Ettrick - Jackson County Line; Osley Ln to Jackson County Line (CTH D, Trempealeau County Ettrick - Jackson County Line). Let by Wisconsin DOT on April 14, 2026, Trempealeau. 6 bids received; low bid $3,209,209 by Lepke Trucking and Excavating, LLC.
- Owner
- Wisconsin DOT
- Letting
- 14 APR 2026
- Pay items
- 130
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lepke Trucking and Excavating, LLC | $3,209,209 | Low |
| 2 | McCabe Construction, Inc. | $3,247,861 | +1.0% |
| 3 | Gerke Excavating Inc | $3,668,835 | +14% |
| 4 | A-1 Excavating LLC | $3,758,885 | +17% |
| 5 | James Peterson Sons, Inc. | $3,875,668 | +21% |
| 6 | Integrity Grading and Excavating, Inc. | $4,135,231 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lepke Trucking and Excavating, LLC | 2. McCabe Construction, Inc. | 3. Gerke Excavating Inc | 4. A-1 Excavating LLC | 5. James Peterson Sons, Inc. | 6. Integrity Grading and Excavating, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 39 | $205.13 | $10.10 | $749.65 | $11.00 | $10.00 | $995.00 |
| 2 | Clearing (201.0120) | ID | 78 | $102.57 | $10.10 | $48.19 | $11.00 | $10.00 | $35.00 |
| 3 | Grubbing (201.0205) | STA | 39 | $307.70 | $808.00 | $749.65 | $840.00 | $800.00 | $425.00 |
| 4 | Grubbing (201.0220) | ID | 78 | $153.85 | $20.20 | $48.19 | $21.00 | $20.00 | $24.00 |
| 5 | Roadside clearing (202.0105) | STA | 2 | $4,000.00 | $995.00 | $2,629.13 | $1.00 | $10.00 | $995.00 |
| 6 | Removing small pipe culverts (203.0100) | EACH | 24 | $208.34 | $393.04 | $706.25 | $700.00 | $200.00 | $1,110.00 |
| 7 | Removing structure (structure) 01. sta. 328+40, 4'X6' concrete box culvert (203.0220) | EACH | 1 | $5,000.00 | $2,098.41 | $2,754.11 | $5,500.00 | $2,996.00 | $15,000 |
| 8 | Removing structure (structure) 02. sta. 376+66, 60" CMCP (203.0220) | EACH | 1 | $5,000.00 | $856.09 | $1,408.26 | $2,600.00 | $1,626.00 | $1,720.00 |
| 9 | Removing structure (structure) 03. sta. 394+78, 75"X112" cmpa (203.0220) | EACH | 1 | $3,000.00 | $1,498.37 | $1,408.26 | $3,500.00 | $2,439.00 | $1,720.00 |
| 10 | Removing structure (structure) 04. sta. 423+58, 60" CMCP (203.0220) | EACH | 1 | $2,000.00 | $856.09 | $1,408.26 | $2,600.00 | $1,626.00 | $1,720.00 |
| 11 | Removing concrete pavement (204.0100) | SY | 35 | $57.15 | $9.79 | $29.73 | $10.00 | $16.38 | $18.60 |
| 12 | Removing delineators and markers (204.0180) | EACH | 38 | $14.25 | $14.25 | $14.25 | $15.00 | $14.25 | $14.25 |
| 13 | Removing (item description) 01. old foundation (204.9060.S) | EACH | 1 | $4,000.00 | $774.85 | $1,984.50 | $3,000.00 | $1,252.00 | $3,300.00 |
| 14 | Excavation common (205.0100) | CY | 17,500 | $10.00 | $11.90 | $10.98 | $12.00 | $13.96 | $16.30 |
| 15 | Excavation marsh (205.0400) | CY | 900 | $10.63 | $18.50 | $14.15 | $21.00 | $17.13 | $35.00 |
| 16 | Finishing roadway (project) 01. 7146-00-75 (213.0100) | EACH | 1 | $1,000.00 | $1,529.75 | $6,567.97 | $3,200.00 | $2,000.00 | $500.00 |
| 17 | Base aggregate dense 3/4-inch (305.0110) | TON | 5,050 | $25.31 | $18.91 | $21.47 | $25.00 | $23.43 | $24.00 |
| 18 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 21,700 | $19.43 | $17.62 | $17.46 | $19.00 | $17.55 | $23.65 |
| 19 | Base aggregate open-graded (310.0110) | TON | 480 | $35.00 | $38.17 | $34.63 | $29.00 | $28.40 | $21.60 |
| 20 | Select crushed material (312.0115) | CY | 1,360 | $51.76 | $40.34 | $33.96 | $46.00 | $64.65 | $47.00 |
| 21 | Pulverize and relay (325.0100) | SY | 46,700 | $0.80 | $1.00 | $1.30 | $0.75 | $0.88 | $1.25 |
| 22 | Tack coat (455.0605) | GAL | 2,500 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 23 | Incentive density HMA pavement (460.2000) | DOL | 7,170 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 6,300 | $87.26 | $87.26 | $87.26 | $92.00 | $87.26 | $87.26 |
| 25 | HMA pavement 4 LT 58-34 S (460.5244) | TON | 4,900 | $89.88 | $89.88 | $89.88 | $95.00 | $89.88 | $89.88 |
| 26 | Asphaltic surface driveways and field entrances (465.0120) | TON | 35 | $183.10 | $183.10 | $183.10 | $210.00 | $183.10 | $183.10 |
| 27 | Asphaltic flumes (465.0315) | SY | 55 | $65.20 | $65.20 | $65.20 | $80.00 | $65.20 | $65.20 |
| 28 | Asphaltic rumble strips, centerline (465.0560) | LF | 13,100 | $0.91 | $0.69 | $0.35 | $0.40 | $0.35 | $0.35 |
| 29 | Apron endwalls for culvert pipe steel 18-inch (521.1018) | EACH | 40 | $122.00 | $295.92 | $423.30 | $440.00 | $277.77 | $755.00 |
| 30 | Apron endwalls for culvert pipe steel 24-inch (521.1024) | EACH | 8 | $175.00 | $413.13 | $512.75 | $670.00 | $412.22 | $836.50 |
| 31 | Apron endwalls for culvert pipe steel 30-inch (521.1030) | EACH | 4 | $385.00 | $655.05 | $745.92 | $1,050.00 | $737.68 | $1,049.00 |
| 32 | Apron endwalls for culvert pipe steel 36-inch (521.1036) | EACH | 4 | $550.00 | $855.40 | $1,194.89 | $1,370.00 | $914.48 | $1,218.00 |
| 33 | Apron endwalls for culvert pipe steel 48-inch (521.1048) | EACH | 14 | $1,235.00 | $1,575.80 | $1,886.17 | $2,210.00 | $1,844.02 | $2,460.00 |
| 34 | Apron endwalls for pipe arch steel 28X20-inch (521.1228) | EACH | 8 | $160.00 | $358.15 | $449.60 | $610.00 | $351.80 | $1,389.00 |
| 35 | Apron endwalls for pipe arch steel 35X24-inch (521.1235) | EACH | 4 | $310.00 | $504.88 | $837.61 | $870.00 | $572.68 | $1,500.00 |
| 36 | Apron endwalls for pipe arch steel 42X29-inch (521.1242) | EACH | 2 | $485.00 | $699.87 | $1,017.53 | $1,190.00 | $743.59 | $1,664.00 |
| 37 | Apron endwalls for pipe arch steel 49X33-inch (521.1249) | EACH | 4 | $840.00 | $1,062.15 | $1,368.91 | $1,680.00 | $1,165.98 | $1,986.00 |
| 38 | Apron endwalls for pipe arch steel 57X38-inch (521.1257) | EACH | 8 | $1,005.00 | $1,304.95 | $2,104.24 | $2,100.00 | $1,546.41 | $2,175.00 |
| 39 | Apron endwalls for pipe arch steel 83X57-inch (521.1283) | EACH | 2 | $2,375.00 | $3,328.45 | $4,202.36 | $4,420.00 | $4,073.09 | $5,311.00 |
| 40 | Culvert pipe corrugated steel 18- inch (521.3118) | LF | 688 | $65.66 | $42.59 | $48.04 | $92.00 | $86.63 | $56.50 |
| 41 | Culvert pipe corrugated steel 24- inch (521.3124) | LF | 128 | $62.46 | $62.42 | $80.43 | $125.00 | $231.02 | $66.30 |
| 42 | Culvert pipe corrugated steel 30- inch (521.3130) | LF | 110 | $68.76 | $83.66 | $107.77 | $129.00 | $250.01 | $83.75 |
| 43 | Culvert pipe corrugated steel 36- inch (521.3136) | LF | 84 | $85.67 | $98.10 | $140.21 | $163.00 | $241.24 | $95.00 |
| 44 | Culvert pipe corrugated steel 48- inch (521.3148) | LF | 420 | $111.41 | $158.02 | $261.15 | $225.00 | $359.00 | $165.00 |
| 45 | Pipe arch corrugated steel 28X20- inch (521.3728) | LF | 230 | $34.25 | $71.96 | $90.62 | $94.00 | $231.79 | $104.00 |
| 46 | Pipe arch corrugated steel 35X24- inch (521.3735) | LF | 54 | $101.83 | $67.08 | $70.02 | $126.00 | $149.16 | $116.50 |
| 47 | Pipe arch corrugated steel 42X29- inch (521.3742) | LF | 50 | $83.46 | $110.33 | $172.66 | $171.00 | $278.55 | $126.60 |
| 48 | Pipe arch corrugated steel 49X33- inch (521.3749) | LF | 100 | $112.18 | $142.38 | $224.24 | $238.00 | $318.29 | $160.00 |
| 49 | Pipe arch corrugated steel 57X38- inch (521.3757) | LF | 220 | $120.59 | $155.60 | $264.55 | $230.00 | $344.38 | $246.00 |
| 50 | Pipe arch corrugated steel 83X57- inch (521.3783) | LF | 64 | $277.35 | $358.88 | $528.08 | $402.00 | $534.21 | $453.00 |
| 51 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 2 | $2,327.00 | $2,369.06 | $2,433.03 | $3,100.00 | $2,653.81 | $3,084.00 |
| 52 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 29X45-inch (522.2629) | EACH | 1 | $2,571.00 | $2,433.23 | $3,038.02 | $3,400.00 | $2,724.72 | $3,152.00 |
| 53 | Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553) | LF | 5,600 | $20.52 | $20.52 | $20.52 | $22.00 | $20.52 | $20.52 |
| 54 | Concrete sidewalk 4-inch (602.0405) | SF | 520 | $13.29 | $13.29 | $13.29 | $15.00 | $13.29 | $13.29 |
| 55 | Concrete driveway 6-inch (602.0810) | SY | 200 | $89.26 | $89.26 | $89.26 | $105.00 | $89.26 | $89.26 |
| 56 | Concrete surface drains (602.3010) | CY | 16 | $1,825.75 | $1,825.75 | $1,825.75 | $1,900.00 | $1,825.75 | $1,825.75 |
| 57 | Riprap heavy (606.0300) | CY | 1,950 | $48.00 | $64.46 | $70.00 | $70.00 | $85.82 | $78.00 |
| 58 | Storm sewer pipe reinforced concrete class IV 36-inch (608.0436) | LF | 100 | $219.40 | $211.22 | $304.37 | $297.00 | $269.84 | $242.50 |
| 59 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (608.2429) | LF | 48 | $250.85 | $231.77 | $563.27 | $335.00 | $327.56 | $269.20 |
| 60 | Inlets median 2 grate (611.3902) | EACH | 3 | $4,025.00 | $4,370.01 | $5,453.22 | $4,800.00 | $6,413.20 | $5,366.00 |
| 61 | Pipe underdrain 6-inch (612.0106) | LF | 6,550 | $3.10 | $8.87 | $11.19 | $8.00 | $7.50 | $9.20 |
| 62 | Apron endwalls for underdrain reinforced concrete 6-inch (612.0806) | EACH | 21 | $400.00 | $300.36 | $523.30 | $500.00 | $280.00 | $360.00 |
| 63 | Maintenance and repair of haul roads (project) 01. 7146-0075 (618.0100) | EACH | 1 | $1.00 | $100.00 | $0.01 | $500.00 | $500.00 | $500.00 |
| 64 | Mobilization (619.1000) | EACH | 1 | $317,392 | $212,975 | $395,740 | $315,000 | $372,150 | $414,000 |
| 65 | Water (624.0100) | MGAL | 440 | $54.00 | $44.12 | $19.91 | $30.00 | $50.00 | $40.00 |
| 66 | Salvaged topsoil (625.0500) | SY | 66,100 | $0.16 | $1.35 | $0.93 | $2.00 | $1.75 | $4.50 |
| 67 | Mulching (627.0200) | SY | 50,400 | $0.29 | $0.29 | $0.29 | $0.30 | $0.29 | $0.29 |
| 68 | Silt fence (628.1504) | LF | 14,900 | $1.72 | $1.72 | $1.72 | $1.80 | $1.72 | $1.72 |
| 69 | Silt fence maintenance (628.1520) | LF | 59,600 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 70 | Mobilizations erosion control (628.1905) | EACH | 6 | $200.00 | $200.00 | $200.00 | $210.00 | $200.00 | $200.00 |
| 71 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $100.00 | $100.00 | $100.00 | $105.00 | $100.00 | $100.00 |
| 72 | Erosion mat class I type B (628.2004) | SY | 16,000 | $0.99 | $0.99 | $0.99 | $1.05 | $0.99 | $0.99 |
| 73 | Soil stabilizer type B (628.6510) | ACRE | 11 | $450.00 | $450.00 | $450.00 | $470.00 | $450.00 | $450.00 |
| 74 | Inlet protection type A (628.7005) | EACH | 3 | $175.00 | $175.00 | $175.00 | $180.00 | $175.00 | $175.00 |
| 75 | Temporary ditch checks (628.7504) | LF | 1,390 | $5.75 | $5.75 | $5.75 | $6.00 | $5.75 | $5.75 |
| 76 | Stone ditch checks (628.7515.S) | CY | 20 | $40.00 | $165.61 | $171.28 | $100.00 | $141.41 | $98.00 |
| 77 | Culvert pipe checks (628.7555) | EACH | 390 | $9.50 | $9.50 | $9.50 | $10.00 | $9.50 | $9.50 |
| 78 | Rock bags (628.7570) | EACH | 630 | $9.50 | $9.50 | $9.50 | $10.00 | $9.50 | $9.50 |
| 79 | Fertilizer type B (629.0210) | CWT | 59 | $90.25 | $90.25 | $90.25 | $95.00 | $90.25 | $90.25 |
| 80 | Seeding mixture no. 20 (630.0120) | LB | 4,180 | $6.42 | $6.42 | $6.42 | $7.00 | $6.42 | $6.42 |
| 81 | Seeding mixture no. 60 (630.0160) | LB | 22 | $12.00 | $12.00 | $12.00 | $13.00 | $12.00 | $12.00 |
| 82 | Seeding temporary (630.0200) | LB | 510 | $3.60 | $3.60 | $3.60 | $4.00 | $3.60 | $3.60 |
| 83 | Seed water (630.0500) | MGAL | 2,100 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 84 | Markers row (633.5100) | EACH | 200 | $35.00 | $35.00 | $35.00 | $37.00 | $35.00 | $35.00 |
| 85 | Markers culvert end (633.5200) | EACH | 45 | $58.25 | $58.25 | $58.25 | $61.00 | $58.25 | $58.25 |
| 86 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 9 | $87.45 | $87.50 | $87.50 | $92.00 | $87.50 | $87.50 |
| 87 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 19 | $93.00 | $93.00 | $93.00 | $98.00 | $93.00 | $93.00 |
| 88 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 5 | $104.50 | $104.50 | $104.50 | $110.00 | $104.50 | $104.50 |
| 89 | Signs type II reflective H (637.2210) | SF | 58.34 | $18.40 | $18.40 | $18.40 | $20.00 | $18.40 | $18.40 |
| 90 | Signs type II reflective F (637.2230) | SF | 159.92 | $23.25 | $23.25 | $23.25 | $25.00 | $23.25 | $23.25 |
| 91 | Moving signs type II (638.2102) | EACH | 4 | $113.00 | $113.00 | $113.00 | $120.00 | $113.00 | $113.00 |
| 92 | Removing signs type II (638.2602) | EACH | 40 | $21.50 | $21.50 | $21.50 | $25.00 | $21.50 | $21.50 |
| 93 | Removing small sign supports (638.3000) | EACH | 29 | $21.50 | $21.50 | $21.50 | $25.00 | $21.50 | $21.50 |
| 94 | Field office type B (642.5001) | EACH | 1 | $12,000 | $7,500.00 | $10,667 | $8,400.00 | $15,000 | $12,500 |
| 95 | Traffic control drums (643.0300) | DAY | 250 | $1.00 | $1.00 | $1.00 | $1.10 | $1.00 | $1.00 |
| 96 | Traffic control barricades type III (643.0420) | DAY | 3,408 | $0.50 | $0.50 | $0.50 | $0.55 | $0.50 | $0.50 |
| 97 | Traffic control warning lights type A (643.0705) | DAY | 3,408 | $0.50 | $0.10 | $0.10 | $0.15 | $0.10 | $0.10 |
| 98 | Traffic control warning lights type C (643.0715) | DAY | 250 | $1.00 | $0.10 | $0.10 | $0.15 | $0.10 | $0.10 |
| 99 | Traffic control signs (643.0900) | DAY | 4,544 | $0.50 | $0.25 | $0.25 | $0.30 | $0.25 | $0.25 |
| 100 | Traffic control covering signs type II (643.0920) | EACH | 2 | $125.00 | $105.00 | $105.00 | $110.00 | $105.00 | $105.00 |
| 101 | Traffic control signs PCMS (643.1050) | DAY | 14 | $75.00 | $45.00 | $45.00 | $47.00 | $45.00 | $45.00 |
| 102 | Temporary marking line paint 6- inch (643.3165) | LF | 18,650 | $0.30 | $0.23 | $0.23 | $0.50 | $0.23 | $0.23 |
| 103 | Temporary marking line epoxy 6- inch (643.3170) | LF | 18,650 | $0.63 | $0.47 | $0.47 | $0.25 | $0.47 | $0.47 |
| 104 | Traffic control (643.5000) | EACH | 1 | $12,250 | $11,950 | $11,950 | $25,000 | $11,950 | $11,950 |
| 105 | Geotextile type DF schedule A (645.0111) | SY | 2,930 | $1.65 | $1.64 | $1.83 | $3.00 | $0.91 | $0.83 |
| 106 | Geotextile type HR (645.0120) | SY | 3,590 | $2.30 | $1.94 | $2.77 | $3.00 | $1.91 | $1.89 |
| 107 | Geotextile type R (645.0130) | SY | 260 | $1.95 | $3.35 | $3.20 | $4.00 | $2.03 | $1.93 |
| 108 | Geotextile type SR (645.0135) | SY | 2,000 | $1.68 | $2.83 | $2.91 | $4.00 | $2.23 | $2.00 |
| 109 | Marking line epoxy 6-inch (646.2020) | LF | 52,700 | $0.71 | $0.52 | $0.52 | $0.55 | $0.52 | $0.52 |
| 110 | Marking outfall epoxy (646.5520) | EACH | 21 | $73.00 | $53.91 | $53.91 | $57.00 | $53.91 | $53.91 |
| 111 | Locating no-passing zones (648.0100) | MI | 2.85 | $738.85 | $545.50 | $545.50 | $573.00 | $545.50 | $545.50 |
| 112 | Construction staking storm sewer (650.4000) | EACH | 6 | $83.34 | $300.00 | $300.00 | $315.00 | $300.00 | $300.00 |
| 113 | Construction staking subgrade (650.4500) | LF | 15,800 | $0.04 | $0.01 | $0.50 | $0.01 | $0.01 | $0.01 |
| 114 | Construction staking base (650.5000) | LF | 15,800 | $0.04 | $0.50 | $0.50 | $0.55 | $0.50 | $0.50 |
| 115 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 5,600 | $1.00 | $1.00 | $1.00 | $1.05 | $1.00 | $1.00 |
| 116 | Construction staking pipe culverts (650.6000) | EACH | 21 | $17.00 | $300.00 | $300.00 | $315.00 | $300.00 | $300.00 |
| 117 | Construction staking sidewalk (project) 01. 7146-00-75 (650.9500) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,050.00 | $1,000.00 | $2,500.00 |
| 118 | Construction staking supplemental control (project) 01. 7146-00-75 (650.9911) | EACH | 1 | $500.00 | $2,500.00 | $2,500.00 | $2,625.00 | $2,500.00 | $2,500.00 |
| 119 | Construction staking slope stakes (650.9920) | LF | 15,800 | $0.04 | $0.75 | $0.75 | $1.00 | $0.75 | $0.75 |
| 120 | Sawing asphalt (690.0150) | LF | 190 | $3.00 | $3.16 | $1.95 | $3.00 | $1.95 | $1.95 |
| 121 | Sawing concrete (690.0250) | LF | 20 | $5.00 | $6.31 | $2.95 | $6.00 | $2.95 | $2.95 |
| 122 | Incentive iri ride (740.0440) | DOL | 11,420 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 123 | Crack and damage survey (999.1501.S) | EACH | 2 | $4,000.00 | $2,777.50 | $2,750.00 | $500.00 | $6,579.00 | $2,750.00 |
| 124 | Maintaining bird deterrent system (station) sta. 328+14 (999.2005.S) | EACH | 1 | $200.00 | $1.00 | $1,505.83 | $1,000.00 | $1,500.00 | $2,753.00 |
| 125 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,500 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 126 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 990 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 127 | Special 01. inlet safety bars (SPV.0060) | EACH | 3 | $1,175.00 | $1,895.71 | $2,711.87 | $2,500.00 | $0.01 | $2,306.00 |
| 128 | Special 03. research and locate existing land parcel monuments (SPV.0060) | EACH | 6 | $950.00 | $125.00 | $125.00 | $140.00 | $125.00 | $125.00 |
| 129 | Special 04. verify and replace existing land parcel monuments (SPV.0060) | EACH | 6 | $950.00 | $125.00 | $125.00 | $140.00 | $125.00 | $125.00 |
| 130 | Special 01. pipe arch corrugated steel 112X75-inch (SPV.0090) | LF | 70 | $241.33 | $382.01 | $791.64 | $500.00 | $622.19 | $410.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.