WisDOT contract 20250114022 bid tabulation
V Bristol, 128th St; Dutch Gap Canal Bridge P30-910 (CTH WG, Kenosha County V Bristol, 128th St). Let by Wisconsin DOT on January 14, 2025, Kenosha. 4 bids received; low bid $795,573 by Concrete Structures, Inc..
- Owner
- Wisconsin DOT
- Letting
- 14 JAN 2025
- Pay items
- 81
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Concrete Structures, Inc. | $795,573 | Low |
| 2 | Lunda Construction Company | $831,613 | +5.0% |
| 3 | Pheifer Brothers Construction Co., Inc. | $867,525 | +9.0% |
| 4 | Sheet Piling Services LLC | $933,938 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Concrete Structures, Inc. | 2. Lunda Construction Company | 3. Pheifer Brothers Construction Co., Inc. | 4. Sheet Piling Services LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 5 | $905.00 | $500.00 | $527.50 | $527.50 |
| 2 | Grubbing (201.0205) | STA | 5 | $310.00 | $500.00 | $211.00 | $211.00 |
| 3 | Removing structure over waterway remove debris (structure) 01. P-30- 0910 (203.0250) | EACH | 1 | $15,000 | $115,000 | $147,900 | $65,000 |
| 4 | Removing guardrail (204.0165) | LF | 290 | $5.00 | $5.00 | $5.00 | $5.00 |
| 5 | Excavation common (205.0100) | CY | 626 | $19.76 | $20.00 | $19.76 | $44.00 |
| 6 | Excavation for structures bridges (structure) 01. B-30-0153 (206.1001) | EACH | 1 | $10,000 | $6,250.00 | $80,100 | $18,000 |
| 7 | Borrow (208.0100) | CY | 311 | $43.00 | $5.00 | $43.00 | $11.00 |
| 8 | Backfill structure type A (210.1500) | TON | 200 | $20.00 | $25.00 | $43.00 | $43.00 |
| 9 | Finishing roadway (project) 01. 3745-05-70 (213.0100) | EACH | 1 | $500.00 | $1,000.00 | $1,500.00 | $500.00 |
| 10 | Base aggregate dense 3/4-inch (305.0110) | TON | 175 | $48.00 | $35.00 | $48.00 | $49.00 |
| 11 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,750 | $37.00 | $19.00 | $37.00 | $26.00 |
| 12 | Concrete pavement approach slab (415.0410) | SY | 164 | $291.17 | $250.00 | $224.34 | $291.17 |
| 13 | Tack coat (455.0605) | GAL | 88 | $3.00 | $2.50 | $3.00 | $3.00 |
| 14 | Asphaltic surface (465.0105) | TON | 348 | $85.75 | $102.00 | $85.75 | $85.75 |
| 15 | Concrete masonry bridges (502.0100) | CY | 310 | $753.00 | $600.00 | $500.00 | $950.00 |
| 16 | Protective surface treatment (502.3200) | SY | 362 | $7.00 | $5.00 | $4.60 | $2.50 |
| 17 | Pigmented surface sealer (502.3210) | SY | 76 | $10.00 | $8.00 | $12.00 | $3.00 |
| 18 | Bar steel reinforcement HS structures (505.0400) | LB | 6,260 | $1.10 | $1.05 | $1.30 | $1.10 |
| 19 | Bar steel reinforcement HS coated structures (505.0600) | LB | 45,790 | $1.30 | $1.20 | $1.40 | $1.20 |
| 20 | Bar steel reinforcement HS stainless structures 01. B-30-0153 (505.0800.S) | LB | 390 | $4.50 | $4.65 | $4.40 | $4.00 |
| 21 | Rubberized membrane waterproofing (516.0500) | SY | 18 | $37.00 | $25.00 | $59.00 | $18.00 |
| 22 | Concrete collars for pipe (520.8000) | EACH | 2 | $400.00 | $950.00 | $400.00 | $1,000.00 |
| 23 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 1,800 | $50.00 | $40.00 | $18.00 | $50.00 |
| 24 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 79 | $56.98 | $95.00 | $88.95 | $56.98 |
| 25 | Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590) | LF | 39 | $58.99 | $95.00 | $89.93 | $58.99 |
| 26 | Concrete surface drains (602.3010) | CY | 1.40 | $3,233.08 | $1,850.00 | $654.84 | $3,233.08 |
| 27 | Riprap medium (606.0200) | CY | 6 | $135.00 | $150.00 | $135.00 | $170.00 |
| 28 | Riprap heavy (606.0300) | CY | 100 | $80.00 | $110.00 | $140.00 | $140.00 |
| 29 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 180 | $9.00 | $10.00 | $20.00 | $9.00 |
| 30 | Pipe underdrain wrapped 8-inch (612.0408) | LF | 300 | $20.00 | $18.00 | $20.00 | $33.00 |
| 31 | Drain tile exploration (612.0700) | LF | 18 | $37.00 | $50.00 | $37.00 | $30.00 |
| 32 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $425.00 | $150.00 | $310.00 | $250.00 |
| 33 | Guardrail mow strip emulsified asphalt (614.0397) | SY | 144 | $40.10 | $28.00 | $40.10 | $40.10 |
| 34 | MGS thrie beam transition (614.2500) | LF | 157.60 | $98.00 | $99.00 | $98.00 | $98.00 |
| 35 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $4,000.00 | $5,000.00 | $4,000.00 | $4,000.00 |
| 36 | Maintenance and repair of haul roads (project) 01. 3745-05-70 (618.0100) | EACH | 1 | $500.00 | $500.00 | $1.00 | $1.00 |
| 37 | Mobilization (619.1000) | EACH | 1 | $42,300 | $89,129 | $40,907 | $67,863 |
| 38 | Water (624.0100) | MGAL | 16.70 | $70.00 | $50.00 | $70.00 | $50.00 |
| 39 | Salvaged topsoil (625.0500) | SY | 810 | $2.40 | $6.00 | $2.40 | $9.00 |
| 40 | Silt fence (628.1504) | LF | 1,510 | $2.50 | $2.50 | $2.50 | $2.50 |
| 41 | Silt fence maintenance (628.1520) | LF | 2,420 | $0.05 | $0.01 | $0.05 | $0.05 |
| 42 | Mobilizations erosion control (628.1905) | EACH | 3 | $250.00 | $250.00 | $250.00 | $250.00 |
| 43 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $300.00 | $250.00 | $300.00 | $300.00 |
| 44 | Erosion mat urban class I type B (628.2008) | SY | 810 | $1.85 | $2.00 | $1.85 | $1.85 |
| 45 | Turbidity barriers (628.6005) | SY | 180 | $65.00 | $65.00 | $65.00 | $65.00 |
| 46 | Fertilizer type B (629.0210) | CWT | 1.30 | $100.00 | $250.00 | $100.00 | $100.00 |
| 47 | Seeding mixture no. 30 (630.0130) | LB | 35 | $24.00 | $15.00 | $24.00 | $24.00 |
| 48 | Seeding temporary (630.0200) | LB | 50 | $7.50 | $15.00 | $7.50 | $7.50 |
| 49 | Seed water (630.0500) | MGAL | 32 | $75.00 | $10.00 | $75.00 | $75.00 |
| 50 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 4 | $65.00 | $150.00 | $65.00 | $65.00 |
| 51 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 1 | $80.00 | $175.00 | $80.00 | $80.00 |
| 52 | Signs type II reflective H (637.2210) | SF | 5 | $35.00 | $50.00 | $35.00 | $35.00 |
| 53 | Signs type II reflective F (637.2230) | SF | 12 | $35.00 | $50.00 | $35.00 | $35.00 |
| 54 | Removing signs type II (638.2602) | EACH | 5 | $50.00 | $50.00 | $50.00 | $50.00 |
| 55 | Removing small sign supports (638.3000) | EACH | 5 | $50.00 | $100.00 | $50.00 | $50.00 |
| 56 | Field office type B (642.5001) | EACH | 1 | $1,500.00 | $3,000.00 | $3,700.00 | $3,000.00 |
| 57 | Traffic control barricades type III (643.0420) | DAY | 1,738 | $0.45 | $0.45 | $1.00 | $0.35 |
| 58 | Traffic control warning lights type A (643.0705) | DAY | 3,476 | $0.10 | $0.10 | $0.11 | $0.10 |
| 59 | Traffic control signs (643.0900) | DAY | 15,010 | $0.20 | $0.20 | $0.30 | $0.25 |
| 60 | Traffic control covering signs type II (643.0920) | EACH | 4 | $75.00 | $75.00 | $40.00 | $50.00 |
| 61 | Traffic control signs PCMS (643.1050) | DAY | 14 | $45.00 | $45.00 | $15.00 | $50.00 |
| 62 | Traffic control (643.5000) | EACH | 1 | $10,925 | $10,925 | $9,400.00 | $7,300.00 |
| 63 | Geotextile type DF schedule A (645.0111) | SY | 96 | $9.00 | $6.00 | $3.00 | $5.00 |
| 64 | Geotextile type HR (645.0120) | SY | 216 | $6.00 | $6.00 | $6.00 | $6.00 |
| 65 | Marking line epoxy 4-inch (646.1020) | LF | 1,689 | $2.50 | $2.50 | $2.75 | $2.50 |
| 66 | Construction staking subgrade (650.4500) | LF | 562 | $2.00 | $2.00 | $2.00 | $2.00 |
| 67 | Construction staking base (650.5000) | LF | 562 | $2.00 | $2.00 | $2.00 | $2.00 |
| 68 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 118 | $4.75 | $4.75 | $4.75 | $4.75 |
| 69 | Construction staking structure layout (structure) 01. B-30-0153 (650.6501) | EACH | 1 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 70 | Construction staking concrete pavement (650.7000) | LF | 40 | $8.50 | $8.50 | $8.50 | $8.50 |
| 71 | Construction staking supplemental control (project) 01. 3745-05-70 (650.9911) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 72 | Construction staking slope stakes (650.9920) | LF | 562 | $1.85 | $1.85 | $1.85 | $1.85 |
| 73 | Sawing asphalt (690.0150) | LF | 48 | $16.50 | $2.95 | $2.95 | $2.95 |
| 74 | Incentive strength concrete structures (715.0502) | DOL | 1,860 | $1.00 | $1.00 | $1.00 | $1.00 |
| 75 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 76 | Installing and maintaining bird deterrent system (station) 01. 14+50 (999.2000.S) | EACH | 1 | $500.00 | $1.00 | $0.01 | $0.01 |
| 77 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 350 | $5.00 | $5.00 | $5.00 | $5.00 |
| 78 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 900 | $5.00 | $5.00 | $5.00 | $5.00 |
| 79 | Special 01. verify landmark reference monuments (SPV.0060) | EACH | 1 | $1,800.00 | $1,800.00 | $1,800.00 | $1,800.00 |
| 80 | Special 02. landmark reference monuments special (SPV.0060) | EACH | 1 | $1,800.00 | $1,800.00 | $1,800.00 | $1,800.00 |
| 81 | Special 01. select crushed material for travel corridor (SPV.0195) | TON | 20 | $50.00 | $100.00 | $60.00 | $88.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.