Pheifer Brothers Construction Co., Inc.: WisDOT bid record
Pheifer Brothers Construction Co., Inc. submitted 103 bids on Wisconsin DOT contracts in the data, from 11 JAN 2022 to 10 NOV 2026, and was the low bidder on 27 of them (26%). When it was not low, its total sat a median +11% above the low bid.
- Owner
- Wisconsin DOT
- Low bid volume
- $22,991,594
- Latest bid
- 10 NOV 2026
- Data through
- 10 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 47 | 9 | 19% |
| 2023 | 22 | 4 | 18% |
| 2024 | 17 | 6 | 35% |
| 2025 | 13 | 6 | 46% |
| 2026 | 4 | 2 | 50% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| Trempealeau | 9 | 2 | 22% |
| Dane | 8 | 2 | 25% |
| Buffalo | 7 | 0 | 0% |
| Langlade | 4 | 2 | 50% |
| Dunn | 4 | 0 | 0% |
| Fond Du Lac | 4 | 2 | 50% |
| Jackson | 4 | 2 | 50% |
| Clark | 4 | 1 | 25% |
| Brown | 3 | 2 | 67% |
| Green | 3 | 1 | 33% |
| Marathon | 3 | 1 | 33% |
| Vernon | 3 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Incentive strength concrete structures | 715.0502 | DOL | 103 | 103 (100%) | $1.00 | $1.00 |
| Concrete masonry bridges | 502.0100 | CY | 101 | 87 (86%) | $490.00 | $850.00 |
| Construction staking subgrade | 650.4500 | LF | 90 | 86 (96%) | $0.01 | $0.01 |
| Traffic control barricades type III | 643.0420 | DAY | 101 | 81 (80%) | $0.55 | $0.60 |
| Construction staking slope stakes | 650.9920 | LF | 89 | 81 (91%) | $1.00 | $1.00 |
| Traffic control signs | 643.0900 | DAY | 101 | 80 (79%) | $0.40 | $0.40 |
| Traffic control warning lights type A | 643.0705 | DAY | 97 | 77 (79%) | $0.12 | $0.12 |
| Traffic control | 643.5000 | EACH | 100 | 76 (76%) | $2,263.00 | $7,500.00 |
| Tack coat | 455.0605 | GAL | 87 | 76 (87%) | $7.60 | $3.85 |
| On-the-job training graduate at $5.00/HR | ASP.1T0G | HRS | 75 | 75 (100%) | $5.00 | $5.00 |
| On-the-job training apprentice at $5.00/HR | ASP.1T0A | HRS | 75 | 75 (100%) | $5.00 | $5.00 |
| Mobilization | 619.1000 | EACH | 101 | 72 (71%) | $39,427 | $136,364 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Lunda Construction Company | 94 | 24 of 94 |
| Sheet Piling Services LLC | 79 | 25 of 79 |
| Larson Construction Co., Inc. | 51 | 37 of 51 |
| Zenith Tech., Inc. - Waukesha | 43 | 8 of 43 |
| Radtke Contractors Inc. | 41 | 23 of 41 |
| Janke General Contractors, Inc. | 32 | 9 of 32 |
| Concrete Structures, Inc. | 23 | 17 of 23 |
| R.G. Huston Company, Inc. | 11 | 3 of 11 |
| Kraemer North America, LLC | 10 | 1 of 10 |
| Granite Construction Company | 8 | 2 of 8 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 10 NOV 2026 | 20261110004 | Rock | Town of Bradford, O Riley Road; Turtle Creek Bridge B-53-0390 (LOC STR, Rock County Town of Bradford, O'Riley Rd) | 2 of 6 | $2,141,298 | +2.0% |
| 15 SEP 2026 | 20260915005 | Juneau | T Orange, Schroeder Road; Ltl Lemonweir Rvr Bridge B-29-0169 (LOC STR, Juneau County T Orange, Schroeder Road) | 5 of 5 | $731,413 | +23% |
| 15 SEP 2026 | 20260915025 | Langlade | Antigo - Langlade; Wolf River Bridge B-34-0061 (STH 064, Langlade County Antigo - Langlade) | 1 of 4 | $3,378,276 | Low, 5.0% under the second |
| 10 FEB 2026 | 20260210038 | Jackson | T Hixton, Cain Road; N Br Trempealeau River Br B-27-0178 (LOC STR, Jackson County T Hixton, Cain Road) | 1 of 4 | $665,514 | Low, 1.0% under the second |
| 09 DEC 2025 | 20251209020 | Fond Du Lac | T Forest, Walnut Road; Sheboygan River Bridge (LOC STR, Fond du Lac County T Forest, Walnut Road) | 1 of 4 | $626,576 | Low, 1.0% under the second |
| 09 DEC 2025 | 20251209023 | Winnebago | T Wolf River, Apache Avenue; Alder Creek Bridge (LOC STR, Winnebago County T Wolf River, Apache Avenue) | 2 of 4 | $433,984 | +6.0% |
| 09 DEC 2025 | 20251209036 | Trempealeau | Whitehall - Strum; Elk Creek Bridge B-61-0293 (CTH D, Trempealeau County Whitehall - Strum) | 4 of 5 | $967,124 | +17% |
| 09 SEP 2025 | 20250909002 | Iowa | Town of Wyoming, Lake View Road; Sneed Creek Bridge B-25-0197 (LOC STR, Iowa County Town of Wyoming) | 4 of 4 | $419,112 | +20% |
| 08 APR 2025 | 20250408002 | Dane | 3672-00-70 | 1 of 5 | $1,446,013 | Low, 1.0% under the second |
| 08 APR 2025 | 20250408003 | Dane | T Medina - T York (CTH Tt); Maunesha River Bridge B-13-0913 (CTH TT, Dane County T Medina - T York (CTH TT)) | 3 of 6 | $883,574 | +5.0% |
| 11 MAR 2025 | 20250311029 | Winnebago | Oshkosh - Winchester; Brooks Road Overpass, R-70-0007 (USH 045, Winnebago County Oshkosh - Winchester) | 3 of 3 | $1,000,000 | +5.0% |
| 11 FEB 2025 | 20250211004 | La Crosse | Town of Barre - Town of Bangor; Russlan Coulee Crk Bridge B-32-0239 (CTH M, La Crosse County Town of Barre - Town of Bangor) | 1 of 2 | $1,218,683 | Low, 9.0% under the second |
| 11 FEB 2025 | 20250211040 | Waushara | Redgranite - CTH H; Little Silver Lake Creek, B-69-0054 (CTH E, Waushara, County Redgranite - CTH H) | 1 of 5 | $570,905 | Low, 2.0% under the second |
| 11 FEB 2025 | 20250211049 | Trempealeau | T Burnside, Filla Valley Road; Lyga Valley Creek Bridge B-61-0254 (LOC STR, Trempealeau County T Burnside, Filla Valley Road) | 1 of 4 | $465,475 | Low, 2.0% under the second |
| 11 FEB 2025 | 20250211052 | Clark | T Thorp, Pine Road; Goggle-Eye Creek Bridge B-10-0263 (LOC STR, Clark County T Thorp, Pine Road) | 4 of 5 | $423,914 | +15% |
| 14 JAN 2025 | 20250114022 | Kenosha | V Bristol, 128th St; Dutch Gap Canal Bridge P30-910 (CTH WG, Kenosha County V Bristol, 128th St) | 3 of 4 | $867,525 | +9.0% |
| 14 JAN 2025 | 20250114024 | Racine | T Burlington, Mt Tom Rd; Hoosier Creek Bridge P51-0911 (LOC STR, Racine County T Burlington, Mt Tom Rd) | 1 of 5 | $747,913 | Low, 2.0% under the second |
| 10 DEC 2024 | 20241210006 | Vernon | Town of Coon, Cornell Lane; Br Coon Creek Bridge B-62-0274 (LOC STR, Vernon County Town of Coon, Cornell Lane) | 2 of 6 | $902,850 | +3.0% |
| 10 DEC 2024 | 20241210019 | Fond Du Lac | T Forest, Poplar Road; Sheboygan River Bridge (LOC STR, Fond du Lac County T Forest, Poplar Road) | 1 of 4 | $458,947 | Low, 15% under the second |
| 10 DEC 2024 | 20241210021 | Iron | Manitowish - Hurley; Turtle River Bridge B-26-0016 (USH 051, Iron County Manitowish - Hurley) | 1 of 4 | $785,811 | Low, 2.0% under the second |
| 10 DEC 2024 | 20241210035 | Trempealeau | T Ettrick, Lien Lane; N Fork Beaver Creek Br B-61-0253 (LOC STR, Trempealeau County T Ettrick, Lien Lane) | 1 of 4 | $416,853 | Low, 2.0% under the second |
| 10 DEC 2024 | 20241210036 | Buffalo | STH 25 - STH 37; Lee Valley Creek Bridge B-06-0239 (CTH KK, Buffalo County STH 25 - STH 37) | 2 of 6 | $411,020 | +6.0% |
| 10 SEP 2024 | 20240910024 | St Croix | Baldwin - Clear Lake; Br Willow River Bridge B-55-0055 (USH 063, St. Croix County Baldwin - Clear Lake) | 3 of 5 | $493,076 | +11% |
| 10 SEP 2024 | 20240910027 | Dane | Sun Prairie - Watertown; Maunesha River Structure B-13-190 (STH 019, Dane County Sun Prairie - Watertown) | 1 of 3 | $149,018 | Low, 1.0% under the second |
| 11 JUN 2024 | 20240611006 | Walworth | T Linn - Lackey Lane; Over Lake Geneva Tributary P64-906 (LOC STR, Walworth County T Linn - Lackey Lane) | 3 of 5 | $448,350 | +12% |
How this record was read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Every bid counted here matched its published total to within one dollar; WisDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.