Integrity Grading and Excavating, Inc.: WisDOT bid record
Integrity Grading and Excavating, Inc. submitted 98 bids on Wisconsin DOT contracts in the data, from 08 FEB 2022 to 10 NOV 2026, and was the low bidder on 10 of them (10%). When it was not low, its total sat a median +14% above the low bid.
- Owner
- Wisconsin DOT
- Low bid volume
- $135,918,869
- Latest bid
- 10 NOV 2026
- Data through
- 10 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 14 | 2 | 14% |
| 2023 | 19 | 1 | 5% |
| 2024 | 27 | 2 | 7% |
| 2025 | 18 | 2 | 11% |
| 2026 | 20 | 3 | 15% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| Dane | 28 | 3 | 11% |
| Marathon | 7 | 1 | 14% |
| La Crosse | 7 | 0 | 0% |
| Columbia | 4 | 1 | 25% |
| Wood | 4 | 0 | 0% |
| Vernon | 4 | 1 | 25% |
| St Croix | 3 | 0 | 0% |
| Sauk | 3 | 0 | 0% |
| Portage | 3 | 0 | 0% |
| Monroe | 3 | 0 | 0% |
| Forest | 3 | 2 | 67% |
| Jefferson | 2 | 1 | 50% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| On-the-job training graduate at $5.00/HR | ASP.1T0G | HRS | 85 | 85 (100%) | $5.00 | $5.00 |
| On-the-job training apprentice at $5.00/HR | ASP.1T0A | HRS | 85 | 85 (100%) | $5.00 | $5.00 |
| Construction staking subgrade | 650.4500 | LF | 88 | 81 (92%) | $0.01 | $0.01 |
| Incentive density HMA pavement | 460.2000 | DOL | 78 | 78 (100%) | $1.00 | $1.00 |
| Tack coat | 455.0605 | GAL | 87 | 74 (85%) | $3.40 | $3.85 |
| Incentive iri ride | 740.0440 | DOL | 74 | 74 (100%) | $1.00 | $1.00 |
| Traffic control signs | 643.0900 | DAY | 96 | 69 (72%) | $0.29 | $0.40 |
| Silt fence | 628.1504 | LF | 87 | 68 (78%) | $2.00 | $2.35 |
| Silt fence maintenance | 628.1520 | LF | 86 | 68 (79%) | $0.01 | $0.02 |
| Traffic control barricades type III | 643.0420 | DAY | 96 | 64 (67%) | $0.55 | $0.60 |
| Construction staking base | 650.5000 | LF | 82 | 64 (78%) | $0.94 | $0.80 |
| Traffic control warning lights type A | 643.0705 | DAY | 93 | 63 (68%) | $0.11 | $0.12 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| James Peterson Sons, Inc. | 53 | 38 of 53 |
| Hoffman Construction Company | 37 | 22 of 37 |
| Michels Road & Stone, Inc. | 30 | 22 of 30 |
| Zignego Company, Inc. | 28 | 19 of 28 |
| Rock Road Companies, Inc. | 26 | 21 of 26 |
| Gerke Excavating Inc | 23 | 17 of 23 |
| Parisi Construction, LLC | 22 | 12 of 22 |
| A-1 Excavating LLC | 22 | 10 of 22 |
| Mashuda Contractors, Inc. | 20 | 16 of 20 |
| Musson Bros., Inc. | 17 | 15 of 17 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 10 NOV 2026 | 20261110011 | Dane | C Madison, Mineral Point Road; USH 12 to High Point Road (LOC STR, Dane County C Madison, Mineral Point Road) | 3 of 4 | $4,307,421 | +22% |
| 10 NOV 2026 | 20261110017 | Walworth | 3170-09-70 | 3 of 5 | $18,916,329 | +1.0% |
| 11 AUG 2026 | 20260811005 | Vernon | 5865-02-64 | 5 of 5 | $8,830,433 | +24% |
| 11 AUG 2026 | 20260811014 | Marathon | Abbotsford - Wausau; CTH E South to STH 97, Wb (STH 029, Marathon County Abbotsford - Wausau) | 7 of 7 | $6,359,766 | +16% |
| 14 JUL 2026 | 20260714002 | Dane | 5845-16-76 | 4 of 5 | $39,803,589 | +18% |
| 14 JUL 2026 | 20260714003 | Columbia | V Cambria - STH 73 (CTH P); Kikkert Court to STH 73 (CTH P, Columbia County V Cambria - STH 73 (CTH P)) | 7 of 7 | $7,516,218 | +20% |
| 14 JUL 2026 | 20260714009 | Lincoln | Merrill - Rhinelander; STH 64 to Big Hay Meadow Creek (STH 017, Lincoln County Merrill - Rhinelander) | 6 of 6 | $8,623,888 | +20% |
| 12 MAY 2026 | 20260512007 | Sauk | 6130-01-72 | 3 of 3 | $58,869,420 | +29% |
| 14 APR 2026 | 20260414019 | Wood | Wisconsin Rapids - Plover; Biron/Plover Xing Approach Repairs (STH 054, Wood County Wisconsin Rapids - Biron/Plover Xing Approach Repairs) | 7 of 7 | $512,630 | +50% |
| 14 APR 2026 | 20260414024 | Trempealeau | Ettrick - Jackson County Line; Osley Ln to Jackson County Line (CTH D, Trempealeau County Ettrick - Jackson County Line) | 6 of 6 | $4,135,231 | +29% |
| 10 MAR 2026 | 20260310012 | Dane | 6085-02-76 | 4 of 6 | $2,917,308 | +17% |
| 10 MAR 2026 | 20260310025 | Wood | 1520-00-74 | 7 of 7 | $4,754,748 | +9.0% |
| 10 MAR 2026 | 20260310031 | Forest | 9260-00-71 | 4 of 5 | $2,980,971 | +20% |
| 10 FEB 2026 | 20260210003 | Dane | 5627-00-71 | 2 of 6 | $3,125,672 | +15% |
| 10 FEB 2026 | 20260210007 | Dane | Windsor - Bristol; Snowy Owl Court to CTH N (CTH V, Dane County Windsor - Bristol) | 8 of 8 | $5,849,752 | +16% |
| 10 FEB 2026 | 20260210034 | Langlade | C Antigo, 10th Avenue; Western Avenue to Clermont Street (LOC STR, Langlade County C Antigo, 10th Avenue) | 1 of 4 | $3,230,119 | Low, 13% under the second |
| 10 FEB 2026 | 20260210047 | Dane | 5845-16-73 | 1 of 7 | $41,615,733 | Low, 1.0% under the second |
| 13 JAN 2026 | 20260113006 | Jefferson | 3997-01-79 | 1 of 7 | $3,245,906 | Low, 1.0% under the second |
| 13 JAN 2026 | 20260113007 | Monroe | T Christiana - T Portland (CTH Pc); Vernon Co Line to STH 33 (CTH PC, Monroe County T. Christiana - T. Portland (CTH PC)) | 5 of 8 | $7,693,247 | +19% |
| 13 JAN 2026 | 20260113017 | La Crosse | STH 35 - CTH Sn (CTH Ot); STH 35 to CTH Sn (CTH OT, La Crosse County STH 35 - CTH SN (CTH OT)) | 4 of 6 | $2,864,256 | +9.0% |
| 09 DEC 2025 | 20251209002 | Dane | Dodgeville - Mount Horeb; CTH F Intersection (USH 018, Dane County Dodgeville - Mount Horeb) | 4 of 4 | $2,728,027 | +11% |
| 09 DEC 2025 | 20251209003 | Richland | 1640-03-73 | 7 of 7 | $10,930,401 | +10% |
| 09 DEC 2025 | 20251209007 | Dane | Mazomanie - Sun Prairie; Division Street to River Road (STH 019, Dane County Mazomaine - Sun Prairie) | 4 of 5 | $7,557,702 | +7.0% |
| 09 DEC 2025 | 20251209048 | Dane | Stoughton - Madison; Tower Road to Exchange Street (USH 051, Dane County Stoughton - Madison) | 9 of 9 | $6,544,641 | +17% |
| 11 NOV 2025 | 20251111002 | Dane | Madison - Cambridge; CTH W/Oak Park Road Intersection (USH 012, Dane County Madison - Cambridge) | 5 of 6 | $2,999,437 | +12% |
How this record was read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Every bid counted here matched its published total to within one dollar; WisDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.