WisDOT contract 20251209026 bid tabulation
Pittsfield - Chase; S County Line to CTH S (CTH C, Oconto County Pittsfield - Chase). Let by Wisconsin DOT on December 9, 2025, Oconto. 3 bids received; low bid $2,448,020 by Northeast Asphalt, Inc.
- Owner
- Wisconsin DOT
- Letting
- 09 DEC 2025
- Pay items
- 93
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Northeast Asphalt, Inc | $2,448,020 | Low |
| 2 | Relyco Plus, LLC | $2,472,616 | +1.0% |
| 3 | MCC, Inc. | $2,899,529 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Northeast Asphalt, Inc | 2. Relyco Plus, LLC | 3. MCC, Inc. |
|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0205) | STA | 6 | $525.00 | $750.00 | $750.00 |
| 2 | Grubbing (201.0220) | ID | 5 | $100.00 | $20.00 | $20.00 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 14 | $350.00 | $770.00 | $460.00 |
| 4 | Removing asphaltic surface (204.0110) | SY | 859 | $4.10 | $4.00 | $8.00 |
| 5 | Removing curb & gutter (204.0150) | LF | 86 | $15.00 | $15.00 | $8.55 |
| 6 | Removing surface drains (204.0190) | EACH | 6 | $125.00 | $250.00 | $525.00 |
| 7 | Excavation common (205.0100) | CY | 4,400 | $17.00 | $33.19 | $13.50 |
| 8 | Excavation marsh (205.0400) | CY | 200 | $18.00 | $35.20 | $19.00 |
| 9 | Borrow (208.0100) | CY | 618 | $0.01 | $28.55 | $26.00 |
| 10 | Backfill granular grade 2 (209.2100) | CY | 6,214 | $26.00 | $0.01 | $28.25 |
| 11 | Finishing roadway (project) 01. 9095-10-71 (213.0100) | EACH | 1 | $2,500.00 | $1,500.00 | $1,500.00 |
| 12 | Base aggregate dense 3/4-inch (305.0110) | TON | 3,265 | $14.30 | $29.35 | $23.50 |
| 13 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 5,345 | $17.60 | $22.22 | $15.50 |
| 14 | Breaker run (311.0110) | TON | 180 | $35.00 | $19.60 | $16.50 |
| 15 | Pulverize and relay (325.0100) | SY | 64,915 | $1.30 | $1.30 | $1.20 |
| 16 | QMP pulverize and relay compaction (374.1020.S) | SY | 64,915 | $0.10 | $0.10 | $0.25 |
| 17 | Drilled tie bars (416.0610) | EACH | 44 | $8.00 | $8.00 | $8.00 |
| 18 | Tack coat (455.0605) | GAL | 4,246 | $3.00 | $3.00 | $3.75 |
| 19 | Incentive density HMA pavement (460.2000) | DOL | 10,097 | $1.00 | $1.00 | $1.00 |
| 20 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 8,760 | $62.10 | $62.10 | $72.00 |
| 21 | HMA pavement 4 LT 58-34 S (460.5244) | TON | 7,008 | $70.30 | $70.30 | $78.50 |
| 22 | Asphaltic surface driveways and field entrances (465.0120) | TON | 144 | $152.00 | $152.00 | $150.00 |
| 23 | Asphaltic flumes (465.0315) | SY | 170 | $62.00 | $62.00 | $50.00 |
| 24 | Culvert pipe reinforced concrete class III 18-inch (522.0118) | LF | 136 | $112.00 | $138.00 | $230.00 |
| 25 | Culvert pipe reinforced concrete class III 24-inch (522.0124) | LF | 746 | $135.00 | $178.00 | $245.00 |
| 26 | Culvert pipe reinforced concrete class III 36-inch (522.0136) | LF | 58 | $220.00 | $263.00 | $350.00 |
| 27 | Culvert pipe reinforced concrete class V 12-inch (522.0512) | LF | 48 | $100.00 | $128.00 | $190.00 |
| 28 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 2 | $822.00 | $1,419.00 | $1,525.00 |
| 29 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 4 | $1,021.00 | $1,633.00 | $1,825.00 |
| 30 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 19 | $1,200.00 | $2,176.00 | $2,100.00 |
| 31 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 2 | $2,302.00 | $3,231.00 | $3,200.00 |
| 32 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 1,960 | $26.10 | $26.10 | $26.10 |
| 33 | Riprap medium (606.0200) | CY | 8 | $98.00 | $150.00 | $75.00 |
| 34 | Reconstructing inlets (611.0430) | EACH | 5 | $740.00 | $910.00 | $1,065.00 |
| 35 | Inlet covers type F (611.0615) | EACH | 5 | $2,348.00 | $1,724.00 | $885.00 |
| 36 | Salvaged rail (614.0920) | LF | 536 | $4.00 | $4.00 | $4.00 |
| 37 | MGS guardrail 3 (614.2300) | LF | 328 | $29.75 | $29.75 | $29.75 |
| 38 | MGS guardrail short radius (614.2350) | LF | 14 | $40.00 | $40.00 | $40.00 |
| 39 | MGS thrie beam transition (614.2500) | LF | 157.60 | $94.95 | $94.95 | $94.95 |
| 40 | MGS guardrail terminal eat (614.2610) | EACH | 5 | $3,333.00 | $3,333.00 | $3,333.00 |
| 41 | MGS guardrail short radius terminal (614.2630) | EACH | 1 | $2,455.00 | $2,455.00 | $2,455.00 |
| 42 | Maintenance and repair of haul roads (project) 01. 9095-10-71 (618.0100) | EACH | 1 | $1.00 | $0.01 | $1,000.00 |
| 43 | Mobilization (619.1000) | EACH | 1 | $246,870 | $320,000 | $298,500 |
| 44 | Water (624.0100) | MGAL | 248 | $25.00 | $0.01 | $66.00 |
| 45 | Topsoil (625.0100) | SY | 34,805 | $3.20 | $0.01 | $4.73 |
| 46 | Silt fence (628.1504) | LF | 4,160 | $1.75 | $1.75 | $1.75 |
| 47 | Silt fence maintenance (628.1520) | LF | 4,160 | $0.03 | $0.03 | $0.03 |
| 48 | Mobilizations erosion control (628.1905) | EACH | 5 | $193.00 | $193.00 | $193.00 |
| 49 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $395.00 | $395.00 | $395.00 |
| 50 | Erosion mat class I type A (628.2002) | SY | 33,735 | $0.98 | $0.98 | $0.98 |
| 51 | Erosion mat urban class I type B (628.2008) | SY | 1,070 | $2.25 | $2.25 | $2.25 |
| 52 | Inlet protection type C (628.7015) | EACH | 6 | $85.00 | $85.00 | $85.00 |
| 53 | Temporary ditch checks (628.7504) | LF | 40 | $8.00 | $8.00 | $8.00 |
| 54 | Culvert pipe checks (628.7555) | EACH | 52 | $25.00 | $25.00 | $25.00 |
| 55 | Rock bags (628.7570) | EACH | 300 | $7.15 | $7.15 | $7.15 |
| 56 | Fertilizer type B (629.0210) | CWT | 23 | $105.00 | $105.00 | $105.00 |
| 57 | Seeding mixture no. 30 (630.0130) | LB | 980 | $7.33 | $7.33 | $7.33 |
| 58 | Seeding mixture no. 40 (630.0140) | LB | 655 | $8.33 | $8.33 | $8.33 |
| 59 | Seeding temporary (630.0200) | LB | 950 | $5.33 | $5.33 | $5.33 |
| 60 | Seed water (630.0500) | MGAL | 615 | $5.00 | $5.00 | $5.00 |
| 61 | Markers culvert end (633.5200) | EACH | 28 | $75.00 | $75.00 | $75.00 |
| 62 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 20 | $95.00 | $95.00 | $95.00 |
| 63 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 29 | $105.00 | $105.00 | $105.00 |
| 64 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 5 | $109.00 | $109.00 | $109.00 |
| 65 | Signs type II reflective H (637.2210) | SF | 252.97 | $23.00 | $23.00 | $23.00 |
| 66 | Signs type II reflective SH (637.2220) | SF | 13.34 | $50.00 | $50.00 | $50.00 |
| 67 | Signs type II reflective F (637.2230) | SF | 101.91 | $23.00 | $23.00 | $23.00 |
| 68 | Removing signs type II (638.2602) | EACH | 80 | $25.00 | $25.00 | $25.00 |
| 69 | Removing small sign supports (638.3000) | EACH | 54 | $25.00 | $25.00 | $25.00 |
| 70 | Field office type C (642.5201) | EACH | 1 | $10,860 | $9,500.00 | $13,500 |
| 71 | Traffic control drums (643.0300) | DAY | 1,500 | $0.50 | $0.50 | $0.50 |
| 72 | Traffic control barricades type III (643.0420) | DAY | 4,125 | $0.55 | $0.55 | $0.75 |
| 73 | Traffic control warning lights type A (643.0705) | DAY | 4,500 | $0.15 | $0.15 | $0.15 |
| 74 | Traffic control signs (643.0900) | DAY | 13,575 | $0.50 | $0.50 | $0.65 |
| 75 | Traffic control signs PCMS (643.1050) | DAY | 14 | $90.00 | $90.00 | $85.00 |
| 76 | Traffic control (643.5000) | EACH | 1 | $3,500.00 | $3,500.00 | $8,500.00 |
| 77 | Geotextile type HR (645.0120) | SY | 22 | $8.00 | $10.00 | $6.90 |
| 78 | Marking line epoxy 6-inch (646.2020) | LF | 46,693 | $0.52 | $0.52 | $0.52 |
| 79 | Marking stop line epoxy 18-inch (646.6120) | LF | 79 | $15.00 | $15.00 | $15.00 |
| 80 | Locating no-passing zones (648.0100) | MI | 3.08 | $1,050.00 | $1,050.00 | $1,050.00 |
| 81 | Construction staking base (650.5000) | LF | 17,554 | $0.55 | $0.55 | $0.55 |
| 82 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 1,960 | $0.75 | $0.75 | $0.75 |
| 83 | Construction staking pipe culverts (650.6000) | EACH | 14 | $105.00 | $105.00 | $105.00 |
| 84 | Construction staking supplemental control (project) 01. 9095-10-71 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 |
| 85 | Construction staking slope stakes (650.9920) | LF | 17,554 | $0.76 | $0.76 | $0.76 |
| 86 | Public land reference monument verify and reset (680.0100) | EACH | 5 | $400.00 | $400.00 | $400.00 |
| 87 | Sawing asphalt (690.0150) | LF | 1,185 | $1.89 | $1.89 | $1.95 |
| 88 | Sawing concrete (690.0250) | LF | 66 | $2.75 | $2.75 | $2.95 |
| 89 | Incentive iri ride (740.0440) | DOL | 12,508 | $1.00 | $1.00 | $1.00 |
| 90 | Installing and maintaining climbing turtle exclusion fence (999.2100.S) | LF | 1,480 | $4.25 | $4.25 | $4.25 |
| 91 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 |
| 92 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,320 | $5.00 | $5.00 | $5.00 |
| 93 | Special 01. removing excess pulverized material (SPV.0180) | SY | 8,035 | $0.40 | $0.40 | $1.90 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of December 9, 2025. Compiled by Mirage Metrics.