WisDOT contract 20260915025 bid tabulation
Antigo - Langlade; Wolf River Bridge B-34-0061 (STH 064, Langlade County Antigo - Langlade). Let by Wisconsin DOT on September 15, 2026, Langlade. 4 bids received; low bid $3,378,276 by Pheifer Brothers Construction Co., Inc..
- Owner
- Wisconsin DOT
- Letting
- 15 SEP 2026
- Pay items
- 124
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pheifer Brothers Construction Co., Inc. | $3,378,276 | Low |
| 2 | Sheet Piling Services LLC | $3,531,782 | +5.0% |
| 3 | Lunda Construction Company | $3,669,880 | +9.0% |
| 4 | Zenith Tech., Inc. - Waukesha | $4,023,062 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pheifer Brothers Construction Co., Inc. | 2. Sheet Piling Services LLC | 3. Lunda Construction Company | 4. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 3 | $500.00 | $500.00 | $500.00 | $500.00 |
| 2 | Grubbing (201.0205) | STA | 3 | $500.00 | $500.00 | $500.00 | $500.00 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 2 | $500.00 | $500.00 | $500.00 | $500.00 |
| 4 | Removing structure over waterway minimal debris (structure) 01. B-34- 0838 (203.0260) | EACH | 1 | $474,500 | $400,000 | $730,362 | $490,000 |
| 5 | Removing concrete pavement (204.0100) | SY | 210 | $25.50 | $25.50 | $25.50 | $25.50 |
| 6 | Removing asphaltic surface (204.0110) | SY | 2,160 | $12.75 | $12.75 | $12.75 | $12.75 |
| 7 | Removing asphaltic surface milling (204.0120) | SY | 230 | $18.20 | $18.20 | $18.20 | $18.20 |
| 8 | Removing curb & gutter (204.0150) | LF | 192 | $15.25 | $15.25 | $15.25 | $15.25 |
| 9 | Removing fence (204.0170) | LF | 120 | $5.00 | $5.00 | $5.00 | $5.00 |
| 10 | Removing concrete bases (204.0195) | EACH | 4 | $800.00 | $800.00 | $800.00 | $800.00 |
| 11 | Removing inlets (204.0220) | EACH | 1 | $125.00 | $125.00 | $125.00 | $125.00 |
| 12 | Removing storm sewer (size) 01. 18-inch (204.0245) | LF | 4 | $42.00 | $42.00 | $42.00 | $42.00 |
| 13 | Excavation common (205.0100) | CY | 260 | $24.15 | $24.15 | $24.15 | $24.15 |
| 14 | Excavation for structures bridges (structure) 01. B-34-0061 (206.1001) | EACH | 1 | $130,200 | $200,000 | $50,000 | $100,000 |
| 15 | Cofferdams (structure) 01. B-34- 0061 (206.5001) | EACH | 1 | $194,000 | $200,000 | $300,000 | $170,000 |
| 16 | Borrow (208.0100) | CY | 995 | $20.75 | $20.75 | $20.75 | $20.75 |
| 17 | Backfill structure type A (210.1500) | TON | 730 | $26.95 | $26.95 | $26.95 | $26.95 |
| 18 | Base aggregate dense 3/4-inch (305.0110) | TON | 120 | $32.50 | $32.50 | $32.50 | $32.50 |
| 19 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 2,734 | $24.75 | $24.75 | $24.75 | $24.75 |
| 20 | Concrete pavement 9-inch (415.0090) | SY | 167 | $186.16 | $133.50 | $133.50 | $186.16 |
| 21 | Concrete pavement approach slab (415.0410) | SY | 295 | $379.75 | $326.00 | $326.00 | $379.75 |
| 22 | Tack coat (455.0605) | GAL | 205 | $6.30 | $6.30 | $6.30 | $6.30 |
| 23 | Asphaltic surface (465.0105) | TON | 790 | $179.45 | $179.45 | $179.45 | $179.45 |
| 24 | Asphaltic surface temporary (465.0125) | TON | 8 | $295.00 | $295.00 | $295.00 | $295.00 |
| 25 | Asphaltic flumes (465.0315) | SY | 19 | $68.40 | $68.40 | $68.40 | $68.40 |
| 26 | Asphaltic rumble strips, transverse (465.0580) | SY | 17 | $195.50 | $195.50 | $195.50 | $195.50 |
| 27 | Concrete masonry bridges (502.0100) | CY | 623 | $900.00 | $975.00 | $750.00 | $1,325.00 |
| 28 | Protective surface treatment (502.3200) | SY | 751 | $5.30 | $5.00 | $2.00 | $4.25 |
| 29 | Pigmented surface sealer (502.3210) | SY | 350 | $13.00 | $5.00 | $3.00 | $14.00 |
| 30 | Prestressed girder type I 36W-inch (503.0137) | LF | 1,168 | $320.00 | $340.00 | $335.00 | $300.00 |
| 31 | Bar steel reinforcement HS structures (505.0400) | LB | 14,240 | $1.43 | $1.45 | $1.35 | $1.80 |
| 32 | Bar steel reinforcement HS coated structures (505.0600) | LB | 88,340 | $1.43 | $1.55 | $1.45 | $1.85 |
| 33 | Bearing pads elastomeric non- laminated (506.2605) | EACH | 28 | $110.00 | $160.00 | $150.00 | $150.00 |
| 34 | Steel diaphragms (structure) 01. B- 34-0061 (506.4000) | EACH | 24 | $1,500.00 | $1,400.00 | $1,200.00 | $1,400.00 |
| 35 | Treated lumber and timber (507.0200) | MBM | 2 | $15,950 | $15,000 | $4,450.00 | $17,000 |
| 36 | Polymer overlay (509.5100.S) | SY | 266 | $42.62 | $42.62 | $42.62 | $42.62 |
| 37 | Temporary shoring (structure) 01. B-34-0061 (511.1200) | SF | 733 | $42.00 | $45.00 | $20.00 | $165.00 |
| 38 | Railing steel type C2 (513.7011) | LF | 198 | $200.00 | $160.00 | $160.00 | $180.00 |
| 39 | Rubberized membrane waterproofing (516.0500) | SY | 30 | $68.00 | $25.00 | $25.00 | $68.00 |
| 40 | Apron endwalls for pipe arch sloped side drains steel 21X15- inch 4 to 1 (521.1705) | EACH | 3 | $1,750.00 | $1,750.00 | $1,750.00 | $1,750.00 |
| 41 | Pipe arch corrugated steel 21X15- inch (521.3721) | LF | 84 | $82.50 | $82.50 | $82.50 | $82.50 |
| 42 | Pre-boring unconsolidated materials (550.0010) | LF | 738 | $268.00 | $220.00 | $200.00 | $270.00 |
| 43 | Piling steel HP 12-inch X 53 LB (550.1120) | LF | 1,535 | $18.00 | $70.00 | $73.73 | $79.00 |
| 44 | Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553) | LF | 14 | $79.10 | $76.00 | $76.00 | $79.10 |
| 45 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 156 | $79.10 | $76.00 | $76.00 | $79.10 |
| 46 | Concrete barrier temporary precast delivered (603.8000) | LF | 1,050 | $15.29 | $15.29 | $15.29 | $35.00 |
| 47 | Concrete barrier temporary precast installed (603.8125) | LF | 1,300 | $8.68 | $8.68 | $8.68 | $4.25 |
| 48 | Anchoring concrete barrier temporary precast (603.8500) | LF | 1,300 | $11.25 | $11.25 | $11.25 | $11.00 |
| 49 | Riprap medium (606.0200) | CY | 6 | $155.00 | $155.00 | $155.00 | $155.00 |
| 50 | Riprap heavy (606.0300) | CY | 528 | $78.00 | $78.00 | $78.00 | $78.00 |
| 51 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 8 | $76.00 | $76.00 | $76.00 | $76.00 |
| 52 | Manhole covers type J (611.0530) | EACH | 1 | $875.00 | $875.00 | $875.00 | $875.00 |
| 53 | Inlet covers type F (611.0615) | EACH | 1 | $3,200.00 | $3,200.00 | $3,200.00 | $3,200.00 |
| 54 | Catch basins 4-FT diameter (611.1004) | EACH | 1 | $4,500.00 | $4,500.00 | $4,500.00 | $4,500.00 |
| 55 | Manholes 4-FT diameter (611.2004) | EACH | 1 | $4,500.00 | $4,500.00 | $4,500.00 | $4,500.00 |
| 56 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 206 | $6.50 | $6.50 | $6.50 | $6.50 |
| 57 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $380.00 | $500.00 | $250.00 | $300.00 |
| 58 | Guardrail mow strip asphalt (614.0396) | SY | 102 | $36.40 | $36.40 | $36.40 | $36.40 |
| 59 | Crash cushions temporary (614.0905) | EACH | 7 | $4,400.00 | $4,750.00 | $4,400.00 | $4,700.00 |
| 60 | Salvaged rail (614.0920) | LF | 686 | $3.50 | $3.50 | $3.50 | $3.50 |
| 61 | MGS guardrail 3 (614.2300) | LF | 163 | $27.00 | $27.00 | $27.00 | $27.00 |
| 62 | MGS thrie beam transition (614.2500) | LF | 156 | $89.00 | $89.00 | $89.00 | $89.00 |
| 63 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,213.00 | $3,213.00 | $3,213.00 | $3,213.00 |
| 64 | Mobilization (619.1000) | EACH | 1 | $207,290 | $311,333 | $355,660 | $395,000 |
| 65 | Topsoil (625.0100) | SY | 2,310 | $6.25 | $6.25 | $6.25 | $6.25 |
| 66 | Mobilizations erosion control (628.1905) | EACH | 3 | $193.00 | $193.00 | $193.00 | $193.00 |
| 67 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $253.00 | $253.00 | $253.00 | $253.00 |
| 68 | Erosion mat urban class I type B (628.2008) | SY | 2,320 | $2.00 | $2.00 | $2.00 | $2.00 |
| 69 | Turbidity barriers (628.6005) | SY | 350 | $44.00 | $44.00 | $44.00 | $44.00 |
| 70 | Inlet protection type C (628.7015) | EACH | 2 | $75.00 | $75.00 | $75.00 | $75.00 |
| 71 | Temporary ditch checks (628.7504) | LF | 36 | $9.00 | $9.00 | $9.00 | $9.00 |
| 72 | Culvert pipe checks (628.7555) | EACH | 6 | $30.00 | $30.00 | $30.00 | $30.00 |
| 73 | Fertilizer type B (629.0210) | CWT | 1.40 | $100.00 | $100.00 | $100.00 | $100.00 |
| 74 | Seeding mixture no. 20 (630.0120) | LB | 104 | $12.00 | $12.00 | $12.00 | $12.00 |
| 75 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 21 | $100.00 | $100.00 | $100.00 | $100.00 |
| 76 | Signs type II reflective F (637.2230) | SF | 26.70 | $30.00 | $30.00 | $30.00 | $30.00 |
| 77 | Moving signs type II (638.2102) | EACH | 23 | $150.00 | $150.00 | $150.00 | $150.00 |
| 78 | Removing signs type II (638.2602) | EACH | 5 | $25.00 | $25.00 | $25.00 | $25.00 |
| 79 | Removing small sign supports (638.3000) | EACH | 17 | $25.00 | $25.00 | $25.00 | $25.00 |
| 80 | Field office type C (642.5201) | EACH | 1 | $4,600.00 | $2,000.00 | $3,000.00 | $13,000 |
| 81 | Traffic control drums (643.0300) | DAY | 8,834 | $0.15 | $0.50 | $0.15 | $0.50 |
| 82 | Traffic control barricades type III (643.0420) | DAY | 1,392 | $0.50 | $1.00 | $0.50 | $1.00 |
| 83 | Traffic control warning lights type C (643.0715) | DAY | 2,884 | $0.15 | $0.20 | $0.15 | $0.20 |
| 84 | Traffic control signs (643.0900) | DAY | 7,836 | $0.20 | $0.80 | $0.20 | $0.80 |
| 85 | Temporary marking line paint 6- inch (643.3165) | LF | 50 | $9.95 | $100.00 | $9.95 | $0.50 |
| 86 | Temporary marking line removable tape 6-inch (643.3180) | LF | 10,219 | $2.25 | $1.98 | $2.25 | $1.98 |
| 87 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 153 | $7.50 | $5.94 | $7.50 | $5.94 |
| 88 | Temporary marking removable mask out tape 6-inch (643.3960) | LF | 1,465 | $2.75 | $3.00 | $2.75 | $3.00 |
| 89 | Temporary marking removable mask out tape 10-inch (643.3970) | LF | 190 | $3.75 | $6.00 | $3.75 | $6.00 |
| 90 | Traffic control (643.5000) | EACH | 1 | $35,750 | $2,000.00 | $35,750 | $2,000.00 |
| 91 | Temporary pedestrian barricade (644.1810) | LF | 44 | $9.50 | $5.00 | $9.50 | $5.00 |
| 92 | Geotextile type DF schedule A (645.0111) | SY | 160 | $5.75 | $5.75 | $5.75 | $5.75 |
| 93 | Geotextile type HR (645.0120) | SY | 800 | $6.75 | $6.75 | $6.75 | $6.75 |
| 94 | Geotextile type R (645.0130) | SY | 195 | $6.00 | $6.00 | $6.00 | $6.00 |
| 95 | Marking line epoxy 6-inch (646.2020) | LF | 1,462 | $3.00 | $2.60 | $3.00 | $2.60 |
| 96 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 1,164 | $8.00 | $4.60 | $8.00 | $4.60 |
| 97 | Marking stop line epoxy 18-inch (646.6120) | LF | 18 | $100.00 | $21.00 | $100.00 | $21.00 |
| 98 | Construction staking storm sewer (650.4000) | EACH | 2 | $55.55 | $55.55 | $55.55 | $250.00 |
| 99 | Construction staking subgrade (650.4500) | LF | 650 | $0.01 | $8.35 | $0.01 | $1.00 |
| 100 | Construction staking base (650.5000) | LF | 650 | $1.75 | $1.75 | $1.75 | $2.50 |
| 101 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 170 | $1.25 | $1.25 | $1.25 | $4.00 |
| 102 | Construction staking pipe culverts (650.6000) | EACH | 2 | $125.93 | $125.93 | $125.93 | $250.00 |
| 103 | Construction staking structure layout (structure) 01. B-34-0061 (650.6501) | EACH | 1 | $7,127.89 | $7,127.89 | $7,127.89 | $5,500.00 |
| 104 | Construction staking concrete pavement (650.7000) | LF | 125 | $1.50 | $1.50 | $1.50 | $4.00 |
| 105 | Construction staking supplemental control (project) 01. 9140-12-81 (650.9911) | EACH | 1 | $760.39 | $760.39 | $760.39 | $1,500.00 |
| 106 | Construction staking slope stakes (650.9920) | LF | 650 | $1.75 | $1.75 | $1.75 | $3.00 |
| 107 | Temporary traffic signals for bridges (structure) 01. B-34-0061 (661.0101) | EACH | 1 | $18,500 | $11,000 | $18,500 | $22,000 |
| 108 | Temporary traffic signals for bridges (structure) 02. B-34-0024 (661.0101) | EACH | 1 | $5,250.00 | $5,500.00 | $5,250.00 | $11,000 |
| 109 | Sawing asphalt (690.0150) | LF | 1,475 | $2.00 | $2.00 | $2.00 | $2.00 |
| 110 | Sawing concrete (690.0250) | LF | 86 | $3.00 | $3.00 | $2.95 | $3.00 |
| 111 | Incentive strength concrete structures (715.0502) | DOL | 3,738 | $1.00 | $1.00 | $1.00 | $1.00 |
| 112 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 113 | Installing and maintaining bird deterrent system (station) 01. 341+00 (999.2000.S) | EACH | 1 | $0.01 | $0.01 | $1,500.00 | $10,500 |
| 114 | Installing and maintaining climbing turtle exclusion fence (999.2100.S) | LF | 1,260 | $3.93 | $3.93 | $3.93 | $3.93 |
| 115 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 | $5.00 |
| 116 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,260 | $5.00 | $5.00 | $5.00 | $5.00 |
| 117 | Special 01. residential driveway traffic signal system (SPV.0045) | DAY | 252 | $25.00 | $65.00 | $22.42 | $65.00 |
| 118 | Special 02. waterway buoys (SPV.0045) | DAY | 2,496 | $4.00 | $0.15 | $0.25 | $6.50 |
| 119 | Special 01. temporary vehicle detection (SPV.0060) | EACH | 2 | $1,500.00 | $100.00 | $1,500.00 | $100.00 |
| 120 | Special 02. install state-supplied solar flashing beacon (SPV.0060) | EACH | 4 | $470.00 | $0.01 | $500.00 | $1,000.00 |
| 121 | Special 03. remove existing flashing beacon (SPV.0060) | EACH | 4 | $1,100.00 | $0.01 | $500.00 | $1,500.00 |
| 122 | Special 04. temporary portage path (SPV.0060) | EACH | 1 | $12,500 | $12,500 | $12,500 | $12,500 |
| 123 | Special 05. pipe joint collar external rubber 18-inch (SPV.0060) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 124 | Special 01. infill riprap B-34-0061 (SPV.0195) | TON | 287 | $10.00 | $10.00 | $10.00 | $10.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of September 15, 2026. Compiled by Mirage Metrics.