| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Northeast Asphalt, Inc | $1,757,467 | Low |
| 2 | MCC, Inc. | $1,883,357 | +7.0% |
| 3 | Stark Pavement Corporation | $2,020,235 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Northeast Asphalt, Inc | 2. MCC, Inc. | 3. Stark Pavement Corporation |
|---|---|---|---|---|---|---|
| 1 | Removing small pipe culverts (203.0100) | EACH | 4 | $500.00 | $800.00 | $2,540.00 |
| 2 | Removing asphaltic surface (204.0110) | SY | 1,260 | $9.00 | $2.50 | $5.06 |
| 3 | Removing asphaltic surface butt joints (204.0115) | SY | 240 | $4.70 | $11.40 | $13.55 |
| 4 | Removing asphaltic surface milling (204.0120) | SY | 7,000 | $2.55 | $2.50 | $3.30 |
| 5 | Removing curb & gutter (204.0150) | LF | 20 | $25.00 | $40.00 | $15.00 |
| 6 | Removing inlets (204.0220) | EACH | 1 | $500.00 | $1,200.00 | $500.00 |
| 7 | Removing storm sewer (size) 01. 15-inch (204.0245) | LF | 8 | $50.00 | $50.00 | $90.00 |
| 8 | Prepare foundation for asphaltic paving (project) 01. 6838-00-70 (211.0101) | EACH | 1 | $69,750 | $0.01 | $29,885 |
| 9 | Finishing roadway (project) 01. 6838-00-70 (213.0100) | EACH | 1 | $2,350.00 | $3,775.00 | $6,560.00 |
| 10 | Base aggregate dense 3/4-inch (305.0110) | TON | 4,167 | $20.20 | $18.45 | $24.50 |
| 11 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 320 | $19.00 | $17.40 | $30.00 |
| 12 | Pulverize and relay (325.0100) | SY | 73,700 | $0.45 | $1.60 | $1.35 |
| 13 | QMP pulverize and relay compaction (374.1020.S) | SY | 73,700 | $0.10 | $0.13 | $0.16 |
| 14 | Drilled tie bars (416.0610) | EACH | 8 | $25.00 | $28.00 | $55.00 |
| 15 | Tack coat (455.0605) | GAL | 4,830 | $3.25 | $2.90 | $3.20 |
| 16 | Incentive density HMA pavement (460.2000) | DOL | 12,040 | $1.00 | $1.00 | $1.00 |
| 17 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 10,596 | $60.15 | $61.10 | $62.60 |
| 18 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 8,521 | $65.45 | $65.00 | $67.75 |
| 19 | Asphaltic surface (465.0105) | TON | 5 | $395.00 | $160.00 | $280.00 |
| 20 | Asphaltic surface driveways and field entrances (465.0120) | TON | 180 | $195.00 | $90.00 | $145.00 |
| 21 | Concrete collars for pipe (520.8000) | EACH | 1 | $1,000.00 | $1,450.00 | $500.00 |
| 22 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 94 | $157.00 | $210.25 | $163.00 |
| 23 | Culvert pipe reinforced concrete class IV 42-inch (522.0442) | LF | 46 | $302.00 | $375.00 | $280.00 |
| 24 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 4 | $1,667.00 | $1,620.00 | $1,850.00 |
| 25 | Apron endwalls for culvert pipe reinforced concrete 42-inch (522.1042) | EACH | 2 | $3,100.00 | $3,250.00 | $4,655.00 |
| 26 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (522.2424) | LF | 44 | $206.00 | $293.50 | $214.00 |
| 27 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624) | EACH | 2 | $2,200.00 | $2,525.00 | $2,650.00 |
| 28 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 20 | $150.00 | $125.00 | $145.00 |
| 29 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 8 | $126.00 | $165.00 | $72.00 |
| 30 | Inlet covers type H (611.0624) | EACH | 1 | $1,017.00 | $1,080.00 | $1,100.00 |
| 31 | Inlets 2X3-FT (611.3230) | EACH | 1 | $2,150.00 | $4,055.00 | $2,650.00 |
| 32 | Mobilization (619.1000) | EACH | 1 | $79,000 | $183,000 | $187,083 |
| 33 | Water (624.0100) | MGAL | 469 | $26.00 | $37.00 | $50.00 |
| 34 | Topsoil (625.0100) | SY | 800 | $4.00 | $20.00 | $8.75 |
| 35 | Silt fence (628.1504) | LF | 800 | $2.50 | $3.25 | $2.75 |
| 36 | Silt fence maintenance (628.1520) | LF | 800 | $0.01 | $0.05 | $0.10 |
| 37 | Mobilizations erosion control (628.1905) | EACH | 2 | $250.00 | $300.00 | $250.00 |
| 38 | Mobilizations emergency erosion control (628.1910) | EACH | 1 | $250.00 | $200.00 | $300.00 |
| 39 | Erosion mat urban class I type A (628.2006) | SY | 50 | $3.00 | $6.00 | $4.00 |
| 40 | Erosion mat class II type A (628.2021) | SY | 750 | $3.00 | $5.00 | $3.80 |
| 41 | Inlet protection type B (628.7010) | EACH | 1 | $100.00 | $75.00 | $65.00 |
| 42 | Inlet protection type C (628.7015) | EACH | 9 | $125.00 | $75.00 | $75.00 |
| 43 | Temporary ditch checks (628.7504) | LF | 40 | $12.00 | $9.50 | $13.50 |
| 44 | Culvert pipe checks (628.7555) | EACH | 22 | $15.00 | $15.00 | $20.00 |
| 45 | Rock bags (628.7570) | EACH | 22 | $15.00 | $15.00 | $15.00 |
| 46 | Fertilizer type B (629.0210) | CWT | 0.40 | $300.00 | $250.00 | $110.00 |
| 47 | Seeding mixture no. 30 (630.0130) | LB | 5 | $20.00 | $35.00 | $10.00 |
| 48 | Seeding mixture no. 40 (630.0140) | LB | 30 | $20.00 | $25.00 | $8.50 |
| 49 | Seed water (630.0500) | MGAL | 17 | $10.00 | $25.00 | $15.00 |
| 50 | Markers culvert end (633.5200) | EACH | 8 | $85.00 | $68.00 | $75.00 |
| 51 | Field office type B (642.5001) | EACH | 1 | $7,715.00 | $8,500.00 | $9,855.00 |
| 52 | Traffic control drums (643.0300) | DAY | 150 | $1.00 | $0.25 | $2.25 |
| 53 | Traffic control barricades type III (643.0420) | DAY | 2,246 | $1.00 | $0.40 | $1.05 |
| 54 | Traffic control warning lights type A (643.0705) | DAY | 4,086 | $0.15 | $0.09 | $0.33 |
| 55 | Traffic control signs (643.0900) | DAY | 11,074 | $0.85 | $0.55 | $0.55 |
| 56 | Traffic control covering signs type II (643.0920) | EACH | 2 | $30.00 | $150.00 | $128.00 |
| 57 | Traffic control signs PCMS (643.1050) | DAY | 30 | $40.00 | $35.00 | $66.00 |
| 58 | Traffic control (643.5000) | EACH | 1 | $2,780.00 | $1,850.00 | $4,300.00 |
| 59 | Marking line epoxy 4-inch (646.1020) | LF | 82,220 | $0.41 | $0.41 | $0.72 |
| 60 | Marking railroad crossing epoxy (646.5320) | EACH | 2 | $1,020.00 | $1,020.00 | $2,200.00 |
| 61 | Locating no-passing zones (648.0100) | MI | 4.28 | $550.00 | $550.00 | $600.00 |
| 62 | Construction staking storm sewer (650.4000) | EACH | 1 | $41.31 | $41.31 | $250.00 |
| 63 | Construction staking pipe culverts (650.6000) | EACH | 4 | $106.09 | $106.09 | $200.00 |
| 64 | Construction staking resurfacing reference (650.8000) | LF | 21,180 | $0.10 | $0.10 | $0.13 |
| 65 | Construction staking supplemental control (project) 01. 6838-00-70 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 |
| 66 | Sawing asphalt (690.0150) | LF | 1,022 | $1.39 | $1.95 | $1.75 |
| 67 | Sawing concrete (690.0250) | LF | 10 | $2.00 | $2.95 | $5.50 |
| 68 | Incentive iri ride (740.0440) | DOL | 17,240 | $1.00 | $1.00 | $1.00 |
| 69 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 | $5.00 |
| 70 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 |
| 71 | Special 01. replacing adjusting rings 12-inch and greater depth (SPV.0060) | EACH | 1 | $1,500.00 | $2,050.00 | $1,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.