MCC, Inc. submitted 19 bids on Wisconsin DOT contracts in the data, from 08 NOV 2022 to 11 AUG 2026, and was the low bidder on 8 of them (42%). When it was not low, its total sat a median +7.0% above the low bid.
- Owner
- Wisconsin DOT
- Low bid volume
- $17,446,535
- Latest bid
- 11 AUG 2026
- Data through
- 10 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 3 | 2 | 67% |
| 2023 | 2 | 0 | 0% |
| 2024 | 5 | 2 | 40% |
| 2025 | 5 | 2 | 40% |
| 2026 | 4 | 2 | 50% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| Outagamie | 7 | 4 | 57% |
| Brown | 6 | 3 | 50% |
| Waupaca | 2 | 0 | 0% |
| Manitowoc | 1 | 0 | 0% |
| Shawano | 1 | 1 | 100% |
| Winnebago | 1 | 0 | 0% |
| Oconto | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Incentive density HMA pavement | 460.2000 | DOL | 19 | 19 (100%) | $1.00 | $1.00 |
| On-the-job training graduate at $5.00/HR | ASP.1T0G | HRS | 18 | 18 (100%) | $5.00 | $5.00 |
| On-the-job training apprentice at $5.00/HR | ASP.1T0A | HRS | 18 | 18 (100%) | $5.00 | $5.00 |
| Construction staking base | 650.5000 | LF | 15 | 15 (100%) | $0.50 | $0.80 |
| Construction staking curb gutter and curb & gutter | 650.5500 | LF | 16 | 14 (88%) | $0.70 | $1.50 |
| Incentive iri ride | 740.0440 | DOL | 14 | 14 (100%) | $1.00 | $1.00 |
| Traffic control | 643.5000 | EACH | 19 | 13 (68%) | $4,500.00 | $7,500.00 |
| Traffic control barricades type III | 643.0420 | DAY | 19 | 13 (68%) | $0.65 | $0.60 |
| Traffic control warning lights type A | 643.0705 | DAY | 19 | 13 (68%) | $0.20 | $0.12 |
| Silt fence maintenance | 628.1520 | LF | 16 | 13 (81%) | $0.02 | $0.02 |
| Construction staking subgrade | 650.4500 | LF | 13 | 13 (100%) | $0.01 | $0.01 |
| Traffic control signs | 643.0900 | DAY | 19 | 11 (58%) | $0.60 | $0.40 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Northeast Asphalt, Inc | 11 | 7 of 11 |
| Vinton Construction Company | 10 | 4 of 10 |
| James Peterson Sons, Inc. | 10 | 0 of 10 |
| Peters Concrete Company | 9 | 4 of 9 |
| Michels Road & Stone, Inc. | 8 | 4 of 8 |
| Relyco Plus, LLC | 4 | 3 of 4 |
| Dorner Inc. | 2 | 1 of 2 |
| Musson Bros., Inc. | 2 | 0 of 2 |
| Mashuda Contractors, Inc. | 2 | 0 of 2 |
| Relyco, Inc. | 1 | 0 of 1 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 11 AUG 2026 | 20260811013 | Outagamie | Appleton - Black Creek; CTH S Intersection (STH 047, Outagamie County Appleton - Black Creek) | 3 of 4 | $2,714,985 | +8.0% |
| 10 MAR 2026 | 20260310022 | Brown | 4516-11-73 | 1 of 4 | $2,963,668 | Low, 0.0% under the second |
| 10 MAR 2026 | 20260310045 | Outagamie | T Buchanan, CTH N; CTH Kk to CTH Ce (CTH N, Outagamie County T. Buchanan, CTH N) | 1 of 4 | $4,804,549 | Low, 4.0% under the second |
| 10 FEB 2026 | 20260210023 | Brown | Ledgeview - Bellevue; CTH Mm - Continental Dr (USH 141, Brown County Ledgeview - Bellevue) | 2 of 2 | $2,394,960 | +24% |
| 09 DEC 2025 | 20251209026 | Oconto | Pittsfield - Chase; S County Line to CTH S (CTH C, Oconto County Pittsfield - Chase) | 3 of 3 | $2,899,529 | +18% |
| 13 MAY 2025 | 20250513024 | Winnebago | Oshkosh - Greenville; Larsen Rd Intersection (STH 076, Winnebago County Oshkosh - Greenville) | 3 of 5 | $1,809,402 | +4.0% |
| 13 MAY 2025 | 20250513026 | Outagamie | 6508-00-71 | 1 of 4 | $2,709,889 | Low, 1.0% under the second |
| 11 MAR 2025 | 20250311030 | Outagamie | C New London, House Rd; CTH S - STH 54 (LOC STR, Outagamie County C New London, House Rd CTH S - STH 54) | 1 of 2 | $409,526 | Low, 33% under the second |
| 11 FEB 2025 | 20250211038 | Waupaca | Winnebago Co Line - New London; STH 96 to Cut Off Road (CTH W, Waupaca County CTH W, Winnebago Co Line - New London) | 2 of 3 | $1,883,357 | +7.0% |
| 12 NOV 2024 | 20241112029 | Outagamie | Buchanan - East County Line; CTH Zz to Outagamie Road (CTH Z, Outagamie County Buchanan - East County Line) | 1 of 7 | $5,291,780 | Low, 2.0% under the second |
| 12 NOV 2024 | 20241112036 | Waupaca | Winnebago County Line - STH 110; CTH Ah to Lind Street (CTH H, Waupaca County Winnebago County Line - STH 110) | 5 of 8 | $1,333,237 | +9.0% |
| 13 FEB 2024 | 20240213020 | Brown | V Allouez, Libal Street; STH 172 to Kalb Ave (LOC STR, Brown County V Allouez, Libal Street) | 2 of 6 | $4,023,137 | +2.0% |
| 09 JAN 2024 | 20240109017 | Brown | V Bellevue, Allouez Avenue; Hazen Road - USH 141 (LOC STR, Brown County V Bellevue, Allouez Avenue) | 2 of 5 | $1,948,111 | +3.0% |
| 09 JAN 2024 | 20240109022 | Shawano | C Shawano, E Fifth Street; N Main Street to N Hamlin Street (LOC STR, Shawano County C Shawano, E Fifth Street) | 1 of 7 | $806,973 | Low, 5.0% under the second |
| 14 NOV 2023 | 20231114026 | Outagamie | STH 96 - STH 15; School Road Intersection (STH 076, Outagamie County STH 96 - STH 15) | 4 of 6 | $2,757,754 | +6.0% |
| 10 JAN 2023 | 20230110019 | Manitowoc | Maple Grove - North County Line; Taus Road To Mancal Road (CTH W, Manitowoc County Maple Grove - N County Line) | 4 of 4 | $3,265,737 | +19% |
| 08 NOV 2022 | 20221108038 | Brown | V Wrightstown, Alison Ct; Highland St - Clay St (LOC STR, Brown County V Wrightstown, Alison CT) | 1 of 2 | $174,205 | Low, 31% under the second |
| 08 NOV 2022 | 20221108040 | Outagamie | T Vandenbroek, Cth Jj; Cth N Intersection (CTH JJ, Outagamie County T Vandenbroek, CTH JJ) | 4 of 5 | $1,143,340 | +4.0% |
| 08 NOV 2022 | 20221108043 | Brown | V Pulaski, E Glenbrook Dr; Sth 32 To Great American Way (LOC STR, Brown County V Pulaski, E Glenbrook Dr) | 1 of 2 | $285,946 | Low, 14% under the second |
How this record was read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Every bid counted here matched its published total to within one dollar; WisDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.