.2027) | SY | 40 | $5.00 | $10.00 | $20.00 |
| 36 | Temporary ditch checks (628.7504) | LF | 50 | $16.50 | $15.00 | $9.00 |
| 37 | Fertilizer type B (629.0210) | CWT | 0.30 | $100.00 | $500.00 | $500.00 |
| 38 | Seeding mixture no. 20 (630.0120) | LB | 11 | $10.00 | $16.00 | $20.00 |
| 39 | Seeding temporary (630.0200) | LB | 6 | $5.00 | $7.00 | $20.00 |
| 40 | Seed water (630.0500) | MGAL | 6 | $100.00 | $25.00 | $50.00 |
| 41 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 4 | $130.00 | $200.00 | $150.00 |
| 42 | Signs type II reflective F (637.2230) | SF | 12 | $30.00 | $20.00 | $50.00 |
| 43 | Moving signs type II (638.2102) | EACH | 1 | $50.00 | $65.00 | $150.00 |
| 44 | Removing signs type II (638.2602) | EACH | 4 | $20.00 | $40.00 | $50.00 |
| 45 | Removing small sign supports (638.3000) | EACH | 4 | $20.00 | $40.00 | $50.00 |
| 46 | Moving small sign supports (638.4000) | EACH | 1 | $100.00 | $150.00 | $150.00 |
| 47 | Field office type B (642.5001) | EACH | 1 | $4,600.00 | $2,500.00 | $3,500.00 |
| 48 | Traffic control barricades type III (643.0420) | DAY | 725 | $0.45 | $0.45 | $0.45 |
| 49 | Traffic control warning lights type A (643.0705) | DAY | 1,125 | $0.10 | $0.10 | $0.10 |
| 50 | Traffic control signs (643.0900) | DAY | 485 | $0.45 | $0.45 | $0.45 |
| 51 | Traffic control (643.5000) | EACH | 1 | $2,930.00 | $2,930.00 | $2,930.00 |
| 52 | Geotextile type DF schedule A (645.0111) | SY | 60 | $8.50 | $3.50 | $3.50 |
| 53 | Geotextile type HR (645.0120) | SY | 80 | $4.00 | $4.50 | $5.00 |
| 54 | Construction staking subgrade (650.4500) | LF | 200 | $5.00 | $2.00 | $2.00 |
| 55 | Construction staking base (650.5000) | LF | 200 | $5.00 | $3.00 | $3.00 |
| 56 | Construction staking structure layout (structure) 01. B-26-0047 (650.6501) | EACH | 1 | $7,000.00 | $3,500.00 | $3,500.00 |
| 57 | Construction staking supplemental control (project) 01. 9826-00-70 (650.9911) | EACH | 1 | $1.00 | $1,500.00 | $1,500.00 |
| 58 | Construction staking slope stakes (650.9920) | LF | 200 | $5.00 | $3.00 | $3.00 |
| 59 | Sawing asphalt (690.0150) | LF | 14 | $10.00 | $24.00 | $2.95 |
| 60 | Incentive strength concrete structures (715.0502) | DOL | 918 | $1.00 | $1.00 | $1.00 |
| 61 | Maintaining bird deterrent system (station) 01. 10+00 (999.2005.S) | EACH | 1 | $1,500.00 | $3,900.00 | $0.01 |
| 62 | Special 01. moving boulders (SPV.0060) | EACH | 2 | $650.00 | $100.00 | $250.00 |
| 63 | Special 02. temporary construction access B-26-0047 (SPV.0060) | EACH | 1 | $39,500 | $61,000 | $10,000 |
| 64 | Special 01. infill riprap - B-26-0047 (SPV.0180) | SY | 50 | $40.00 | $39.00 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 10, 2026. Compiled by Mirage Metrics.