Low bidders on WisDOT contracts carried a median of $1.45 per SY for this item, over the 24 months to 10 NOV 2026, across 37 low bids. Half of all 106 bids fell between $1.00 and $2.00.

Owner
Wisconsin DOT
Item
325.0100
Unit
SY
Data through
10 NOV 2026

WisDOT prints this item as “Pulverize and Relay”.

$1.45Low bidder's median, per SY
$1.48Median of all bids, per SY
38Contracts in the window

By year of letting

Pulverize and relay, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20223535$1.3784$1.35
20231010$1.2724$1.60
20241717$1.8043$1.51
20252222$1.4657$1.51
2026109$1.4128$1.27

Bid prices as published, not adjusted for inflation.

By quantity

Quantity (SY)Low bidsLow-bid median
1,660 to 13,7819$2.51
15,130 to 25,9409$1.35
29,236 to 52,7209$1.01
64,915 to 223,56010$1.35
Pulverize and relay, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Pulverize and relay, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
13 OCT 202620261013003Grant142,126$1.96$1.961Iverson Construction, A Div. of Mathy CoWisDOT
13 OCT 202620261013023Dunn800n/a$3.321Sheet Piling Services LLCWisDOT
11 AUG 202620260811016Green Lake25,000$1.50$1.932Northeast Asphalt, IncWisDOT
14 JUL 202620260714009Lincoln25,940$0.74$0.746James Peterson Sons, Inc.WisDOT
12 MAY 202620260512021Bayfield2,520$5.00$3.912Northern Interstate Construction, Inc.WisDOT
14 APR 202620260414008Vernon223,560$1.41$1.411Mathy Construction CompanyWisDOT
14 APR 202620260414024Trempealeau46,700$0.80$0.946Lepke Trucking and Excavating, LLCWisDOT
10 MAR 202620260310024Marinette193,656$1.07$1.383James Peterson Sons, Inc.WisDOT
10 FEB 202620260210018Kenosha18,710$3.66$3.212Musson Bros., Inc.WisDOT
10 FEB 202620260210034Langlade24,620$1.17$1.414Integrity Grading and Excavating, Inc.WisDOT
09 DEC 202520251209017Calumet76,180$1.50$1.322Northeast Asphalt, IncWisDOT
09 DEC 202520251209026Oconto64,915$1.30$1.303Northeast Asphalt, IncWisDOT
11 NOV 202520251111007Sauk15,130$1.62$1.913D L Gasser ConstructionWisDOT
11 NOV 202520251111013Racine11,902$3.35$2.902Stark Pavement CorporationWisDOT
11 NOV 202520251111023Portage21,550$0.31$1.574Gerke Excavating IncWisDOT
Latest WisDOT contracts carrying Pulverize and relay

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.