WisDOT contract 20261013024 bid tabulation
Elk Mound - Chippewa Falls; Chippewa River Br B090210 & B090209 (STH 029, Chippewa County Elk Mound - Chippewa Falls). Let by Wisconsin DOT on October 13, 2026, Chippewa. 2 bids received; low bid $2,818,858 by Lunda Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 13 OCT 2026
- Pay items
- 127
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lunda Construction Company | $2,818,858 | Low |
| 2 | Zenith Tech., Inc. - Waukesha | $3,271,947 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|
| 1 | Removing structure over waterway remove debris (structure) 01. B-09- 0209 (203.0250) | EACH | 1 | $25,000 | $75,000 |
| 2 | Removing structure over waterway debris capture (structure) 01. B-09- 0210 (203.0270) | EACH | 1 | $25,000 | $75,000 |
| 3 | Removing concrete pavement (204.0100) | SY | 430 | $35.00 | $35.00 |
| 4 | Removing asphaltic surface (204.0110) | SY | 2,790 | $3.60 | $3.60 |
| 5 | Removing guardrail (204.0165) | LF | 1,316 | $3.00 | $3.00 |
| 6 | Removing fence (204.0170) | LF | 100 | $3.00 | $3.00 |
| 7 | Removing surface drains (204.0190) | EACH | 6 | $635.00 | $635.00 |
| 8 | Removing inlets (204.0220) | EACH | 1 | $1,025.00 | $1,025.00 |
| 9 | Excavation common (205.0100) | CY | 7,022 | $14.40 | $14.40 |
| 10 | Excavation for structures bridges (structure) 01. B-09-0210 (206.1001) | EACH | 1 | $35,000 | $25,000 |
| 11 | Excavation for structures bridges (structure) 02. B-09-0209 (206.1001) | EACH | 1 | $35,000 | $25,000 |
| 12 | Backfill structure type A (210.1500) | TON | 1,665 | $15.00 | $15.00 |
| 13 | Finishing roadway (project) 01. 1050-02-73 (213.0100) | EACH | 1 | $1,000.00 | $1,000.00 |
| 14 | Base aggregate dense 3/4-inch (305.0110) | TON | 1,384 | $25.00 | $25.00 |
| 15 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 7,432 | $20.00 | $20.00 |
| 16 | Concrete pavement 8-inch (415.0080) | SY | 152 | $186.42 | $186.42 |
| 17 | Concrete pavement 10-inch (415.0100) | SY | 99 | $196.23 | $196.23 |
| 18 | Concrete pavement approach slab (415.0410) | SY | 244 | $330.08 | $330.08 |
| 19 | Rout and seal (415.6000.S) | LF | 5,272 | $1.74 | $1.74 |
| 20 | Drilled tie bars (416.0610) | EACH | 18 | $11.03 | $11.03 |
| 21 | Drilled dowel bars (416.0620) | EACH | 52 | $15.05 | $15.05 |
| 22 | Tack coat (455.0605) | GAL | 946 | $8.33 | $8.33 |
| 23 | Asphaltic surface (465.0105) | TON | 562 | $148.30 | $148.30 |
| 24 | Asphaltic surface temporary (465.0125) | TON | 2,171 | $94.42 | $94.42 |
| 25 | Asphaltic rumble strips, shoulder divided roadway (465.0510) | LF | 5,131 | $1.00 | $1.00 |
| 26 | Concrete masonry bridges (502.0100) | CY | 136 | $600.00 | $2,000.00 |
| 27 | Expansion device (502.3101) | LF | 99 | $350.00 | $475.00 |
| 28 | Expansion device modular (502.3111.S) | LF | 99 | $3,150.00 | $3,500.00 |
| 29 | Protective surface treatment (502.3200) | SY | 3,180 | $5.00 | $4.20 |
| 30 | Pigmented surface sealer reseal (502.3205) | SY | 545 | $8.00 | $22.50 |
| 31 | Pigmented surface sealer (502.3210) | SY | 20 | $8.00 | $15.00 |
| 32 | Adhesive anchors no. 6 bar (502.4206) | EACH | 410 | $20.00 | $40.00 |
| 33 | Bar steel reinforcement HS coated structures (505.0600) | LB | 23,030 | $2.35 | $2.50 |
| 34 | Preparation decks type 1 (509.0301) | SY | 171 | $175.00 | $220.00 |
| 35 | Preparation decks type 2 (509.0302) | SY | 73 | $200.00 | $300.00 |
| 36 | Cleaning decks to reapply concrete masonry overlay (509.0505.S) | SY | 3,094 | $10.00 | $20.00 |
| 37 | Joint repair (509.1000) | SY | 115 | $1,500.00 | $1,750.00 |
| 38 | Concrete surface repair (509.1500) | SF | 40 | $175.00 | $275.00 |
| 39 | Full-depth deck repair (509.2000) | SY | 15 | $500.00 | $0.01 |
| 40 | Concrete masonry deck repair (509.2100.S) | CY | 15 | $500.00 | $650.00 |
| 41 | Concrete masonry overlay decks (509.2500) | CY | 275 | $1,000.00 | $900.00 |
| 42 | Removing concrete masonry deck overlay (structure) 01. B-09-0210 (509.9005.S) | SY | 3,094 | $14.59 | $20.00 |
| 43 | Removing and resetting tubular railing (structure) 01. B-09-0209 (513.9006.S) | EACH | 1 | $10,000 | $2,500.00 |
| 44 | Adjusting floor drains (514.0900) | EACH | 4 | $200.00 | $475.00 |
| 45 | Rubberized membrane waterproofing (516.0500) | SY | 58 | $25.00 | $50.00 |
| 46 | Culvert pipe temporary 12-inch (520.2012) | LF | 247 | $32.00 | $32.00 |
| 47 | Culvert pipe temporary 15-inch (520.2015) | LF | 781 | $34.00 | $34.00 |
| 48 | Culvert pipe temporary 18-inch (520.2018) | LF | 56 | $40.00 | $40.00 |
| 49 | Concrete curb & gutter 4-inch sloped 30-inch type TBT (601.0584) | LF | 20 | $99.71 | $99.71 |
| 50 | Concrete curb & gutter 4-inch sloped 30-inch type TBTT (601.0586) | LF | 159 | $99.71 | $99.71 |
| 51 | Concrete surface drains (602.3010) | CY | 4.50 | $1,527.22 | $1,527.22 |
| 52 | Concrete barrier temporary precast delivered (603.8000) | LF | 1,307 | $9.99 | $9.99 |
| 53 | Concrete barrier temporary precast installed (603.8125) | LF | 1,307 | $6.47 | $6.47 |
| 54 | Anchoring concrete barrier temporary precast (603.8500) | LF | 1,307 | $11.25 | $5.00 |
| 55 | Riprap medium (606.0200) | CY | 20 | $120.00 | $120.00 |
| 56 | Inlet covers type MS (611.0642) | EACH | 2 | $600.00 | $600.00 |
| 57 | Inlets median 2 grate (611.3902) | EACH | 1 | $4,700.00 | $4,700.00 |
| 58 | Cover plates temporary (611.8120.S) | EACH | 7 | $180.00 | $180.00 |
| 59 | Barrier system grading shaping finishing (614.0010) | EACH | 3 | $1,150.00 | $1,150.00 |
| 60 | Crash cushions temporary (614.0905) | EACH | 4 | $4,750.00 | $4,750.00 |
| 61 | Salvaged rail (614.0920) | LF | 292 | $4.00 | $4.00 |
| 62 | Salvaged guardrail end treatments (614.0925) | EACH | 1 | $344.00 | $344.00 |
| 63 | MGS guardrail temporary (614.1000) | LF | 25 | $22.00 | $22.00 |
| 64 | MGS guardrail temporary thrie beam transition (614.1100) | LF | 39.40 | $88.00 | $88.00 |
| 65 | MGS guardrail temporary terminal eat (614.1200) | EACH | 1 | $3,200.00 | $3,200.00 |
| 66 | MGS guardrail 3 (614.2300) | LF | 1,375 | $29.00 | $29.00 |
| 67 | MGS thrie beam transition (614.2500) | LF | 236.40 | $92.00 | $92.00 |
| 68 | MGS guardrail terminal eat (614.2610) | EACH | 5 | $3,835.00 | $3,835.00 |
| 69 | MGS guardrail terminal type 2 (614.2620) | EACH | 1 | $3,300.00 | $3,300.00 |
| 70 | Fence chain link 8-FT (616.0208) | LF | 100 | $50.00 | $50.00 |
| 71 | Maintenance and repair of haul roads (project) 01. 1050-02-73 (618.0100) | EACH | 1 | $0.01 | $250.00 |
| 72 | Mobilization (619.1000) | EACH | 1 | $299,887 | $350,000 |
| 73 | Water (624.0100) | MGAL | 178 | $50.00 | $50.00 |
| 74 | Salvaged topsoil (625.0500) | SY | 15,671 | $2.00 | $2.00 |
| 75 | Mobilizations erosion control (628.1905) | EACH | 7 | $350.00 | $350.00 |
| 76 | Mobilizations emergency erosion control (628.1910) | EACH | 7 | $50.00 | $50.00 |
| 77 | Erosion mat urban class I type B (628.2008) | SY | 15,671 | $2.00 | $2.00 |
| 78 | Inlet protection type A (628.7005) | EACH | 9 | $106.00 | $106.00 |
| 79 | Temporary ditch checks (628.7504) | LF | 2,006 | $7.00 | $7.00 |
| 80 | Culvert pipe checks (628.7555) | EACH | 8 | $15.00 | $15.00 |
| 81 | Fertilizer type B (629.0210) | CWT | 14 | $95.00 | $95.00 |
| 82 | Seeding mixture no. 70A (630.0171) | LB | 91 | $95.00 | $95.00 |
| 83 | Seeding temporary (630.0200) | LB | 424 | $3.55 | $3.55 |
| 84 | Seeding nurse crop (630.0400) | LB | 179 | $5.00 | $5.00 |
| 85 | Seed water (630.0500) | MGAL | 117 | $1.00 | $1.00 |
| 86 | Delineator posts steel (633.0100) | EACH | 4 | $40.00 | $40.00 |
| 87 | Delineator reflectors (633.0500) | EACH | 4 | $11.00 | $11.00 |
| 88 | Delineators temporary (633.1100) | EACH | 90 | $18.00 | $18.00 |
| 89 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 1 | $90.00 | $90.00 |
| 90 | Moving signs type II (638.2102) | EACH | 7 | $119.00 | $119.00 |
| 91 | Moving small sign supports (638.4000) | EACH | 9 | $105.00 | $105.00 |
| 92 | Field office type B (642.5001) | EACH | 1 | $7,000.00 | $10,000 |
| 93 | Traffic control drums (643.0300) | DAY | 26,890 | $0.50 | $0.50 |
| 94 | Traffic control barricades type III (643.0420) | DAY | 1,639 | $1.00 | $1.00 |
| 95 | Traffic control flexible tubular marker posts (643.0500) | EACH | 153 | $28.00 | $28.00 |
| 96 | Traffic control flexible tubular marker bases (643.0600) | EACH | 153 | $7.00 | $7.00 |
| 97 | Traffic control warning lights type A (643.0705) | DAY | 1,816 | $0.12 | $0.12 |
| 98 | Traffic control warning lights type C (643.0715) | DAY | 3,115 | $0.15 | $0.15 |
| 99 | Traffic control connected arrow boards (643.0810) | DAY | 449 | $18.00 | $18.00 |
| 100 | Traffic control signs (643.0900) | DAY | 10,825 | $0.70 | $0.70 |
| 101 | Traffic control signs PCMS (643.1050) | DAY | 77 | $50.00 | $50.00 |
| 102 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 449 | $7.00 | $7.00 |
| 103 | Temporary marking line paint 6- inch (643.3165) | LF | 15,636 | $0.65 | $0.58 |
| 104 | Temporary marking line removable tape 6-inch (643.3180) | LF | 2,903 | $2.00 | $2.00 |
| 105 | Traffic control (643.5000) | EACH | 1 | $4,900.00 | $4,900.00 |
| 106 | Geotextile type HR (645.0120) | SY | 67 | $6.50 | $6.50 |
| 107 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 6,850 | $2.40 | $1.60 |
| 108 | Marking line grooved permanent tape 6-inch (646.2050) | LF | 1,520 | $8.00 | $9.00 |
| 109 | Marking removal line 4-inch (646.9000) | LF | 10,280 | $0.30 | $0.40 |
| 110 | Construction staking storm sewer (650.4000) | EACH | 6 | $300.00 | $300.00 |
| 111 | Construction staking subgrade (650.4500) | LF | 8,344 | $0.50 | $0.01 |
| 112 | Construction staking base (650.5000) | LF | 8,344 | $0.01 | $0.50 |
| 113 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 27 | $20.00 | $20.00 |
| 114 | Construction staking structure layout (structure) 01. B-09-0210 (650.6501) | EACH | 1 | $3,000.00 | $3,000.00 |
| 115 | Construction staking structure layout (structure) 02. B-09-0209 (650.6501) | EACH | 1 | $3,000.00 | $3,000.00 |
| 116 | Construction staking concrete pavement (650.7000) | LF | 148 | $20.00 | $20.00 |
| 117 | Construction staking supplemental control (project) 01. 1050-02-73 (650.9911) | EACH | 1 | $2,000.00 | $2,000.00 |
| 118 | Construction staking slope stakes (650.9920) | LF | 8,344 | $0.75 | $0.75 |
| 119 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 48 | $48.00 | $48.00 |
| 120 | Sawing asphalt (690.0150) | LF | 137 | $2.25 | $2.25 |
| 121 | Sawing concrete (690.0250) | LF | 252 | $2.75 | $2.75 |
| 122 | Incentive strength concrete structures (715.0502) | DOL | 2,508 | $1.00 | $1.00 |
| 123 | Installing and maintaining bird deterrent system (station) 01. 149+95.35 'EB' (999.2000.S) | EACH | 1 | $0.01 | $20,000 |
| 124 | Installing and maintaining climbing turtle exclusion fence (999.2100.S) | LF | 1,313 | $2.45 | $2.45 |
| 125 | Special 01. temporary inlet, median 1 grate (SPV.0060) | EACH | 5 | $4,600.00 | $4,600.00 |
| 126 | Special 02. temporary inlet covers type MS (SPV.0060) | EACH | 5 | $600.00 | $600.00 |
| 127 | Special 01. abutment seat cleaning and sealing (SPV.0180) | SY | 76 | $75.00 | $70.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of October 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.